| 1 | SCHEDULE G-1- Construction of RCC Overhead Tank |
| 2 | Construction of OHT:Design, Submission of vetted design and drawing from IIT, Supply of all materials, site clearance labour, T&P etc. required for construction of INTZ type RCC Overhead Tank with minimum freeboard of 15 cm including Ventilator and Water Level Indicator, Lightning Conductor, C.I. D/F Vertical Pipes (Inlet Pipe-1 No., Outlet Pipe-2 No., Overflow Pipe-1 No. & Washout Pipe-1 No.), Duck Foot Bend, Puddle Collars and Bell Mouths, DI/D/F Sluice Valves with actuartors on Inlet, Outlet & Washout Pipes and Sluice Valve Chambers, Bypass Arrangement of OHT, Flooring with Apron & Drain (minimum 100 mm thick PCC of 1:2:4 & 100 mm thick RCC of 1:1.5:3 with nominal reinforcement), the construction of a 30x30 cm cement concrete (CC) drain with an internal wall thickness of 100 mm, over a 60 cm wide plain cement concrete (PCC) base of 100 mm thickness in 1:2:4 mix, for rain water disposal of campus, shall be carried out for a minimum length of 200 meters along the boundary wall of the campus up to the disposal point, Floor Level shall be 70 cm above the Finished Ground Level of whole Campus (The finished Ground level of campus shall be kept 30 cm above the nearest approach road) including supply of earth to fill the whole campus according to the formation level(floor) of OHT, Three Coats of Apex Painting(Painting through spray is prohibited) over One Coat Primer of Approved Colour after Finishing of RCC Surface with Grinder, Repair of Pinholes, Unevenness (contractor to ensure smooth surface free from any marks and roughness), supply and fixing of four number 60 Watt solar light system (with dry battery) at the height of second brace of the OHT near stair case and main gate, Railings – G.I. Pipe Railing around Staircase (both sides), Balcony & Top Dome Periphery, S.S. Ladder from Opening of Top Dome to Bottom Dome, Staircase (Separate Two-Column Based RCC Staircase including Escape Channel of 20 m Length, Box-Type Enclosure at the Entrance of the Staircase having Locking Arrangements, and 1.20 m Wide Balcony), Food Grade Epoxy Coating on Inside Surface Area of Water Container after Successful Testing for Water Tightness as specified as per Tender Document for Following Capacity and Staging mentioned as per BOQ. Item also include earthwork, brickwork, pumping out of water/mud/sewage, 1 no. toilet (with Saptik tank and proper flushing system) required activity necessary for construction of OHT and its appurtenant structures. Cost Included in Item 1.03 & 1.04 |
| 3 | For bidding purposes, the bearing capacity of soil shall be considered as 7.0 t/sq.m. Working design shall be based on the SBC determined (The depth of bore hole shall be two times of proposed dia meter raft foundation of OHT) after soil investigation / 7.0 tonne/sq.m. The depth of foundation is minimum 3.0 m from existing ground level on raft foundation or pile-cum-raft foundation or at more depth based on the design of the tank, for which no extra claim shall be entertained. The height of columns shall be desided by considering the natural ground level and formation level of floor of OHT. The staging shall be accounted between floor level to bottom ring beam.Note: The bid price of Overhead Tanks is to be submitted considering net safe allowable bearing capacity as 7.0 t/m², keeping the minimum foundation depth to be 3 m below the existing ground level at the site of work. The successful bidder will be required to investigate the soil bearing capacity. If net safe allowable bearing capacity is found to be equivalent to or more than 7.0 t/m², the design of OHT will be based on 7.0 t/m² capacity. However, in case the net safe allowable bearing capacity is found to be below 7.0 t/m², then the design of OHT will be based on the actual bearing capacity, adopting raft foundation or raft-cum-pile foundation.Cost Included in Item 1.03 & 1.04 |
| 4 | For Zone 2 -Capacity - 2000 KL Staging -22m a. C.I D/f pipe inlet - 1 nos of 200 mm diab. C.I D/f pipe outlet - 2 nos of 350mm diac. C.I D/f pipe overflow - 1 nos of 400mm diad. C.I D/f pipe washout - 1 nos of 100mm dia |
| 5 | For Zone -3Capacity - 1450 KL Staging -22m a. C.I D/f pipe inlet - 1 nos of 200 mm diab. C.I D/f pipe outlet - 2 nos of 300mm dia & 350 mm diac. C.I D/f pipe overflow - 1 nos of 400mm diad. C.I D/f pipe washout - 1 nos of 100mm dia |
| 6 | SCHEDULE G-2 (Construction of pump house, chlorinating room, MCS room, Boundary Wall with gate and approach road etc. works) |
