|
| 1 | The work of safe carriage of the following material from Raebareli store center to work site under the jurisdiction of Electricity Distribution Circle - 1 Raebareli . Approx. distance upto 50 Km. Including safe loading and unloading. |
| 2 | PCC Pole 8.5 meter long. |
| 3 | PCC Pole 11 meter long. |
| 4 | STP 11/13 Mtr Long |
| 5 | Line material i.e., cross arm/ pin insulator/stay/earthing rod/Ms Channel/MS Angle/Disc Fitting/Disc Insulators etc |
| 6 | 11 KV XLPE Cable Size 3x70sqmm |
| 7 | 11 KV XLPE Cable Size 3x120sqmm |
| 8 | ACSR Dog Conductor |
| 9 | 3 Phase Arial Bunched Conductor |
| 10 | 1 Phase Arial Bunched Conductor |
| 11 | Distribution Box 1 Phase |
| 12 | Distribution Box 3 Phase |
| 13 | 11 KV Cable Box Size 3x70sqmm |
| 14 | Straight Through |
| 15 | 11/0.4 KV 3 Phase 25 KVA T/F |
| 16 | 11/0.4 KV 3 Phase 63 KVA T/F |
| 17 | 11/0.4 KV 3 Phase 100 KVA T/F |
| 18 | 11/0.4 KV 3 Phase 250 KVA T/F |
| 19 | 11 KV Pilfer proof Metering cubical and CT PT Unit |
| 20 | Erection of new PCC Single/Double pole in H.T/L.T lines including fitting of all accessories as per RESSPO Norms |
| 21 | PCC Pole 8.5 Mtr Long Single Pole |
| 22 | PCC Pole 8.5 Mtr Long Double Pole |
| 23 | PCC Pole 11 Mtr Long Single Pole |
| 24 | ST Pole 11 Mtr Long Single Pole. |
| 25 | ST Pole 11 Mtr Long Double Pole. |
| 26 | Grouting with 1:4:8 mixture in size(450x450x1500mm.) including cost of cement/Concreate & sand Required as per RESSPO Norms |
| 27 | PCC Pole 8.5 Mtr Long Single Pole |
| 28 | PCC Pole 8.5 Mtr Long Double Pole |
| 29 | PCC Pole 11 Mtr Long Single Pole |
| 30 | ST Pole 13 Mtr Long Single Pole. |
| 31 | ST Pole 13 Mtr Long Double Pole. |
| 32 | ST Pole 11 Mtr Long Single Pole. |
| 33 | Dismantling of PCC/ST Pole due to line shifting/damagedcomplete in all respect |
| 34 | ST Pole 11 Mtr Long Single Pole. |
| 35 | The work of Driving the earthing electrode and making connections with 6 S.W.G. GI wire as per RESSPO Norms |
| 36 | LT ABC (3x95+1x70+1x16) SQ. MM |
| 37 | LT ABC (3x120+1x95+1x16) SQ. MM |
| 38 | Dismantling of Old and damaged conductor complete in all respect |
| 39 | Dismantling of Existing Distribution Transformer forincreasing capacity/Shifting complete in all respect |
| 40 | 11/0.4 KV 3 Phase 25 KVA T/F |
| 41 | 11/0.4 KV 3 Phase 63 KVA T/F |
| 42 | Laying, Stringing & Sagging of Following Conductorcomplete in all respect |
| 43 | ACSR Weasel Conductor |
| 44 | ACSR Dog Conductor |
| 45 | 3 Phase Arial Bunched Conductor |
| 46 | 1 Phase Arial Bunched Conductor |
| 47 | Erection and fixing of Overhead Line By XLPE Cable Complete in all respect. |
| 48 | 11 KV XLPE Cable Size 3x70 sqmm |
| 49 | 11 KV XLPE Cable Size 3x120 sqmm |
| 50 | After Mounting of CT PT unit on double pole, laying of 50 Mtr 11 KV 3cx70 sq mm cable in single circuit on river sand form Double Pole to metering room complete in all respect. Alongwith filling of 04 nos cable jointing kits |
| 51 | Installation of 11 KV Pilfer Proof Metering Cubicle in metering room complete in all respect |
| 52 | Under ground laying of Following cable in Single circuit on river sand to Double pole situated at both sides of road complete in all respect. Minimum depth should be 0.75 Mtr and cable should be covered by bricks from three sides. Along with filling of 04 nos cable jointing kits |
| 53 | 11 KV XLPE Cable Size 3x70 sqmm |
| 54 | 11 KV XLPE Cable Size 3x120 sqmm |
| 55 | Under ground laying of Following cable in Single circuit by drill method to Double pole situated at both sides of NH/SH/Railway Crossing (with HDPE Pipe if required) complete in all respect. Alongwith filling of 04 nos cable jointing kits |
| 56 | 11 KV XLPE Cable Size 3x70 sqmm |
| 57 | 11 KV XLPE Cable Size 3x120 sqmm |
| 58 | Hoisting of Following size 11 KV & 33 KV XLPE Cable on double pole with GI pipe of size 6 \\" dia 4 Mtr long including the jumpering complete with clamps, nut and bolts |
| 59 | Supply & Laying of G.I. Pipe at various places i.e road crossing & Hoisting etc. complete in all respect (GI pipe would be Provided by contractor at his own cost) |
