| 1 | Dismantling & Removing cement concrete including stacking theuseful material for reuse and removing the debris within 50m lead & cost of all labour,cess etc. all complete |
| 2 | Earth work in excavation of foundation in hard soil or Gravelly soil within 50 m initial lead & 1.50 m initial lift including levelling & dressing the bed and breaking clods to maximum 5cm to 7cm. and laying in layers not exceeding 0.3 M in depth and as per direction of the Engineer-in-charge. including cost of all labour cess etc.all complete |
| 3 | Carriage of Excavated earth by mechanical means with in 5km lead including loading and unloading with all cost Conveyance T&P sun dries etc.complete as per direction of Enggineer-in-charge. |
| 4 | Filling Stone Screened Dust in road surface and pavement well watered & rammed including cost , conveyance to site , royalty , cess DMF & EMF and additinol royalty etc all taxes of all materials & cost of all labour complete |
| 5 | Filling sand in foundation & plinth well watered & rammed including cost , conveyance to site , royalty , cess DMF & EMF and additinol royalty etc all taxes of all materials & cost of all labour complete |
| 6 | C.C. ( 1 : 4 : 8 ) using 40 mm size hgcb metal free from weathered skin & all foreign materials including cost , conveyance to site , watering and curing,royalty , cess DMF & EMF and additinol royalty etc all taxes of all materials & cost of all labour complete |
| 7 | RCC/PCC work in M- 20 Grade of concrete with 20 mm & down graded size CBHG chips including hoisting & laying & cost, conveyance to site , royalty , Cess DMF & EMF and additinol royalty etc. All taxes of all materials complete |
| 8 | Rigid & smooth Centering & shuttering for PCC works including false work and dismentalling them after casting including cost & charges of all materials & cost of all labour complete . |
| 9 | Suplying , fitting & placing in position uncoated HYSD bar reinforcement for RCC work including cutting ,bending ,binding & placing in position including cost & conveyance to site etc. all taxes of MS/ TS Rod & binding wire 18to 20 gauge complete . |
| 10 | Filling the Low area with borrow earth (arranged by contractor) in layers including watering and comaction with cost, conveyance, royalty and taxes of all materials cost of all labour carriage of water T and P sundries as required for the work etc all complete as per directiom of EIC |
| 11 | Supplying all labour , T & P , etc. for preparation stainless steel with ACP Sheet Display Board including writing charges & provision of photto graphs Pre, during & post etc. including cost of all materials & cost of all labour complete Please Enable Macros to View BoQ information |