| 7 | Design, soil investigation, submission of vetted structural designs and drawings, supply of all materials, labour, Provide all materials, labour, T&P etc. complete for construction of Pump House size 3.6 x 3.0 x 3.0 m, Chlorinating Room size 1.8 x 2.5 x 3.0 m as per type design and specifications provided in the tender document. The structure will be RCC frame structure providing separate beams at plinth and lintel level. The reinforcement of RCC base slab of the by-pass chamber will be connected with the plinth beam to ensure its stability.There is no fixed minimum depth criterion for the foundation of the pump house. The depth of foundation shall be decided based on firm soil at the time of structural design. Column footings shall extend from the natural ground level down to the formation level of the pump house, as determined by the Engineer-in-Charge, ensuring adequate support and stability. A minimum 230 mm thick brick wall shall be constructed from the footings up to the formation level of the pump house. The column footings shall be left empty and shall not be filled with the earth. The parapet wall above the pump house shall be a minimum of 60 cm high, constructed with 230 mm thick brickwork. For installing the pumping plant, MS girders shall be provided above the pump house, supported on a minimum 450 mm thick brick wall of 1.5 m height. The I-sections shall be properly cast in concrete to ensure structural stability. An MS door of size 1.5 m × 2.1 m height shall be provided. Grills (Fabricated with 10mm square bars) shall be provided on the outside of all windows and ventilators. Minimum 05 nos. MS windows (size 0.6m x 1.5m) shall be designed to open inward into the pump house. The minimum thickness of MS sheet used for the main door and window panels shall be 3 mm. |
| 8 | The floor of the Pump House shall be constructed by providing 300 mm sand filling over compacted earth and thereafter 100 mm thick 1:2:4 PCC and 100 mm thick RCC with minimum reinforcement. The floor of the pump house shall be finished with 40 mm thick Kota stone. The V-notch of 6 mm thick MS plate shall be fixed in RCC top beam of 230 mm thickness. The apron shall be constructed with a protection brick wall of 230 mm width & 600 mm thickness, including 100 mm thick RCC with minimum reinforcement over PCC. The external surface of pump house shall be finished with two coats of Asian Apex Ultima exterior paint over one coat of primer. The preperation base surface shall be done with birla wall plast. Painting through spray is prohibited. The top roof slab shall be treated with brick wet coba using appropriate waterproofing chemicals. The vertical rainwater pipes shall be fixed using minimum 100 mm dia PVC pipes of 8 kg/cm², apron of minimum 60 cm width with proper side slopes all around the stucture. All works shall be completed to the satisfaction of the Engineer-in-Charge.Provide all materials, labour, T&P etc. complete and construct Pump house size (3.6x3.0x3.0)m Chlorinating room size (1.80x2.50x3.0)m as per departmental type design for Tube Well. |
| 9 | MCS BuildingThe contractor shall carry out the structural design, supply of all materials, tools, plants, and labour required for construction of MCS with a built-up area of 62 m². The structure shall be an RCC framed structure with brick masonry in 1:2:4 cement mortar. External and internal plaster shall be 12 mm thick in 1:3 cement mortar; internal walls shall be finished with Birla Wall Putty, and external walls with Birla Wall Plast. External walls shall be painted with Asian Apex Ultima exterior paint, and internal walls with two coats of Tractor emulsion plastic paint over one coat of primer. All doors and windows shall be made of UPVC material; windows shall be sliding type with GI grills and mosquito mesh on windows and ventilators. Electrical wiring and fittings shall be done using 2.5 mm² Havells wires, with all switches, sockets, and accessories from Havells. Plumbing shall be done using UPVC pipes, and sanitary fixtures shall be from Cera, Hindware, or Jaguar. Floors shall be finished with 8 mm thick vitrified tiles, and the kitchen counter shall be 25 mm thick granite stone with proper finishing. The MCS building shall consist of two rooms with attached toilets, one pantry, an open verandah, apron of minimum 60 cm width with proper side slopes all around the stucture and one common toilet. Plinth protection and apron shall also be provided as specified in the tender document to ensure proper drainage and site finishing. |
