| 1 | Carriage of 8.5 Mtrs. long PCC pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) | Carriage of 8.5 Mtrs. long PCC pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) |
| 2 | Carriage of 9 Mtrs. long PCC pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) | Carriage of 9 Mtrs. long PCC pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) |
| 3 | Carriage of 11/13 Mtrs. long ST pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) | Carriage of 11/13 Mtrs. long ST pole from Electricity Store Center Taj, Agra to site of work through the Kacha and Pakka road including the work of its loading and unloading at the respective ends by using manual labour or tractor/Hydra as per site requirment including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) |
| 4 | Carriage of following from Electricity Store Center Taj, Agra to related 33/11 KV Substations and to site of work i.e. pit point through the Kacha and Pakka road including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) 11 KV X-Arms, weasal conductor, G.I wire,Disc Insulators, Pin insulators, clamps and other required for LT/11KV/33KV line material, if any. | Carriage of following from Electricity Store Center Taj, Agra to related 33/11 KV Substations and to site of work i.e. pit point through the Kacha and Pakka road including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) 11 KV X-Arms, weasal conductor, G.I wire,Disc Insulators, Pin insulators, clamps and other required for LT/11KV/33KV line material, if any. |
| 5 | Removal of existing ACSR Weasel conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. | Removal of existing ACSR Weasel conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. |
| 6 | Removal of existing ACSR Dog/Raccon conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. | Removal of existing ACSR Dog/Raccon conductor from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. |
| 7 | Removal of existing Arial Bunch Conductor 3x50/95/120 sq mm from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. | Removal of existing Arial Bunch Conductor 3x50/95/120 sq mm from damaged line/Pole including opening of jumpers etc as per requirement of site and as per direction of Supervising Engineer. |
| 8 | Replacement of 8.5 Mtrs. Long damaged PCC pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. | Replacement of 8.5 Mtrs. Long damaged PCC pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 9 | Replacement of 9 Mtrs. Long damaged PCC pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. | Replacement of 9 Mtrs. Long damaged PCC pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 10 | Replacement of 11/13 Mtrs. Long damaged ST pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. | Replacement of 11/13 Mtrs. Long damaged ST pole by opening of all existing accessories from damaged pole properly and removal of damaged pole and erecttion the new pole with grouting at same place including fixing of all existing accessories on the new pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 11 | Replacement of 8.5 Mtrs. Long damaged PCC Double Pole by opening of all existing Accessories, T/F from damaged Double pole properly and removal of damaged poles and Erection of New Double Pole with grouting at same place including fixing of all existing accessories on the New Double Pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. | Replacement of 8.5 Mtrs. Long damaged PCC Double Pole by opening of all existing Accessories, T/F from damaged Double pole properly and removal of damaged poles and Erection of New Double Pole with grouting at same place including fixing of all existing accessories on the New Double Pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 12 | Replacement of 11/13 Mtrs. Long damaged ST Duoble Pole by opening of all existing Accessories, T/F from damaged Double pole properly and removal of damaged poles and Erection of New Double Pole with grouting at same place including fixing of all existing accessories on the New Double Pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. | Replacement of 11/13 Mtrs. Long damaged ST Duoble Pole by opening of all existing Accessories, T/F from damaged Double pole properly and removal of damaged poles and Erection of New Double Pole with grouting at same place including fixing of all existing accessories on the New Double Pole etc. as per direction of supervising engineer. It including the cost of all labour, T&P etc. required for proper completion of work. |
| 13 | Mounting of 10/16 KVA Transformer on the Single Pole structures and connections thereof. | Mounting of 10/16 KVA Transformer on the Single Pole structures and connections thereof. |
| 14 | Mounting of 25/63 KVA Transformer on the Double pole structures and connections thereof. | Mounting of 25/63 KVA Transformer on the Double pole structures and connections thereof. |
| 15 | Mounting of 100 KVA Transformer on the Double pole structures and connections thereof. | Mounting of 100 KVA Transformer on the Double pole structures and connections thereof. |
| 16 | Installation of stay set with grouting and Nuzzling etc. as per RESPO drawing /norms along with all routine material to be used for such works. | Installation of stay set with grouting and Nuzzling etc. as per RESPO drawing /norms along with all routine material to be used for such works. |
| 17 | Earthing of poles by fixing earth rods and binding with earth wire as per standard norms including cost of labour T&P and required material for such work. | Earthing of poles by fixing earth rods and binding with earth wire as per standard norms including cost of labour T&P and required material for such work. |
