| 1 | Carriage of 3 NO. 33 KV CT (2000-1250/1 Amp) diverted from 132 KV Sub-station Ghatampur to 220 KV Sub-station Bharthana. |
| 2 | Shifting of 3 NO. 33KV CT from store to loading point and safely loading of 3 NO. 33KV CT with terminal connector with the help of manual labour/crane at 132 KV Sub-station Ghatampur alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in the direction of the supervising engineer. |
| 3 | Safe carriage of 3 NO. 33 KV CT on suitable vehicle from 132 KV Sub-station Ghatampur to 220 KV Sub-station Bharthana (Approx. Distance 200 Km.) |
| 4 | Unloading and proper stacking of 03 Nos. 33KV CT wither terminal connector from the vehicle to store/ suitable place with the help of manual labour /crane at 220 KV Sub-station Bharthana. alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in the direction of the supervising engineer |
| 5 | Carriage of 1 No. 33 KV BUS ISOLATOR (2000 Amp) diverted from 220 KV Sub-station Sikandara, Kanpur to 220 KV Sub-station Bharthana. |
| 6 | Shifting of 01 No. 33KV Bus Isolator from store to loading point and safely loading of 01 No. 33KV Bus Isolator with the help of manual labour/crane at 220 KV Sub-station Sikandara, Kanpur alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in the direction of the supervising engineer. |
| 7 | Safe carriage of 1 No. 33 KV Bus Isolator on suitable vehicle from 220 KV Sub-station Sikandara to 220 KV Sub-station Bharthana (Approx. Distance 80 Km.) |
| 8 | Unloading and proper stacking of 01 No. 33KV Bus Isolator from the vehicle to store/ suitable place with the help of manual labour /crane at 220 KV Sub-station Bharthana. alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in thedirection of the supervising engineer |
| 9 | Carriage of unarmoured control cable 2cx2.5sq.mm-01Km and 4cx2.5Sq.mm-1Km diverted from 220 KV Sub-station Bithoor to 220 KV Sub-station Bharthana. |
| 10 | Shifting & loading of unarmoured control cable 2cx2.5sq.mm-01Km and 4cx2.5Sq.mm-1Km Cable at 220kv S/S Bithoor with help of manual labour including all cost of men, material and T&P etc. |
| 11 | Safe carriage of unarmoured control cable 2cx2.5sq.mm-01Km and 4cx2.5Sq.mm-1Km Cable on suitable vehicle from 220 KV Sub-station Bithoor to 220 KV Sub-station Bharthana (Approx. Distance 180 Km.) |
| 12 | Unloading and proper stacking of unarmoured control cable 2cx2.5sq.mm-01Km and 4cx2.5Sq.mm-1Km Cable from the vehicle to store/ suitable place with the help of manual labour /crane at 220 KV Sub-station Bharthana. alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in the direction of the supervising engineer |
| 13 | Carriage of 1 Km Cable 6c x2.5Sq.mm diverted from 220 KV Sub-station Farrukhabad to 220 KV Sub-station Bharthana. |
| 14 | Shifting & loading of 1 Km Cable 6c x2.5Sq.mm at 220KV S/S Farrukhabad with help of manual labour including all cost of men, material and T&P etc. |
| 15 | Safe carriage of 1 Km Cable 6c x2.5Sq.mm on suitable vehicle from 220 KV Sub-station Farrukhabad to 220 KV Sub-station Bharthana (Approx. Distance 150 Km.) |
| 16 | Unloading and proper stacking of 1 Km Cable 6c x2.5Sq.mm Cable from the vehicle to store/ suitable place with the help of manual labour /crane at 220 KV Sub-station Bharthana. alongwith other associated work with all cost of men, materials and T&P etc required for satisfactory completion of work in thedirection of the supervising engineer Please Enable Macros to View BoQ information |