| 1 | Earth work in excavation by mechanical means (hydraulic excavator)/manual means in foundation pipeline trenches, drain not exceeding 1.5m in width 10 sq.m on plan including dressing of sides ramming of bottoms for all lead and lift including setting out the excavated soil & disposal of surplus soil with all lead including providing barricading danger lighting guarding as directed by departmental officer in all types strata comprising any of the materials such as soil, silt sand clay gravel moorum of all conglomerated laterite rock, soft rock fissured shattered decomposed rock or weathered rock and all such other materials as described under Appendix A to these specification either in full or in parts as the case may be adopting any approved method of methods as may be convenient or permitted inclusive of chiselling, wedging etc, blasting probhibited in all conglomerates as directed by the Engineer-incharge etc, complete. |
| 2 | Supplying at store or site of work Rigid PVC (SEL FIT) pipes for public water supply including Railway freight carting loading and unloading stacking transit insurance etc. complete Conforming to IS: 4985-2000 and bearing ISI mark Class 6 kg/cm2 |
| 3 | 63 mm dia |
| 4 | Supply of rigid PVC fittings conforming to IS: 7834-1975 designed for precision and accuracy so as to join PVC pipes and other specials including railway freight carting loading and unloading and stacking etc. complete. |
| 5 | Elbow PN 10 (10kg/cm2) |
| 6 | 63 mm dia |
| 7 | END CAP ( Plain ) PN 6 (6 kg/cm2) |
| 8 | 63 mm dia |
| 9 | Tee PN 6 (6 kg/cm2) |
| 10 | 63 mm dia |
| 11 | Supplying of ASTM UPVC pipe conforming to ASTM 1785 with ISO 14001 etc. complete. |
| 12 | SCH-80(Blue)/(white) |
| 13 | Conveying carefully from stack at site 250m from both sides rolling and lowering in trenches laying true to line and level and perfect linking for joints for P.V.C / H.D.P.E complete in all respects as per the direction of the engineer in-charge |
| 14 | 63 mm OD |
| 15 | Jointing of rigid / SEL FIT PVC pipes by cleaning the pipe with solvent cement including the cost of solvent cement and hydraulic testing of joints etc. complete as per IS:7634-1975 Part 3 including hydraulic testing of joints as directed by the engineer in-charge. |
| 16 | 63 mm dia |
| 17 | Making connection to individual 15mm /20mm/25mm G.I/ OD Blue PVC pipeline with existing distribution line of any diameter with saddle piece / and necessary pipe and specials required suitable to the distribution line with road cutting trenching refilling the same including the cost of labour and accessories etc. complete. as per the direction of Engineer -in- charge. |
| 18 | Providing and fixing brass full way valve (heavy) duty with wheel of approved quality : |
| 19 | 20 mm nominal bore |
| 20 | 50 mm nominal bore |
| 21 | Construction of masonry chamber 60x60x75cm inside in 40kg/sq. cm ,brickwork complete with 23 cms wall thickness and in cement mortar 1:4( 1 cement : 4coarse sand) for sluice valves 50 to 80mm with necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 coarse sand: 10 graded stone ballast 40 mm nominal size) and inside plastered with CM 1:3 ( 1 cement : 3 coarse sand) finished with floating coat of neat cement complete and chamber cover as specified below etc. all complete as per standard drawing . (rate is inclusive of rate earthwork excavation, cost of surface cover and all other materials and labour and as per details below) |
| 22 | With C.I. Surface box 100mm top dia 160mm bottom dia and 160mm deep of wt 15kg inside with chain lid in 120 mm thick RCC slab cover in cement concrete 1:2:4 ( 1 cement: 2 coarse sand : 4 graded stone ballast 20 mm nominal size) |
| 23 | Cutting the bituminous road for laying the pipeline in trenches for a width of 0.6m including labour, tools, etc. and disposing the excavated excess material from the trench to a distance of 1000 metres, including making level the trench surface by utilising the serviceable material to the level of the top surface of road, by compacting, watering ramming with rolling with road roller after completion of laying of pipe and refilling the trenches etc. complete as per the direction of engineer in charge. |
| 24 | By Manual Means |
| 25 | Rural Roads |
| 26 | Repairs and reinstatement to the road for trenches made by laying water supply pipeline, by removing the refilled material in the trench for the total depth of 0.40m and making good the road surface by providing laying rolling by road roller compacting for laterite soling 30cm thick, two layer of full grout of 50mm thick each as per specifications mentioned in item no 14086 of road GSR, complete as per the direction of the engineer in charge. |
| 27 | Rural road. |
| 28 | Refilling the pipeline/foundation trenches plinth sides foundation etc. with available excavated earth in layers not exceeding 20 cm depth consolidating each layer ramming and watering lead upto 50 M and all lifts and disposal of surplus earth as directed by Engineer in Charge. Please Enable Macros to View BoQ information |