| 1 | G- 3 -Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN Vibratory roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 with 45 -63 mm stone ballast as per Technical Specification Clause 404) Morth |
| 2 | Providing & applying primer coat with bitumen emulsion on prepared surface of granular base including cleaning of road surface and spraying at the rate of 0.60 kg/sqm using mechanical means as per Technical Specification Clause 502 Morth |
| 3 | Providing & applying Tack coat with bitumen VG-10 grade using emulsion pressure distributor at the rate of 0.30 kg per sqm on the prepared granular surface treated with primer & cleaned with Hydraulic broom as per Technical Specification Clause Morth &H 503 |
| 4 | Providing & laying of dense graded Bituminous 50mm thickMacadam with bitumen VG-30 Bulk with 100-120 TPH batch type hot mix plant producing on average output of 75 tonnes per hour using crushed aggregates of specified grading ,premixed with bituminous binder@ 4.0-4.50 percent by weight of total mix and filler,transporting the hot mix to work site,laying with a hydrostatic paver finisher wih sensor control to the required grade ,level and alignment and rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compaction as per clause MORTH specification clause 507 complete in all respects. |
| 5 | Providing & laying of Bituminous Concrete 30mm thickwith bitumen VG-10 Bulk with 100-120 TPH batch type hot mix plant producing on average output of 75 tonnes per hour using crushed aggregates of specified grading ,premixed with bituminous binder@ 5.4 to 5.6 percent of mix and filler,transporting the hot mix to work site,laying with a hydrostatic paver finisher wih sensor control to the required grade ,level and alignment and rolling with smooth wheeled vibratory and tandem rollers to achieve the desired compaction as per clause MORTH specification clause 509 complete in all respects. |
| 6 | Providing and applying 2.5 mm thick road marking strips (retro-reflective) of specified shade/color using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine fitted with profile shoe glass beads dispenser propane tank heater and profile shoe heater,driven by experienced operator on road surface including cost of material,labour,T&P,cleaning the road surface of all dirt seals,oil,grease and foreign materials etc. completeas per direction of E/I as per specification DSR 16.62 unit rate 747.80 x0.735x106/107 |
| 7 | Supply and fixing of road stud 100 x 100 mm die cast in aluminium,resistant to corrosive effect of salt and grit,fitted with lense reflectors,installed in concrete or asphaltic surface by drilling holes 30mm upto a depth of 600mm and beddded in asuitable bituminous grout or epoxy mortar ,all as per BS:873 part4 1973 |
| 8 | Excavation in foundation in ordinary soil I/C lift upto 1.50 M & lead upto 30 M I/C filling, watering & ramming of excavated earth into the tranches or into the plinth and removal of surplus earth as directed by engineer in charge.S.I. no.251 |
| 9 | Providing and laying in cement concrete 1:4:8 (1 cement :4 coarse sand{FM 2.20-3.60} : stone ballast of 40 mm nominal size) and curing complete,including supply of all material labour T&P etc. required for proper completion of the work, in foundation and floors.SI 281 |
| 10 | Cement concrete with 2 cm gauge grit approved stone ballast, approved coarse sand and cement in the proportion of 4:2:1 including supply of all materials, Labour and T&P etc. required for proper completion of the work.(S.I. No. 279i) |
| 11 | M-150 brick in 1:4 cement and Coarse sand morter in foundation and plinth including supply of all materials, labour and T& P etc. required for proper (SI No.305 |
| 12 | 12 mm thick plaster in 1:4 with cement and coarse sand mortar including supply of all materials, labour and tools & plants. required for proper completion of work. S.I. No.584(I )+Diff |
| 13 | Concrete with 4 cm.Gauge brick ballast fine sand of 1.25 FM in proportion of 1:6:12 and cement in foundation and under floors, including supply of all materials, labour and tools & plants. Royalty etc. required for the proper completion of the work. S.I. No.273 |
| 14 | Dismantling old existing plaster including disposal of refuse as directed by the Engineer-in charge with in a distance of 60 metre(S.I. No. 706) |
| 15 | R.C.C. work with cement approved coarse sand and 2 cm.gauge approved stone grit in the proportion of 1:2:4 in beams & slabs excluding supply supply of reinforcement but including fixing & binding the same with 24 B.W.G. G.I. wire and including the cost of binding wire and including supply of all materials, labour and tools & plants. Royalty etc. required for the proper completion of the work. S.I. No.284 |
