| 1 | Drilling of borehole for tubewell construction by RC Rig machine including Transportation,erection,dismantling of rig and assoilated T&P complete in all respect including required all material,labour etc. |
| 2 | Transportation ,Erection and Dismantling of Rig machine |
| 3 | Drilling of 600mm Size bore from GL to 45 BGL |
| 4 | Drilling of 500mm Size bore from (i)45m BGL to 100m BGL |
| 5 | (ii)100m BGL to 150m BGL |
| 6 | M.S. Tubewell assemebly with all required parts like plain pipe,slotted pipe( as required upto 50% of plain pipes) rings,well cap, bail plug, clamp,reducer,cenreral guide,support structer etc.As required & as per typeed design complete in all respect. |
| 7 | 300mm. Dia M.S ERW Housing/ casing pipe having wall thickness of 7.1mm |
| 8 | 200mm dia M.S ERW slotted/ casing pipe having wall thickness of 7.1mm |
| 9 | Supply of pea gravel |
| 10 | Logging of bore hole by departmental/approved electric logger. |
| 11 | Lowering of tubewell assembely duly welded including welding electrode and shurounding of pea gravel complete in all respect. |
| 12 | Lowering of 300mm dia pipe from GL to 42m deep BGL. |
| 13 | Lowering of 200mm dia pipe from 42m to 100m deep BGL. |
| 14 | Lowering of 200mm dia pipe from 100m to 135m deep BGL. |
| 15 | Development of Tubewell by Compressor |
| 16 | Transportation, Installatoin and Dismantling of 350 PSI compressor. |
| 17 | Development of Tubewell by 350 PSI capacity Air Compressor. |
| 18 | Development of Tubewell by O.P.Unit |
| 19 | Transportation,Installatoin and Dismantling of 1 cusec O.P unit & Yield Test. |
| 20 | Development of Tubewell ,by 1 Cusec capacity By O.P.unit |
| 21 | Chemecial and Bacterological test of water sample from departmently/Approved lab. |
| 22 | Site Clearance and gravel Shifting & other allied works. |
| 23 | Baricading/Fencing of the site during the construction of T.W to ensure that site is note exposed to risk of accident. |
| 24 | SITC of pumping plant including starter, control panel complete in all respect with all required material, T&P labour etc. Submersible pump set of 1600 LPM discharge 37mtr. head coupled with 25 H.P. Motor. AC Three Phase. |
| 25 | Voltage stabilizer Servo Type (240 to 500V) 40 KVA. |
| 26 | SITC of Main Piping and valves of 150mm dia with 24m column pipe, complete in all respect with all required material, T&P and labour. |
| 27 | Xlpe insulated copper conductor cable size 2x3Cx16 sq mm. for submersible pump set. |
| 28 | XLPE insulated Al. armoured cable size 1x3.5cx35sq mm. from transformer LV side to meter panel and meter panel to starter. |
| 29 | Add 18 % GST Amount Please Enable Macros to View BoQ information |