| 1 | Dismantling brick or stone masonry in lime or cement mortar under 3m. height including stacking the useful materials for reuse and removing the debris abate from worksite with all lead etc. complete as per direction of Engineer-in-charge |
| 2 | Earthwork exavation in all kind of Soil including dressing and levelling the bed and depositing the excavated materials away from the work site with all leads, lifts, sundries, T&P required for the work etc complete as directed by the engineer in Charge |
| 3 | Filling foundation and plinth with sand including cost, conveyance & royalty of all materials to the work site including watering & ramming with all leads, lifts, sundries & T&P etc. complete, as per direction of Engineer-in-Charge. |
| 4 | C.C. work of M-15 with 40 mm down graded hard granite crusher broken metal including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge |
| 5 | R.C.C. work of M-25 with 20 mm down graded hard granite crusher broken chips including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge. |
| 6 | C.C. work of M-20 with 12 mm down graded hard granite crusher broken metal including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge. |
| 7 | Supplying, Fitting & Placing uncoated HYSD bar Reinforcement complet as per drwaing & specification including cost of binding wire, cutting, bending & binding etc Complete as per the direction of Engineer in Charge |
| 8 | Rigid smooth centering & shuttering for C.C. work including false work and dismentaling them after casting including cost & conveyance of materials complete as per drawing & specification with all leads, lifts, sundries and T&P etc. complete as per the direction of Engineer-in-charge. |
| 9 | A) For Plinth Bend, Footing Base |
| 10 | B) For Floor & Roof Slab |
| 11 | C) For RCC Wall |
| 12 | Filling in foundation and Plinth with excavated materials with all leads, lifts and delifts incluiding watering, ramming etc complete as per direction of Engineer in charge. |
| 13 | Exavation of any typy of soil in approved borrow area by mechanical means loading into & transportation by mechanical means & unloading the soil with all lead on properly prepared surface including breaking clods to maximum 5cm to 7cm & laying in layers not exceeding 22.5 cm with all leads, lifts, sundries including cost, conveyance labour T&P etc. complete as directed by Engineer-in-charge. Please Enable Macros to View BoQ information |