| 16 | Mild steel or iron work in plain work such as reinforced concrete or reinforced brick work(when not included in overall rates) wrought to required shape as necessary including bending for proper completion of the work including supply of steel wastage beads, hooks and authorized overlapping shall be measured. S.I. No.504 |
| 17 | Dismantling of old damaged A.C sheets and including stacking of materials as per direction E/I DSR 15.28.2 |
| 18 | S/F 6mm thick corrugated asbestos sheet including all necessary T&P etc required for proper completion of work DSR 12.8 (Dsr unit rate 536.40 x0.735x106/107) |
| 19 | S/F of A.C ridge including supply of all materials, labour and tools & plants. required for proper completion of work. DSR 2023 12.12.1 (Dsr unit rate 522.95x0.735x106/107) |
| 20 | Mild steel or iron work in heavy sizes such as trusses ,built up gates,doors,frames,record racks,roof work,gates etc. wrought to required form including drilling holes,rivetting or welding where necessary and also including supply of steel, bolts , nutsetc. & fixing reduired for proper completion of the work. SI 503 |
| 21 | Dismantling cement concrete floor including stacking of dismantled materials as directed by E/I in all Complete SI No 697 |
| 22 | Dismantling Brick work including disposal of refuse as directed by the Engineer-in charge with in a distance of 60 metre(S.I. No. 692) |
| 23 | Dismentling of roof concrete including stacking of dismantled materials as directed by the Egineer -in-charge withing distance of 60 mtr SI 696 |
| 24 | Deduct Cost Of Brick |
| 25 | Deduct Cost Of Brick Bats |
| 26 | Painting two coat over priming coat (encluding cost of prime coat) on steel and other metals surface with superior synthetic enamel standard make brushing to give an even shade and finish and including cleaning the surface of all dirt, dust and other foreign matters sand papering and stripping including cost of all materials, labor and T&P etc. for proper completion of the work ( S.I.3i+4i) |
| 27 | Finishing walls with two coat of water proof cement paint of approved quality of previously old treated surface with this paint to give an even shade including supply of all materials ,labour,and T&P required for proper completion of the work .SI 2x662 |
| 28 | P/L glass strips 3.15 mm thick and 3.5 cm depth joints of floors skirting dado at time of laying floors flush with floor level including supply of all material labour and T&P etc. required for proper completion of work (631b ) |
| 29 | R.C.C. work with cement approved coarse sand and 2 cm.gauge approved stone grit in the proportion of 1:2:4 in Raft foundation, excluding supply supply of reinforcement but including fixing & binding the same with 24 B.W.G. G.I. wire and including the cost of binding wire and including supply of all materials, labour and tools & plants. Royalty etc. required for the proper completion of the work. S.I. No.287 |
| 30 | R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit im the proportion of 1:1.5:3 in columns including supply of all materials, labour and tools and plants etc, required for proper completion of the works. strength of the concrete shall not be less than SI 288 |
| 31 | Finishing walls with Water Proofing cement paint of required shade : New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20Kg /10 sqm) SI 13.46.1 |
| 32 | scraping old white or colour wash including disposal of refuse as directed by E/I within distance of 60 mtr.SI 708 |
| 33 | Providing& Fixing of M.S. Wire mesh (Murga Jali) |
| 34 | Providing and applying fibre reinforced elastomeric liquid water proofing membrane with resilient acrylic polymers having Sun Reflectivity Index (SRI) of 105 on top of concrete roof in three coats @10.76 litre/ 10 sqm. One coat of self-priming of elastomeric waterproofing liquid (dilution with water in the ratio of 3:1) and two coats of undiluted elastomeric waterproofing liquid (dry film thickness of complete application/system not less than 500 microns). The operation shall be carried out after scrapping and properly cleaning the surface to remove loose particles with wire brushes, complete in all respect as per the direction of Engineerin- Charge.D.S.R.22.22A 2023 unit rate =563.10x0.735x106/107 |
| 35 | Supply and fixing rolling shutters of approved make made of 80×120mm cold rolled M.S.latch locked through out their entire length and mounted on specially deigned pipe shall with brackets side guides and arrangement for inside and out side locking with push and pull operation complete but including the cost of top cover 1.2 mm thick and springs including all complete (S.I.520) |
| 36 | Providing/fixing top cover for rolling shutter including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work. (S.I 522) |
| 37 | Providing /fixing 27.5 cm long wire spring grade no.2 rolling shutter including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work. (S.I 521) |