| 60 | Supply & Laying of HDPE Pipe at various places i.e road crossing & Hoisting etc. complete in all respect (HDPE pipe would be Provided by contractor at his own cost). |
| 61 | Chemical earthing of T/F & Fencing including all materials (chemical, gi pipe, gi strip, nut bolt, etc) |
| 62 | Earthing of distribution T/F for body & neutral upto water level with GI Pipe of 1.5\\" Dia. Including GI strip size 35x6 mm. (all material will be supplied by Contractor). |
| 63 | Construction of 250/400 KVA T/F plinth 2x2x1.5 Mtr. for mounting T/F including foundation work (below ground 0.5 M), Brick work, RCC slab of 4” thickness and plastering in 1:6 ratio with 02 Nos channel pieces of 1.5 mtr long of size 100x50x6 mm compete in all respect as per UPPCL Norms. |
| 64 | Cage fencing of 250/400 KVA Plinth mounted transformer in Town areas to avoid electrical human/cattle accidents by fabrication of cage (1 Inch Sq wire mesh) made of 10 No gauge in suitable size angle iron frame of size 7.5'(L)x5'(W)x8'(H) by strengthening of wire mesh 20x3 mm M.S. flat horizontally as well as vertically, Grouting the panel with 1:2:4 cement/coorse send/brick ballast. The Frame should be bolted on angles at the four corners so that frame may be un-bolted/bolted at the time of replacement of the transformer. Provision of 1 gate should be there for maintenance of the transformer. Painting (1 coat of red oxide + 2 coat of Bus green enamel paint). The wire mesh should be earthed with 50x6 mm MS earthing strip with existing earthing of Transformer Body. All manpower, material and T&P provided by the contractor to complete the fabrication, transportation and installation. |
| 65 | The work of digging of pits, erection of Stay Clamp, Insulator etc. |
| 66 | Grouting of stays, 1:4:8 cc ratio (600x600x300mm.) as per RESPO norms. |
| 67 | Installation of 11 KV Pilfer Proof Metering Cubicle in metering room complete in all respect |
| 68 | Mounting of Following Capacity Transformers as per norms complete in all respect |
| 69 | 25 KVA T/F |
| 70 | 63 KVA T/F |
| 71 | 100 KVA T/F |
| 72 | 250 KVA T/F |
| 73 | Fixing of Distribution Box complete in all respect |
| 74 | Guarding at road crossing complete in all respect |
| 75 | Errection & Fixing of Cable box |
| 76 | 11 KV Cable Box Size 3x70sqmm |
| 77 | 11 KV Cable Box Size 3x120sqmm |
| 78 | 11 KV Cable Box Size 3x185sqmm |
| 79 | 11 KV Cable Box Size 3x300sqmm |
| 80 | Straight Through 11 KV Cable Box Size 3x70sqmm,3X120sqmm,3x185sqmm) |
| 81 | Cutting of Tree Branch Comming Near Line |
| 82 | Supply & Fixing of Following Items to complete the work (If Not available in stores) |
| 83 | LT Clamps |
| 84 | Nut & Bolt off size |
| 85 | F Clamp as per RESSPO Norms |
| 86 | Shackle Insulator as per RESSPO Norms |
| 87 | X-Arm Holding Clamp as per RESSPO Norms |
| 88 | clamps for top, t-off & other channel etc. |
| 89 | Stay Clamps as per RESSPO Norms |
| 90 | Three Phase Distribution Box Clamp (LS) |
| 91 | Dead End Clamp |
| 92 | Eye Hook |
| 93 | J Hook |
| 94 | LT Shackle Insulator |
| 95 | Barbed Wire |
| 96 | Aluminum Paint |
| 97 | Number Plate |
| 98 | Al. Lugs 70 Sqmm mm |
| 99 | Al. Lugs 150 Sqmm mm |
| 100 | Al. Lugs 240 Sqmm mm |
| 101 | Al. Lugs 400 Sqmm mm |
| 102 | 11 KV DO Fuse Set |
| 103 | Heneley Type Tail less Unit |
| 104 | SMC Fuse BOX |
| 105 | Garding Angle |
| 106 | Garding Angle Clamp with Nut & Bolt |
| 107 | Suspension Clamp for XLPE Overhead |
| 108 | Danger Board |
| 109 | Stone Pad |
| 110 | Dropper Channel |
| 111 | Safe back carriage of Distribution Transformer from work site to Raebareli Store approx. distance upto 50 Km including safe loading & unloading. |
| 112 | A.B. Cable Scrap |
| 113 | Iron Scrap |
| 114 | STP Pole Scrap |
| 115 | ACSR Weasel Conductor Scrap |
| 116 | 11/0.4 KV 3 Phase 25 KVA T/F |
| 117 | 11/0.4 KV 3 Phase 63 KVA T/F |
| 118 | 11/0.4 KV 3 Phase 100 KVA T/F |
| 119 | 11/0.4 KV 3 Phase 250 KVA T/F |
| 120 | 11/0.4 KV 3 Phase 400 KVA T/F |
| 121 | 11 kv vcb Please Enable Macros to View BoQ information |