| 1 | Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3 complete in all respects but excluding GST. |
| 2 | Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5 complete in all respects but excluding GST. |
| 3 | Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401. complete in all respects but excluding GST. |
| 4 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber, applying and brooming, stone screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. complete in all respects but excluding GST. |
| 5 | Construction of un-reinforced, without dowel jointed at expansion and construction joint, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days. using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501. complete in all respects but excluding GST. |
| 6 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203 P.C.C grade M 10 complete in all respects but excluding GST. |
| 7 | Providing and laying reinforced cement concrete in super structure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 R.C.C grade M 20 complete in all respects but excluding GST. |
| 8 | Supplying, fitting, and placing HYSD bar reinforcement in superstructure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 complete in all respects but excluding GST. |
| 9 | M-150 Brick on edge pavement on parties with bricks, laid dry joints filled with local sand including preparation of base to proper slope, and its ramming, spreading layer of 1 cm. (3/8\\") depth of local sand over the subgrade and including supply of all materials, labour Tools &plants etc. required for proper completion of the work. S.I. No. 763 complete excluding GST. |
| 10 | Supply & fixing of NP-3 class 350 mm dia RCC hume pipe (ISI mark) of following diameters including carriage, loading, unloading at site also including cost of hume pipes & collars & all taxes including laying in proper position & joint filling including cost of necessary jute & cement for proper complete in all respects but excluding GST. |
| 11 | Reinforced cement concrete M15 grade kilometre stone/local stone of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703. Ordinary Kilometer Stone (Precast) complete in all respects but excluding GST. |
| 12 | Reinforced cement concrete M15 grade kilometre stone/local stone (200 m stone (precast)) of standard design as per IRC:8 fixing in position including painting and printing, etc as per drawing and Technical Specification Clause 1703.200 m stone (precast) complete in all respects but excluding GST. Please Enable Macros to View BoQ information |