| 38 | Providing and laying vitrified floor tiles in different sizes (thickness to be specified by the manufacturer) with water absorption less than 0.08% and conforming to IS: 15622, of approved make, in all colours and shades, laid on 20 mm thick cement mortar 1:4 (1 cement : 4 coarse sand), jointing with grey cement slurry @ 3.3 kg/ sqm including grouting the joints with white cement and matching pigments etc., complete.as per Chap.14 SOR 11.41.2 Size 600mmX600mm |
| 39 | Distemper Two coat with oil bound distemper of approved brand manufacture and required shade on decorated wall surface to give an even shade over and including a priming coat with cement primerof approved brand and manufacturer as of british,shalimar,asian paints,after throughly brushing surfaces free from mortar droppings and other foreign matter and also including preparing the surfaces even also sand prepared smooth including cost of all materials on Previously old distempered surfaceSI 650+651 |
| 40 | P/F of flyproof galvanized mosquito MS wire gauge to windowsand celerestory windows using wire guage with average width of aperture 1.4mm in both directions with wire of dia.0.63mm all complete with second class teak wood beading 62x19 mm as per Chap 09 SOR 9.51.1 |
| 41 | S/F of flush door 32 mm thick commercial Quality conforming to I.S. 2202 part I (1983) including Fixing of wooden cleats and stoppers and including fixing and adjustment of hinge bolls locks handle springs fitting with necessary screws. (470i) |
| 42 | Providing wood work in frames of doors,windows,clesrestory windowsand other frames ,wrought framed and fixed in position Sal wood as per DSR 9.1.2 |
| 43 | Providing and fixing water closet squatting pan ( Indian type W.C. pan ) with 100mm sand cast Iron P or S trap, 10 litre low level whiteP.V.C. flushing cistern with manually controlled device (handle lever) conforming to IS:7231,Parryware/Hindware/Seabird/Orient (Coral) with all fittings and fixtures complete including cutting and making good the wallsand floors wherever required.White Vitreous china Orissa pattern W.C. pan of size 580x440mm with integral type foot restsmaterials, labour etc Chap 22 SOR . 17.1.1 |
| 44 | Providing and fixing white vitreous china pedestal type water closet (European type W.C. pan) with seat and lid, 10 litre low level white P.V.C. flushing cistern, including flush pipe, with manually controlled device (handle lever), conforming to IS : 7231, with all fittings and fixtures complete, including cutting and making good the walls and floors wherever required : 17.2.1 W.C. pan with ISI marked white solid plastic seat and lid.Chap22 17.3.1 |
| 45 | Cleaning work of septic tank and disposal of sludge comlete in all respect as per direction of E/I. |
| 46 | Providing and fixing 600x450mm bevelled edge mirror of superior glass of approved quality complete with 6mm thick hard board ground fixed to wooden cleats with CP brass screws and washers complete Chap 22 17.31 |
| 47 | Providing and fixing of 100mm dia P.V.C down pipe including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work. (S.I 730) |
| 48 | Providing and fixing 15mm dia B Class ISI marked G.I. Pipe completes with GI Specials such as bends tee, sockets, cross, clamp etc. Earth work including filling of the trenches required for proper completion of work. The rate also includes concealed fittings wherever required cutting and making good the floor, R.C.C. and the walls etc. The rate also includes supply of all materials, labour and tools and plants etc.Chap 22 SOR 18.10.1 |
| 49 | Supplying and fixing of Brass bib cock 15 mm dia Long Body including supply of all materials, labour and tools & plants. and including threading of the pipe if required for proper completion of work Chap 22 SOR 18.15.1 |
| 50 | Supplying and fixing of Brass stop cock 15mm dia including supply of all materials, labour and tools & plants. and including threading of the pipe if required for proper completion of work Chap 22 SOR 18.16.1 |
| 51 | Providing and fixing full way gate valve15 mm dia with wheel ISI marked heavy quality including supply of including supply of all materials, labour and tools & plants. required for proper completion of work Chap 22 SOR 18.18.1 |
| 52 | Supply andFixing 6mm china white glazed in flooring or skirting dado laid with 1:3 cement and approved coarse sand mortar finished white cement slurry jointing and polishing complete including supply of all material labour and T&P etc. required for prer completion of the work SI 628 |
| 53 | Providing and fixing rectangular high density polyethylene water storage loft tank with cover, conforming to ISI : 12701, colour of opaque white or as approved by Engineer-in-charge. The rate includes making necessary holes for inlet, outlet & over flow pipes. The base support Including fittings & fixtures for tank shall be paid separatelyChap.22 18.48 |
