| 1 | Dismentlling reinforced cemment concerete or reinforced brick work including stacking of materials |
| 2 | Taking out existing CC interlocking paver blocks of footpath/ central verge, including removal of rubbish etc., |
| 3 | Ded cost of old tiles etc all comp. |
| 4 | Earth work in foundation in ordinary soil etc all comp. |
| 5 | Desposal of refused material/malwa distance up to 8 km etc all complete |
| 6 | Dismantlling of brick work or stone work in lime cement mortar and including stacking of material |
| 7 | Deduct the cost of old bricks |
| 8 | Ded the cost of old bricks/batts |
| 9 | Dewatering of Nala by disel pump set etc all comp. |
| 10 | P/I of 110 mm PVC pipe etc all comp. |
| 11 | C.C in 1:6:12 cement, fine sand and 40 mm gauge brick ballest etc |
| 12 | R.C.C. work with cement, approved coarse sand & 2 cm gauge approved stone grit in proportions of 1:1:5:3 in lintels of doors and windows |
| 13 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete |
| 14 | Supply & laying, spreading 53 mm to 22.4 m size stone aggregate of specified sizes to WBM specifications in uniform thickness |
| 15 | Consolidation of stone ballest etc all complete I.S.I No 755 A |
| 16 | Providing and applying Track coat with bitumen VG-10 grade using bitumen pressure distriuter at the rate of 0.30 kg per Sqm |
| 17 | Providing and laying dense graded bituminous macadum with HMP producing an average output of 75 tonnes per hour using crused aggregates from approved quary of specified grading premixed with bituminous binder VG 30 @4.5 percent by weight of total mix and filter etc all comp. |
| 18 | Providing and applying Track coat with bitumen VG-10 grade using bitumen pressure distriuter at the rate of 0.30 kg per Sqm |
| 19 | Recycling pavement by cold milling of existing bituminous layers using by bituminous concrete (grading 2) using bitumen VG 30 content is 5.4% bitumen weight of mix for reclaimed material |
| 20 | p/l of 80mm thick i shape interlocking tiles etc all comp. |
| 21 | Construction of unreinforced plane cement concrete pavement |
| 22 | Road marking with hot applied thermoplastic compound with reflectorising glass bends on bituminous surface etc all comp. |
| 23 | Rising of mainhole incl of material and labour and tools plants etc all material |
| 24 | Making of DPR cost |
| 25 | Supply and fixing of M.S board |
| 26 | GST Please Enable Macros to View BoQ information |