| 18 | Laying, sagging, stringing, jumpering and binding etc. of new & old ACSR Weasel conductor in 11 KV/ LT lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work | Laying, sagging, stringing, jumpering and binding etc. of new & old ACSR Weasel conductor in 11 KV/ LT lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work |
| 19 | Laying, sagging, stringing, jumpering and binding etc. of new & old ACSR Dog/Raccon Conductor in 11 KV/33KV lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work | Laying, sagging, stringing, jumpering and binding etc. of new & old ACSR Dog/Raccon Conductor in 11 KV/33KV lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work |
| 20 | Laying, sagging, stringing, jumpering and binding etc. of new & old Arial Bunch Conductor 3x50/95/120 sq mm. in LT lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work | Laying, sagging, stringing, jumpering and binding etc. of new & old Arial Bunch Conductor 3x50/95/120 sq mm. in LT lines as per RESPO manual as per direction of supervising engineer including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work |
| 21 | Replacement of damaged 33KV/11 KV X-Arm along with Nut & Bolt and all other related accesoories. | Replacement of damaged 33KV/11 KV X-Arm along with Nut & Bolt and all other related accesoories. |
| 22 | Replacement of damaged 33KV/11 KV Disc Insulator with fitting along with Nut & Bolt and all other related accesoories. | Replacement of damaged 33KV/11 KV Disc Insulator with fitting along with Nut & Bolt and all other related accesoories. |
| 23 | Replacement of damaged 33KV/11 KV/LT Pin Insulator with Pin with fitting along with Nut & Bolt and all other related accesoories. | Replacement of damaged 33KV/11 KV/LT Pin Insulator with Pin with fitting along with Nut & Bolt and all other related accesoories. |
| 24 | Replacement of damaged 33KV/11 KV/LT F\\" Clamp/X-Arm Clamp/D.P.Clamp/L.T. Pin Clamp with fitting along with Nut & Bolt and all other related accesoories. | Replacement of damaged 33KV/11 KV/LT F\\" Clamp/X-Arm Clamp/D.P.Clamp/L.T. Pin Clamp with fitting along with Nut & Bolt and all other related accesoories. |
| 25 | Guarding/Reguarding of 11 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. It includes the cost o f labour T&P carriage etc required for proper completion. | Guarding/Reguarding of 11 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. It includes the cost o f labour T&P carriage etc required for proper completion. |
| 26 | Guarding/Reguarding of 33 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. It includes the cost o f labour T&P carriage etc required for proper completion. | Guarding/Reguarding of 33 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 mtrs. as per direction of supervising engineer/RESPO manual. It includes the cost o f labour T&P carriage etc required for proper completion. |
| 27 | Chopping of Tree branches to Clear the line route to give horizontal and vertical clearance to the line including cost of labour T&P etc. | Chopping of Tree branches to Clear the line route to give horizontal and vertical clearance to the line including cost of labour T&P etc. |
| 28 | Re- sagging and stringing of ACSR Weasel conductor in 11KV/ /LT line as per direction of supervising engineer including the cost of arrangement of labour,T&P, carrier etc. required for proper completion of work. | Re- sagging and stringing of ACSR Weasel conductor in 11KV/ /LT line as per direction of supervising engineer including the cost of arrangement of labour,T&P, carrier etc. required for proper completion of work. |
| 29 | Re- sagging and stringing of existing conductor in 33 KV line as per direction of supervising engineer including the cost of arrangement of labour,T&P, carrier etc. required for proper completion of work A) ACSR Dog/Racoon Conductor. | Re- sagging and stringing of existing conductor in 33 KV line as per direction of supervising engineer including the cost of arrangement of labour,T&P, carrier etc. required for proper completion of work A) ACSR Dog/Racoon Conductor. |
| 30 | Re-nuzzling of old stay set by opening old binding for better straightening of pole and re-sag the existing conductor of H.T/L.T line properly as per direction of supervising engineer. | Re-nuzzling of old stay set by opening old binding for better straightening of pole and re-sag the existing conductor of H.T/L.T line properly as per direction of supervising engineer. |
| 31 | Straightening of 8.5/9 Mtr. Long PCC/ST/Rail Pole tilted pole at various places by straightening of pole including the cost of labour ,T&P charges required for proper completion of work. | Straightening of 8.5/9 Mtr. Long PCC/ST/Rail Pole tilted pole at various places by straightening of pole including the cost of labour ,T&P charges required for proper completion of work. |
| 32 | Carriage of 11/13 Mtrs. long Damaged ST pole from Pit Site to J.E. Store/Store Center Agra through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) | Carriage of 11/13 Mtrs. long Damaged ST pole from Pit Site to J.E. Store/Store Center Agra through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work.(Distance 00-70 Kms.) |
| 33 | Numbering of Replaced poles by Yellow enamel paint as per direction of supervising Engineer. (Concerning material shall be provided by the contractor at his own cost) | Numbering of Replaced poles by Yellow enamel paint as per direction of supervising Engineer. (Concerning material shall be provided by the contractor at his own cost) |
| 34 | Vediography of All Work's site Shall be made by the contractor of concerning site before starting the work and after the completion of work & the copy of vediography shall be submitted by the contractor at the time of Measuremnt/Payment. | Vediography of All Work's site Shall be made by the contractor of concerning site before starting the work and after the completion of work & the copy of vediography shall be submitted by the contractor at the time of Measuremnt/Payment. |