| 54 | Providing and fixing Stainless Steel A ISI 304 (18/8) kitchen sink as perIS:13983 with C.I. brackets and stainless steel plug 40 mm, includingpainting of fittings and brackets, cutting and making good the wallswherever required :17.10.2 Kitchen sink without drain board610x460 mm bowl depth 200 mm As per DSR 2023 17.10.2 unit rate =3873.80x0.735x106/107 |
| 55 | M-150 class brick work in 1:6 cement and coarse sand mortar in foundation and plinth including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work..S.I. no.303 |
| 56 | M-150 class one brick thick wall brick work in 1:4 cement and coarse sand mortar in super Structure including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work. S.I. No.305+ 309 |
| 57 | M-150 class one brick thick wall brick work in 1:6 cement and coarse sand mortar in super Structure including supply of all materials, labour and tools & plants. etc. required for the proper completion of the work. S.I. No.303+ 309+310 |
| 58 | M-150 Brick work in 1:4 one cement and 4 coarse and mortar in super structure for walls of half brick thick including necessary cutting & moulding of materials,labour and tools and plants etc. Required for proper completion of work.S.I. 305+309+310 A |
| 59 | Earth filling in plinth including supply of necessary of earth upto 3 km distance. Including watering dressing etc. Labour and T & P etc. Required for proper completion of work.(S.I 253 + cartage ) |
| 60 | Sand filling in plinth including supply of necessary quantity of sand from ganga River including watering dressing wtc. Labour and T & P etc. Required for proper completion of work.(S.I.255) |
| 61 | R.C.C work with cement approval coarse sand and 2cm gauge stone grit in proportion of 1:2:4 in lintels of door & windows excluding supply of reinforcement and its bending but including its fixing and blinding the with 24 B.W.G.G.I binding wire and excluding cost of centering and shuttering and supplyof all materials, labour and tools and plants etc. Required for proper completion of the work as per ( S.I.283 |
| 62 | R.C.C. work with cement approved coarse sand and 2 cm.gauge approved stone grit in the proportion of 1:2:4 in beams & slabs excluding supply supply of reinforcement but including fixing & binding the same with 24 B.W.G. G.I. wire and including the cost of binding wire and including supply of all materials, labour and tools & plants. Royalty etc. required for the proper completion of the work. S.I. No.285 |
| 63 | R.C.C. work with cement approved coarse sand and 20 mm. guage approved stone grit im the proportion of 1:1.5:3 incolumns excluding supply of reinforcement and its fixing and binding the same with 24 BWG binding wire and including necessary centering and shuttering etc.and also including supply of all materials, labour and tools and plants etc, required for proper completion of the works. strength of the concrete shall not beless than M-200. S.I. No.289 |
| 64 | 12 mm thick plaster same as per item No.(21) but on rough face with 1:4 (one cement and four coarse sand) mortar including supply of all materials labour tools & plants requires for proper completion of work.(S.I.584 (1)+596 |
| 65 | Dismantling R.c.c work including stacking of material as directed by E.I. S.I. 694 |
| 66 | Distemper Two coat with oil bound distemper of approved brand manufacture and required shade on decorated wall surface to give an even shade over and including a priming coat with cement primerof approved brand and manufacturer as of british,shalimar,asian paints,after throughly brushing surfaces free from mortar droppings and other foreign matter and also including preparing the surfaces even also sand prepared smooth including cost of all amterials SI 649+650 |
| 67 | Painting two coat over priming coat (including cost of prime coat) on steel and other metals surface with superior synthetic enamel standard make brushing to give an even shade and finish and including cleaning the surface of all dirt, dust and other foreign matters sand papering and stripping including cost of all materials, labor and T&P etc. for proper completion of the work.Chapter No.15 Page 36 SI 1+2+4i |
