| 1 | DETAIL SURVEY AS PER TENTATIVE ROUTE INCLUDES THE FOLLOWING MAJOR ACTIVITIESPegging of line route , providing of survey pillar at an interval of 3-4 Km line route with required jungle clearance for survey, profile preparation of approved route on graph sheet and marking of offset on either side of line , marking of side clearance for hills, sand dunes etc., as per specification and tower scheduling. |
| 2 | CHECK SURVEY AS PER APPROVED ROUTE OF LINE WHICH INCLUDES: -Rechecking of the line route as per approved profile, tower centre marking, pit marking, bisection of angle tower as per required at site. |
| 3 | Excavation:- Excavation excluding back filling, including shoring, shuttering, dewatering, etc. upto the required depth as per foundation specification/drawings. |
| 4 | (i) Any soil,soft rock other than hard rock |
| 5 | (ii) Hard rock (with blasting subject to permission or with out permission ) |
| 6 | SETTING OF TEMPLATE & STUB/ANCHOR BOLT:- (A) Setting of template & stub/ anchor bolt & removal after concreting, excluding cost of excavation and concreting but including back filling with excavated/ borrowed earth (with lead & lift) in layers with ramming andwatering as per specification. |
| 7 | (i) Towers including extension upto 9 Meters |
| 8 | Concreting:- Providing and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand, stone aggregate 20mm nominal size, water etc., preparing surfaces, shuttering, mixing, placing, ramming, curing, finishing as per specification and drawings. |
| 9 | (i) 1:4:8 |
| 10 | (ii) 1:3:6 Mix |
| 11 | (iii) 1:2:4 Mix |
| 12 | (iv) 1:1.5:3 Mix |
| 13 | STEEL REINFORCEMENT: Cutting ,Bending , Welding of joint if required , fixing and placing of steel reinforcement as per specification and drawing s including material. |
| 14 | EARTHING: |
| 15 | (A) Earthing of towers with pipe type earthing excluding the supply of pipes, wires, flats & connectors, but including coke / charcoal, etc., excavation, augering and backfilling in all types of soil. |
| 16 | ERECTION OF TOWERS:Erection of super structures including D-shakles, ACD, Hangers, U Bolts, Step bolts, danger plates, phase plate, number plate etc. Also including tack welding of bolts & nuts upto bottom cross arm/beam level including application of Zinc Rinch Paint. |
| 17 | (I) Erection of towers(with extensions upto 9 Meters) |
| 18 | Erection of substation structures including leveling, setting of stub & Tighting, Punching of Nuts& Bolts and tack welding upto beam level as per specification. |
| 19 | CONDUCTOR STRINGING:- (a) Stringing of ACSR Panther including hoisting of insulator string, laying, jointing & tensioning of conductor, clamping with Armour rods and fixing of vibration damper per route KM of the line. |
| 20 | (i) Single Conductor |
| 21 | Earth Wire Stringing (A) Stringing of Gavalinesed Steel stranded wire including laying , jointing and tensioning , clamping and fixing vibration damper and earth bond etc. |
| 22 | (i) one no 7/3.15mm galvanised wire |
| 23 | RIVETMENT OF TOWERS:- |
| 24 | (A) Providing & laying cement concrete including curing compaction etc. complete using stone aggregate 40 mm nominal size (Crusher broken) in foundation plinth using 1 cement : 5 sand : 10 Aggregate mix |
| 25 | (B) Random rubble stone massonary for rivetment in 1:5 cement sand mortat including providing and fixing 100 mm dia PCC drain pipe and raised and cut pointing on stone masonary in 1:3 cement sand mortar excluding excavation but including Back filling inside rivetment using excavated/ borrowed earth (with all lead & lift) in layers not exceeding 20cm in depth & consolidating each depositing layer by ramming and watering. |
| 26 | (C) Random rubble dry stone pitching including preparing surface etc. complete with raised & cut pointing in cement sand mortar 1:3 curing etc. |
| 27 | (D)Cement concrete coping grade 1:2:4 (1 Cement:2 Coarse sand:4 Graded stone aggregate) rounding off edges etc. but excluding the cost of nosing of step etc. complete for 75mm thik with 20mm thik nominal sige aggregate |
| 28 | LAND IDENTIFICATION AND COMPENSATION :- |
| 29 | (a) During Item No. 2 (Check Survey , as per GOR notification No. F.12(31) Energy/2024-02647 dated 05.11.2024 & Gazeet Notification dated 08.11.2024 and further amendment dated 23.07.2025 \\"policy for payment for in regard to right of way for transmission line Rajasthan \\" land identification for compensation of RoW\\" ROW Corridor marking identifcation of land owner , measurment of area for various land owner under ROW corridor netc. as per specified scope of work a per Annuxer - A |
| 30 | (b) Preparation of case for land compensation as issued vide Gazeet Notification No. F.12(31) Energy/2024-02647 dated 05.11.2024 & Gazeet Notification dated 08.11.2024 and its further amendment dated 23.07.2025 after collection application DLC rate for disbursement of land compensation to land owner a sper specifie scope of work as per Annuxer - A Please Enable Macros to View BoQ information |