| 1 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge |
| 2 | All kinds of soil 80% |
| 3 | Ordinary Rock 10% |
| 4 | Hard Rock (Requiring Blasting ) 10% |
| 5 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil |
| 6 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) |
| 7 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) |
| 8 | Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: Cement mortar 1:6 (1 Cement : 6 coarse sand) |
| 9 | Dry random rubble masonry with hard stone in foundation and plinth Without bond stone |
| 10 | Providing and laying damp-proof Course 50 mm thick with cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) and curing complete |
| 11 | Dumping stone including cost of stones in Horizontal on level |
| 12 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns |
| 13 | Hand-packing stones in wire-crates; excluding cost of crates and including cost of stones |
| 14 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. |
| 15 | Providing and laying non-pressure of specified class R.C.C. pipes including collars/spigot jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement: 2 fine sand) including testing of joints etc. complete. Non-pressure NP-3 class (Medium duty) R.C.C. pipes 1000 mm dia. R.C.C. pipe (laying by manual/mechanical means) |
| 16 | Supply of B.A. wire crates size 20' x 4' x 4' mesh size 4\\" x 4\\" dia of mesh 4mm |
| 17 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 18 | Consolidation of subgrade with power road roller of 8 to 12 tonne capacity including making good the undulations etc. with earth or quarry spoils etc. and rerolling the subgrade. |
| 19 | Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road / vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening /binding material to fill up interstices of coarse aggregate, watering and compacting to the required density. |
| 20 | Supplying and stacking at site Graded crushed stone aggregate of size 90 mm to 45 mm |
| 21 | Supplying and stacking at site Stone screening of size 13.2 mm nominal size (Type A) |
| 22 | Supplying and stacking at site Good Earth |
| 23 | Carriage of Materials |
| 24 | Sand for an Avg. distance of 23 Kms by MT |
| 25 | Stone aggregate above 40mm for an Avg. distance of 23 Kms by MT |
| 26 | Stone for an Avg. distance of 5 Kms by MT |
| 27 | Stone aggregate below 40mm for an Avg. distance of 23 Kms by MT |
| 28 | Pipe for an Avg. distance of 180 Kms by MT |
| 29 | Good Earth for an Avg. distance of 1 Kms by MT Please Enable Macros to View BoQ information |