| 1 | Earth work in excavation in foundation, trenches etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level. In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc. Depth upto 1.5 m |
| 2 | Earth filling with available surplus soil excavated from foundations and taken only from outside of building plinth in layers not exceeding 20cm in depth, onsolidating each deposited layer including ramming and watering and consolidation with lead up to 50 m and lift upto 1.5 m. |
| 3 | Construction of embankment with approved material obtained from borrow pit with all lifts and leads, transporting to site, spreading, grading to required slope and compacting by vibratory roller 8-10 tonne to meet requirement of table 300-2 including cost of compensation for earth taken from private land complete as per MoRT&H specification clause 305. (Lead taken upto 5 km) |
| 4 | Filling with locally available river sand at all levels including watering ramming consolidating and dressing complete including cost of sand. |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering - All work upto plinth level : 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size). |
| 6 | Random rubble masonry with hard stone in foundation and plinth :Cement mortar 1:6 (1 cement : 6 coarse sand) |
| 7 | Random rubble masonry with hard stone in foundation and plinth : Cement mortar 1:4 (1 cement : 4 coarse sand) Extra for random rubble masonry with hard stone in superstructureabove plinth level and upto two stories |
| 8 | Brick work with FPS bricks of class designation 75 in foundation and plinth in:Cement mortar 1:4 (1 cement : 4 coarse sand) |
| 9 | Random rubble dry stone Kharanja (soling) under floor. |
| 10 | Centring and shuttering with plywood or steel sheet upto two stories or height upto 7.5 metre above plinth level including strutting, propping etc. and removal of form for : Lintels, beams, plinth beams, girders, bressumers and cantilevers. |
| 11 | Providing and laying structural plain/ reinforced cement concrete (design mix) of specified grade in substructure at all levels using concrete mixer and vibrator, including cost of form work, as per drawing and technical specifications complete as per clause 1500, 1700 and 2200 of MoRT&H specification including all material, labour, scaffolding etc. RCC Grade M -20 |
| 12 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto two stories excluding the cost of centring, shuttering, finishing and reinforcement: including Providing /mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar M-25 Grade Concrete (1:1:2 (1 cement : 1 coarse sand : 2 graded stone aggregate 20 mm nominal size) -As per design mix) |
| 13 | Centring and shuttering with plywood or steel sheet upto two stories ( each story of height upto 3.5 metre from floor level) including strutting, propping etc. and removal of form for : Suspended floors, roofs, landings, balconies and access platform. |
| 14 | Reinforcement with TMT bar in sub structure |
| 15 | Cement plastering including T&P, scaffolding, material and complete labpour, including cost of water, curing, racking of joints etc. with 20 mm cement plaster of mix : 1:4 (1 cement : 4 fine/ coarse sand) |
| 16 | Distempering with oil bound washable distemper of approved brand and manufacture to give an even shade New work (two or more coats) over and including priming coat with cement primer. |
| 17 | Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete |
| 18 | Providing and laying damp-proof course with cement concrete grade M-15 (1 : 2 : 4) mortar prepared with 1% solution of water-proof compound complete as per specification . including Providing/mixing of synthetic fibers compulsorily complying with IS 16481:2022 of 06 mm/12 mm length to be mixed @ 0.25% by weight of Cement i.e. 125 gms per 50 kg Cement up to 900 gms per cum of Concrete/ mortar.50mm thick. |
| 19 | Providing and fixing 1mm thick M.S. sheet door with frame of 40x40x6mm angle iron and 3mm M.S. gusset plates at the junctions and corners, all necessary fittings complete, including applying a priming coat of approved steel primer.Using M.S. angels 40x40x6 mm for diagonal braces. |
| 20 | Providing and fixing T-iron frames for doors, windows and ventilators of mild steel Tee-sections, joints mitred and welded with 15x3 mm lugs 10cm long embedded in cement concrete blocks 15x10x10 cm of 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) or with wooden plugs and screws or with dashfastener or rawl plugs and screws or with fixing clips or with bolts and nuts as require including fixing of necessary butt hinges and srews and applying a priming coat of approved steel primer. |
| 21 | P & F 1st quality Heavy Duty Vitrified Double Charged tiles on floor, skirting and steps etc.in different sizes (thickness minimum 10mm) with water absorption less than or equal 0.08% and conforming to IS 15622 of approved make in all colour and shade, laid with 20 mm thick CM 1: 4 including grouting the joints with white cement and matching pigment etc complete. size 600 mm X 600mm |
| 22 | Construction of septic Tank in all types of soil with 40 Cm. thick masonry in CM 1:6, 15 Cm thick C.C bed of 1:5:10, M- 15 grade C.C floor & RCC slab covering with M15 grade c.c. floor, 50 mm thick stone slab partition walls, 20 mm thick plaster in CM 1:6 finished with neat floating cement, 4 Nos stone foot rests of approved design ,two No. 450 mm dia each Ferro cement cover with frame, earth work etc. complete as per approved drawing including disposal of surplus earth within a lead of 50 mtr:-Size 230 x110 x150 cm.(for 20 users) with 115 mm thick RCC (M-20) slab with Tor steel reinforcement 10mm ϕ @15 cm c/c bothways including shuttering complete in all respect. |
| 23 | Grading roof for water proofing treatment with water proofing compound Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 24 | Providing and fixing water closet squatting pan (Indian type W.C. pan ) with 100mm sand cast Iron P or S trap, 10 litre low level white P.V.C. flushing cistern with manually controlled device (handle lever) conforming to IS : 7231, with all fittings and fixtures complete including cutting and making good the walls and floors wherever required :White Vitreous china Orissa pattern W.C. pan of size 580x440mm with integral type foot rests. |
| 25 | Providing and fixing white vitreous china flat back half stall urinal of size 580x380x350mm with white PVC automatic flushing cistern, with fittings, standard size C.P. brass flush pipe, spreaders with unions and clamps (all in C.P. brass) with waste fitting as per IS : 2556, C.I. trap with outlet grating and other couplings in C.P. brass including painting of fittings and cutting and making good the walls and floors wherever required :Single half stall urinal with 5 litre P.V.C. automatic flushing cistern. |
| 26 | Providing and fixing wash basin with C.I. brackets, 15 mm C.P. brass pillar taps,32 mm C.P. brass waste of standard pattern, including painting of fittings and brackets, cutting and making good the walls wherever require :White itreous China Wash basin size 630x450 mm with a pair of 15 mm C.P. brass pillar taps. |
| 27 | Providing and placing on terrace (at all floor levels) polyethylene water storage tank ISI : 12701 marked with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank |
| 28 | Electrical work cost =1% (As per Approved Technical Sanction) Please Enable Macros to View BoQ information |