| 1 | Dismentalling and removing cement concrete Including stacking, the useful materials for reuse and removing debris abate from worksite with all lead etc. complete as per direction of Engineer-in-charge.per the direction of Engineer-in-charge. |
| 2 | Earth work excavation of foundation in all kinds of soil including dressing & leveling the bed and sides and depositing the excavated materials away from work site with all leads, lifts, delifts, dewatering, sundries and T&P required for the work etc. complete as directed by the Engineer-in-charge. |
| 3 | Spreading watering and ramming sand for filling of approved quality on finished approved surface portion including cost, carriage, royalty and taxes of all materials to the work site with all leads, lifts, delifts with all other incidental charge etc. complete as per direction of the Engineer - in charge. |
| 4 | Cement concrete (1:3:6) with 40mm size hard granite crusher broken metal including cost, conveyance, royalty & taxes of all materials to the work site, mixing & laying of concrete in position & compacted properly with all leads, lifts, sundries, T&P required for the work, curing etc. complete as directed by Engineer-in-charge |
| 5 | Rigid smooth centering & shuttering for C.C. work including false work and dismentaling them after casting including cost & conveyance of materials complete as per drawing & specification with all leads, lifts, sundries and T&P etc. complete as per the direction of Engineer-in-charge. |
| 6 | Cement concrete (1:2:4) with 12mm hard granite crusher broken chips including cost, conveyance, royalty and other taxes of all materials to the work site, mixing and laying of concrete in position & compacted properly with all leads, lifts, sundries with all hire & running charges of machineries such as concrete mixer, vibrator etc. required for the work site with proper compaction and curing etc. complete as per the direction of Engineer-in-charge. |
| 7 | Suppling, fitting and placing uncoated HYSD bar reinforcement complete as per drawing and specification incluiding cost of binding wire,cutting bending, binding etc.completeas per the direction of Engineer-in-charge. |
| 8 | Providing weep hole in brick masonry/ stone masonry, plain reinforced concrete abutment, wing wall, return wall with 50 mm dia PVC pipe extending through the full width of the structures with slope of 1v:2H towrds drawing face complete as per drawing and as per the direction of Engineer-in-charge. |
| 9 | Supplying and fixing 15cm dia and 1m long guard posts of R.C.C. (1:2:4) using 7.5Kg. Of steel for each guard post with 12mm size H.G.C.B. chips including cost of all reinforcement and materials centering shuttering and watering carrying etc. complete as per direction of the Engineer -in charge. Please Enable Macros to View BoQ information |