| 10 | Boundary Wall:The contractor shall carry out design, soil investigation, submission of structural designs and drawings, and supply all materials, labour, tools, and plants (T&P) required for construction of the boundary wall (1.8m high above plinth beam) of the OHT/TW campus. The boundary wall shall be designed as an RCC framed structure. The minimum size of columns shall be 230 mm × 230 mm, provided at 3.00 m centre-to-centre. Plinth beams and top beams shall also be provided. A 0.60-meter-high Y-shape wire fencing in 6 rows shall be provided, using wire conforming to IS standards. The boundary wall shall be plastered with 12 mm thick cement mortar in 1:4 ratio, finished with Birla Wall Plast, and painted with Asian Apex Ultima exterior paint over one coat of base paint. The colour of the paint shall be as approved by the Engineer-in-Charge.In cases where the boundary wall is constructed to protect a Pump House, no wicket gates shall be required. RCC ramps or stairs shall be provided to facilitate access to the main gate of the campus or the Pump House as necessary. |
| 11 | MS Gate:Supply and fixing 3.6M & 1.20M wide MS Gate with pillers including fabrication and supply of steel and construction of boundary pillars etc. complete for all respect as per direction of Engineer in Charge.The work includes fabrication and fixing of MS main gates of 3.60 m width and 2.5 m height, and wicket gates of 1.0 m width, using 20 mm square bars, including one coat of base paint and two coats of enamel paint. The minimum size of main gate columns shall be 600 × 600 mm, and plinth beams shall be provided. The foundation depth may be increased depending on site conditions, and plinth beams shall be constructed at a minimum of 30 cm above the formation level of the campus. At each campus, one main gate and one wicket gate shall be provided. All work shall be executed for proper completion to the full satisfaction of the Engineer-in-Charge. |
| 12 | Aproach Road:Construction of C.C. Interlocking Tile approach road road including supply of all materials, labour, T&P etc. required for proper completion of work as per following thickness:-PCC = 100 mm,1:3:6 (cement, coarse sand & stone ballast of 20-40 mm)Sand = 30mm to 50mm thick local sand lair for preparation of surfaceTiles = 100% new Note : 80 mm thick rubber moulded interlocking tile of M-30 shall be used for construction of interlocking tile road. |
| 13 | Rain Water Harvesting UnitThe contractor shall carry out the design, submission of IIT/NIT-vetted structural design and drawings, and supply of all materials, tools, plants, and labour required for construction of rainwater harvesting recharge pits. The design of the rainwater harvesting units may vary depending on the area of each waterworks campus; the contractor shall ensure preparation of appropriate designs for all campuses. If a separate design is required for any individual campus, it shall be prepared at the contractor’s cost. The work shall include construction of two bore wells up to the first water table stratum using a minimum 200 mm PVC pipe of 8 kg/cm². Inlet and overflow chambers of minimum 0.6 m × 0.6 m shall be constructed in RCC M-20, with 350 mm thick brick walls on suitable foundations up to the required depth as per approved design and drawings. The pit shall be filled with suitable media in layers of specified thickness. A piezometer shall be installed for monitoring the water table, as per the directions of the Engineer-in-Charge. |
| 14 | Earth filling in TW campus (other than OHT campus):Supply of all materials, tools and plants for filling of earth in the TW campus including site preparation, surface leveling, earth filling or lifting to achieve the required formation level, plantation, and all other associated activities. The work shall be carried out in accordance with the specifications and to the complete satisfaction of the Engineer-in-Charge. |
| 15 | Construction of 300x300 mm size side drain as per direction of Engineer-in-Charge. |
| 16 | SCHEDULE G-3 (Laying of Rising Main pipe line & appurtenent works) |
| 17 | Excavation of earth in ordinary soil (loam, clay or sand) for pipe line and rising main trenches including lift upto 1.50 m and lead upto 8 km and refilling watering, ramming of the excavated earth into the trench and also disposal of surplus earth upto 50m from the center of the trenches including supply of all material labour, T&P etc complete as per instructions of Engineer ‐in ‐charge. If any Utilities are damaged during excavation (such as existing water line, telephone cables, electric cables, gas pipelines, water house connection, chamber/any structure etc.), it will be repaired by the contractor at his own cost. No extra payment will be paid for this work. |
| 18 | Supply of ISI mark K-9 S&S pipes (push on joints) of following class and diameters inclusive of jointing material (Rubber gasket of EPDM Quality, Bend, Tee etc.) including all statutary duties and taxes, third party inspection charges, transit insurance, freight, transportation to store/ site of work, unloading, stacking etc. complete as directed by Engineer –in-charge. |
| 19 | D.I. pipe Class-K-9 |
| 20 | 200 mm dia Please Enable Macros to View BoQ information |
| 21 | 200 mm dia Please Enable Macros to View BoQ information |