| 1 | Earth work in excavated by mechenical means (hydraulic excavator)/ manual means in foudation trenches or drains (not exceeding 1.5 m in width of 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil Item no-2.8.1 DSR 2023 +3% |
| 2 | Extra for every additional lift of 1.5 m or part thereof in excavation/ banking excavated or stacked materials. DSR 2.26.1 + 2.8.1+3% |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering all work up to plinth level 1:4:8 (1) cement: 4 coarse sand (Zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) item no-4.1.8 DSR 2023+3% |
| 4 | Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using cement content as per approved design mix, manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying , excluding the cost of centering, shuttering finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate/ retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge.) DSR 5.37/2023 +3% RAFFT |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanilcally Treated bars of grade Fe-500D DSR2023/5.22.6 +3% |
| 6 | Cement Concrete 2cm. gauge approved stone ballast coarse sand and cement in proportion 4:2:1 including supply of all materials, labour, T&P etc. required for proper completion of the work.DSR/2023 4.1.3+3% |
| 7 | Construction of weep holes with 110 mm dia (OD) RPVC pipe (IS : 4985) (6 kg/sqcm) in the RCC wall at an interval of 1.50 m horizontally & vrtically at the time of casting of wall with all materials labours etc required ofr proper completion of the work. (SANCTION RATE) |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form forWalls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. DSR 5.9.2/2023+3% FOUNDATION |
| 9 | Providing and placing in position 100 mm thick factory made machine batched & machine mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25 grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement of 8 mm dia TMT bars of Fe 500 grade @ maximum 100 mm c/c on both ways, neat cement punning on finished surface, properly encased on all edges with 1.6 mm thick, 100 mm wide MS sheet duly painted over priming coat, reinforcement to be welded at edges with MS sheet andproviding 2 Nos. 12 mm dia bar for hooks etc including cost of cartage, all leads&lift,handling at site etc. all complete asperdirection of Engineer-inCharge.DSR2023/16.93+3% |
| 10 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all( Railing/Jali) complete.DSR2023/10.2+3% |
| 11 | Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints etc. completeDSR2023/19.6.1+3% |
| 12 | Banking excavated earth by mechanical / manual means in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and for all lift:DSR2023/2.3.1+3% |
| 13 | Cartage of earth from 8 km including loading unloading (SOR-2022) |
| 14 | Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately).DSR2023/16.73+3% Please Enable Macros to View BoQ information |