| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed by EIC. All Kinds of soil |
| 2 | P/L of Soling / RBM Filling tightly hand packed i/c carriage charges and headload charges complete job. |
| 3 | Providing and laying in position cement concrete of specified grade Of 1:4:8 mix ( 1 cement : 4 coarse sand : 8 graded stone agg.40 mm nominal size excluding cost of centering and Shuttering all work up to plinth . |
| 4 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with. 1:1½:3 (1 cement :1½ coarse sand: 3 graded stone aggregate 20 mm nominal size) |
| 5 | Centering and shuttering including strutting, propping etc. and removal of form work for:Columns, piers, abutments, pillars, posts and struts |
| 6 | Engagement of Labour for dismantling old wooden work and its disposal all job complete |
| 7 | Providing beams including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with : Second class deodar wood |
| 8 | Providing beams/Planks/Railing including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with :Second class deodar wood all job complete incl. all labour charges for fixing |
| 9 | Providing jafri posts/Vertical posts/Runner including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with :Second class deodar wood all job complete incl. all labour charges for fixing |
| 10 | Dismantling old protection work including cutting of crates and stacking of stones |
| 11 | Supply and filling of Nallah Stones in Wire Crates including Knitting and wraping of crates of 4mm thick wire including all cost (Complete Job) |
| 12 | Filling of available Nallah Stones in Wire Crates including Knitting and wraping of crates of 4mm thick wire including all cost (Complete Job) |
| 13 | Applying priming coat:With ready mixed pink or grey primer of approved brand and manufacture on wood work (hard and soft wood) |
| 14 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade.Two or more coats on new work |
| 15 | Carriage Of Material By Mechnical Transport Sand/Bajri for an average lead of 50 km |
| 16 | Carriage Of Material By Manually for an average lead of 100Metre Sand/Bajri |
| 17 | Wood Please Enable Macros to View BoQ information |