| 1 | Item No.1 - Excavation for foundation in earth, soils of all types, sand, gravel, soft murum including shoring and strutting as necessary and disposing off excavated stuff as directed etc. complete. |
| 2 | Item No.2:-Providing and fixing 25mm diameter steel anchor dowel in hard rock including drilling hole of 32 mm diameter up to 0.75 mtrs depth, placing the dowel in position and effectively grouting the hole with CM 1:1 proportion etc. complete. |
| 3 | Item No.3:-Providing soling using 80 mm size trap metal in 15 cm. layer including filling voids with Crushed sand/grit, ramming, watering etc. complete. |
| 4 | Item No.4 - Providing and laying in situ / ready mix / ready mix M10 cement concrete of trap/ granite/ quartzite/ gneiss metal in foundation including necessary centering, formwork, bailing out water, compacting and curing etc. complete. (with fully automatic micro processor based PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand) |
| 5 | Item nO.5-Providing and laying in situ / ready mix controlled grade of M15 of trap /granite /quartzite /gneiss metal for RCC works in cut off walls / curtain walls including necessary scaffolding, centering, compacting by vibrator, finishing and curing etc. complete. (with fully automatic micro processor based PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand, excluding reinforcement) |
| 6 | Item No.6:-Providing and laying in situ / ready mix M-20 controlled reinforced cement concrete of trap metal for raft slab including \\"V\\" haunches, formwork, scaffolding, compaction by vibrating, finishing curing etc. complete. concrete batch mix plant / pan mixer with fine agreegates of required specifications (Natural sand / VSI sand finely washed etc ) etc. complete. (excluding reinforcement). a) RCC Grade with reversible drum type mixer/ concrete batch mix plant (pan mixer) . |
| 7 | Item No.7 - Providing and laying in situ / ready mix M-20 plain cement concrete of trap /granite/quartzite/ gneiss metal for cast in citu piers, abutment, returns, wings etc. including provision of \\"V\\" shaped false joints to form suitable panels on the faces to approve design with compacting by vibrating and curing complete, including plywood/steel form work centering ( excluding dewatering by means of pump) and including bailling out water and curing finishing in CM 1:3 etc. complete. as directed by engineer in charge basic rate shall be increased for height above 5.00 m in followinh manners |
| 8 | Item No.8 - Providing and laying in situ / ready mix controlled M-25 cement concrete of of trap / granite / quartzite/ gniess metal for reinforced cement concrete caps over piers and abutments including necessary sacffolding plywood/steel formwork, compacting by vibrating, finishing in CM 1:3 and curing etc complete ( Excluding reinforcement) With reversible drum type mixer/ concrete batch mix plant (pan mixer) . with Natural / VSI standard Artificial Sand |
| 9 | Item No.9- Providing and laying in situ / ready mix M25 controlled cement concrete of trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc. including ramming, vibrating, curing, formwork, centering and finishing in cement plaster excluding reinforcement etc. complete. (height up to 4 meter with fully automatic micro processor based PLC with SCADA enabled concrete batch mix plant / pan mixer with Natural / VSI standard Artificial Sand) |
| 10 | Item No.10 - Providing and laying weep holes of 100 mm diameter PVC pipes as per drawing for abutment returns, return walls etc. Complete. |
| 11 | Item No.11 - Providing expansion joints with 25mm thick bituminous pad as per detailed drawings etc. complete. |
| 12 | Item no.12:Providing railing of mild steel angle post 2.0m center to center of section 75mm x 75mm x 10mm or equivalent I/C section of height 1.05 above bridge surface with minimum anchor length of 30cm including hold fast of 25mm diameter MS bar welded at the bottom and concreting of 1:3:6 of size 30cm x 30cm x 30cm with three rows of 40mm B class GI pipe provided at 30cm on center to center including scaffolding and one coat of anticorrosive paint with two coats of oil painting, curing of concrete etc. complete. |
| 13 | Item No.13 - Providing, cutting, bending, hooking, tying and laying in position TMT FE 500 steel bars for reinforcement for all RCC works as per detailed drawings etc. complete. |
| 14 | Item No.14 - Providing and laying in situ / ready mix M20 RCC of trap/ granite/ quartzite/ gneiss metal for RCC work of ballast walls, kerbs and box returns including scaffolding, compaction, formwork finishing and curing etc. complete. (excluding reinforcement, with fully automatic micro processor based PLC with SCADA enabled concrete batch mix plant / pan mixer with Natural / VSI standard Artificial Sand) |
| 15 | Item No.15;-Providing and laying cement concrete wearing coat M30 grade with batch mix type / concrete mixer with SCADA including reinforcement as per drawings and technical specifications etc. complete with fine agreegates of required specifications (Natural sand / VSI sand finely washed etc ) |
| 16 | Item No.16 - Back filling behind abutment, wing wall and return wall as per drawings and technical specifications etc. complete. (by granular material) |
| 17 | Item nO.17:-Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with vibratory roller to the required density. By Mechanical Means -Grading I (Using Screening Type B (11.2 mm) Aggregate) |
| 18 | Item No.18 - Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting with Intelligent Compactor with compaction analyzer and V-Sat attachment. to the required density. Grading II (Using Screening Type B (11.2 mm) Aggregate) |
| 19 | Item No.19 - Providing 50 mm thick semi grout bituminous treatment including supplying all materials , prepairing the exisisting road surface,applying tack coat @ 0.735 kg / sqm and laying the required thickness of metal layer, heating and spraying bitumen of specified Grade at the rate of 2.75 kg / sqm , spreading chips and laying seal coat of specified Grade of bitumen of 1.25 Kg/sqm and compacting , making the surface good etc. complete (VG-30 bulk bitumen rates are considered to arrive at rates) |
| 20 | Item No.20 - Providing and fixing board displaying information, such as 'Name of work, Tender cost, Name of Contractor, Work completion and liability period etc', having rectangular shape of 1.20m x 0.90m size made out 18 gauge (1.25mm) thick mild steel sheet painted with one coat of Zinc chromate stoving primer and two coats of enamel paint on front side and grey stove enamel on back side and border / messages / symbols etc. with approved colour shade paint complete, on M.S.angle of size 35 x 35 x 3 mm frame with properly cross braced M.S. angles of size 35mmx35mmx3mm duly painted including Two M.S. angle iron posts of size 65 mm x 65 mm x 6 mm, 3.65 m long painted with alternate black and white bands of 25 cm width including all fixtures etc.and fixing the boards in 1:4:8 concrete block of size 60 cm x 60 cm x 75 cm including, excavation, refilling, transportation, and labour etc complete. Spec. No. As directed by Engineer in Charge |
| 21 | Item No21- Testing Charges of construction material Metal- sieve AnalysisStrength |
| 22 | Item No.22- Testing Charges of construction material Sand - Silt AND clay Content |
| 23 | Item No.23 - Testing Charges of construction material Concrete Cube M-25 - Compressive Strength |
| 24 | Item No.24 Testing Charges of construction material Bitumen - Penetration |
| 25 | Item No.25 Testing Charges of construction material Bitumen - Penetration |
| 26 | Item No.26 - Royalty Charges of materials |
| 27 | Item No.27 - Royalty Charges of materials |
| 28 | Add For 18 % G.S.T. Charges |
| 29 | Add For 1 % Labour Insurance |
| 30 | Add For 1 % S.Q.M.Charges Please Enable Macros to View BoQ information |