| 1 | Earth work in excavation for foundation, trenches for pipes / cables or drains etc. by mechanical means /manual means (exceeding 30cm in depth.) including ramming of bottom, dressing of sides,disposal of excavated earth including of all |
| 2 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering All workup to plinth level. Cement concrete grade |
| 3 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding upto floor level including cost of binding wire, wastage and over laps upto 12mm horizontal/ inclined position of reinforcement bars in slab and beams, plinth, chajjas, lintels,upto 4.5m vertical length of reinforcement Thermo-Mechanically Treated bars. |
| 4 | Providing and laying in position specified grade of reinforcedcement concrete excluding the cost ofCement concrete grade M-20 (Nominal Mix) with 20 mm maximumsize of stone aggregate. |
| 5 | Filling by available excavated earth (excluding rock) intrenches, plinth, sides of foundations etc. in layers notexceeding 20cm in depth, consolidating |
| 6 | Brick work with fly ash lime bricks (FALG Bricks) conforming to IS:12894-2002, class designation 50 (average compressive strength) upto plinthlevel : Cement mortar 1:6 (1 cement : 6 coarsesand) |
| 7 | Centering and shuttering including strutting, propping stretching etc. complete for and removal of form work by sheet plate or ply woodshuttering for Foundations, footings, bases of columns,etc. For mass concrete. |
| 8 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers,abutments, posts and struts etc.above COLUMN ABOVE PLINTH HIGHT |
| 9 | Centering and shuttering including strutting, propping etc.and removalof form for : Columns, Pillars, Piers, Abutments, Postsand Struts |
| 10 | Brick work with fly ash lime bricks (FALG Bricks) conforming to IS:12894-2002, class designation 50 (average compressive strength) in superstructure above plinth level up tofloor 2 level including the cost of Cement mortar 1:6 (1 cement : 6 coarsesand) |
| 11 | 18 mm cement plaster in two coats under layer 12 mm thick cementplaster 1:5 (1 cement: 5 coarse sand) and a top layer 6mmthick cement plaster 1:3 (1 cement: 3 |
| 12 | Steel work in built up M.S. tubular Hot finished welded type tubes |
| 13 | Steel work welded in built up sections/ framed work including cutting,hoisting, fixing in position and applying a priming coat of approvedsteel primer using structural steel etc. as in gratings, frames, guard bar, ladder, railings, brackets, gatesand similar works |
| 14 | Wall painting with plastic emulsion paint of approved brand and manufacture to give an even shade |
| 15 | Painting Steel work with Deluxe Multi Surface Paint to give an evenshade. Two or more coat applied @0.90 ltr/10 sqm over an under coat of primer applied @ 0.80 ltr/ 10 sqm of approved brand or manufacture Please Enable Macros to View BoQ information |