| 1 | Supplying and installation of horizontal split casing centrifugal pump having discharge of 27200 G.P.H clear water against a total head of 50 meters (164 feet) Make- Kirloskar/Mather and Platt/ jyoti / Wpil with a suitable squirrel cage induction motor 3 ph, 415 V ± 10% , 1480 r.p.m, Make- Kirloskar/Mather and Platt/ jyoti/ Crompton /ABB coupled by means of tyre coupling on a common base plate with N.R valve, sluice valve rating PN- 1, ISI marked , foot valve, pressure gauge etc. all complete. |
| 2 | Cost towards supply and fitting 40 H.P fully automatic air break star delta starter , Make- L&T /Havell’s/ Siemens / Schneider/ BCH |
| 3 | Cost towards replacement of damaged parts of panel by new supply and fitting 200 amp T.P.N DTH MCCB-1no incoming feeder and 160 amp T.P.N DTH MCCB-2 nos. outgoing ,0 to500v voltmeter - 2 nos., 0to 200 amp ammeter-2 nos. with selector switch ,indicating lamp 3 Nos., making internal connection with copper wire etc. |
| 4 | Cost towards dismantling 2 nos. 20 H.P C/F pump set with all accessories such as suction and delivery pipe line ,foot valve ,sluice & N.R valve, base plate etc ,including demolish old foundation -1 nos. for installation of new pump set, including keeping pump set in store or as per direction of E/I and throwing broken foundation outside the pump house including cost of labors , tools, tackles |
| 5 | Cost towards making new P.C.C foundation with supplying stone chips, sand, cement, in the ratio 3:2:1 respectively about 5’x4’x3’for above pump sets including foundation bolts with nut and washer and curing plastering of foundation ,all complete . |
| 6 | Supplying and laying of 95 mm sq. 1.1 K.V grade,3.5 core P.V.C insulated and sheathed armored Al. cable , make – polycab, havell’s /,KEI, ISI marked, |
| 7 | Cost towards doing cable socketing with Al lugs 95 mm sq. Al. cable |
| 8 | Cost of supply & laying, commissioning of 3 core 25 mm² copper conductor cable 1.1 KV grade PVC insulated and PVC sheathed unarmored from panel to starter and starter to motor with lugs socketing, |
| 9 | Cost towards making chemical earthing as per I:E Rules ,etc. all complete. |
| 10 | Cost towards making suction & delivery pipe line with supply of 150 m.m dia. heavy duty M.S pipe 30 feet , 150 m.m dia. M.S flange- 8 nos. , 150 m.m dia. heavy duty M.S bend -2 nos., 100 m.m dia. heavy duty M.S pipe -15 ft., 100 m.m dia. heavy duty M.S flange -8 nos. 100 m.m dia. heavy duty M.S bend -4 nos. including cutting welding , required nut bolts, washer, rubber insertion, testing on load , all complete . |
| 11 | Cost towards making earthing connection from earth pit to change over , stabilizer ,panel, starter, motor with 6 SWG G.I wire |
| 12 | Supply and fitting 200 amp TPN switch fuse unit-1 no before stabilizer on the wall, including required materials such as clamp, nut, bolts, etc, for the job , make – L&T, Havell’s, any Reputed make ISI Marked. |
| 13 | Supply, fitting & commissioning of lighting arrangement at pump hose and outside of pump house such as tube light 40 W complete set 2 no and 70 W LED lamp complete set 1 nos. and making wiring, light point, fan point etc. as required. Please Enable Macros to View BoQ information |