| 68 | Providing and laying Brick bat coba integal cement based waterproofing treatment including preparation of surface as required for treatment of roofs, balconies, terraces etc consisting of following operations: a) Applying a slurry coat of neat cement using 2.75 kg/sqm of cement admixed with waterproofing compound conforming to IS: 2645 and approved by engineer-in-charge over the RCC slab including adjointing walls up to 300 mm height including cleaning the surface before treatment. b) Laying brick bats with mortar using broken bricks/brick bats 25 mm to 115 mm size with 50% of cement mortar 1:5 (1 cement : 5 coarse sand) admixed with water proofing compound conforming to IS : 2645 and approved by Engineer-in-charge over 20mm thick layer of cement mortar of mix 1:5(1cement : 5 coarse sand) admixed with water proofing compound conforming to IS:2645 and approved by engineer-in-charge to required Sqm - 1050.00 New B Providing and laying waterproofing treatment in sunkeri portion of WCs,Bathroom etc. by applying cement slurry mixed with waterproofing cement compound consisting of applying: a) First layer of slurry of conforming to IS:2645 and approved by engineer-in-charge to required slope and treating similarly the adjointing walls up to 300mm height including rounding of junctions of walls and slabs. c) After two days of proper curing applying a second coat of cement slurry using 2.75 kg/sqm of cement admixed with water proofing compound conforming to IS:2645 and approved by Engineer-in-charge. d) Finishing the surface with 20mm thick joint-less cement mortar of mix 1:4(1 cement : 4 coarse sand) admixed with waterproofing compound conforming to IS:2645 and approved by engineer-in-charge inlcuding laying glass fibre cloth ofapproved quality in top layer of plaster and finally finishing the surface with trowel with neat cement slurry and making pattern of 300x300 mm sq. 3mm deep. e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and for final test.All above operations to be done in order and as directed and specifed bythe engineer-in-charge. With average thickness of 120mm and minimum thickness at khurra as 65mm. NOTE :- It is suggested that this method should be adopted after ensuring the structural safety of the structures New Item Chap No.11 |
| 69 | M.S.or iron work in Z-section in ventilator including of all materials labour tools & plants etc...comp.(Chap-10 Sl no.502b) |
| 70 | same as SOR item no 502 but of fabrication of grill SI 502 C |
| 71 | S/F glass pans 4 mm thick of approved quality with brand and putty for window and ventilator mann section or wherever required on other places including cartage of all itemsAs per DSR 2023 14.5.1 unit rate 1090.65x0.735x106/107 |
| 72 | 4.0 cm thick 1:2:4 plain cement concrete floor with cement, approved coarse sand and 2.0 cm graded approved stone shingle laid in panels finished with 3.0 mm floating coat of neat cement or cement and marble dust in 5:1 as specified and removing any overlapping mortar at the joints of panels if any and giving them a uniform finish including supply of all materials, labour and T&P etc. required for proper completion of the work (SI 605+analysis) with 15cm base concrete |
| 73 | 18mm thick cement plaster in dado or skirting upto 30cm in height in 1:3 consisting of one part of cement and 3 parts of app c/sand with floating coat of neat cement as per DSR2023 11.6.1 (Dsr unit rate 662.05x0.735x106/107) |
| 74 | Engraving lines in the plaster of outer face wall vertically and horizontally to display the surface as stone facing as directed by E/I including labour and all T&P etc required for proper completion of the work.SI 598 |
| 75 | Providing and fixing in 4mm thick A.C. Sheet 09cm deep in joint at the time of laying floors flush with floor level including for proper completion of the work.) |
| 76 | Cleaning of Over head RCC tank at all heights with coconut brushes, duster etc., removal of silt, rubbish from the tank and cleaning the tank with fresh water disinfecting with bleaching powder @ 0.5gm per litre capacity of tank including disposal of rubbish as per direction of E/I complete in all respect |
| 77 | 12 mm thick plaster with cement and approved coarse send in 1:3 ovet brick work minimum thickness not to be less than 3/8” 1½x1½x¼ (10 mm thick) including supply of all material labour and T&P etc. required for proper completion of the work SI No. 583 |
| 78 | P/L Neat cement punning on ceiling and R.C.C. column grouting work etc. 13.18 |
| 79 | Maintenance of Bituminous surface road and gravel or WBM road including filling pot holes and patch repair etc. restoration of rain cuts and dressing of side slop standing tree at adjacent to road wherever cutting of branches of tree, shurb and traimming of grass and weeds etc mentioned in GO No.55 12022/187/23-9-2022-02 Nabard / 2021 Dt 28.04.2022 & Enc letter No. 14 BDD-1 (NH)/40 MT-11/ 2024 Dated 03.01.2024 subjected to approval from Govt. maintence of 1st Year after completion of work @ Zero % of Total PC work amount of first Year @ 0.00% of Total Work Amount of Hotmix area |
| 80 | Maintainance of Second Year @ 0.25% of Total Work Amount of Hotmix Area |
| 81 | Maintainance of Third Year @ 0.50% of Total Work Amount of Hotmix Area |
| 82 | Maintainance of Forth Year @ 0.75% of Total Work Amount of Hotmix Area |
| 83 | Maintainance of FifthYear @ 1.00% of Total Work Amount of Hotmix Area Please Enable Macros to View BoQ information |