| 1 | Carriage loading and unloading of PCC/ ST Poole from ESC store Unnao/Sub Station Store/ other site to site work as per required and vice versa. |
| 2 | Carriage all type Loose line material from ESC store Unnao/Sub Station Store/ other site to site work as per required and vice versa. |
| 3 | Dismantling of old damaged pole/ Double Pole and X-arms, brackets, Insulators, Channels and all hardware fittings. |
| 4 | Erection of new PCC/ST Pole fitting of X-Arms, brackets insulators and other hardware fittings. |
| 5 | Erection of Double Pole Structure including digging of pit and fitting of all accessories complete. |
| 6 | Placement of 33/11/0.4 KV T/F on Double Pole and Installation cable termination and commissioning of 25/63/100 KVA Transformer including dressing damaged cable, lugs, Jumpering & connecting Earthing of body & neutral as per required. |
| 7 | Dismantling re-usable Old Pole from site to site and their erection and fitting of X-Arms, brackets insulators and other hardware fittings etc. |
| 8 | Dismantling/ Laying / Repairing of Aerial Bunched Cable from L.T.O/H line (to be replaced/damaged) |
| 9 | Digging of cable trench approx. 1200x1200 mm by JCB/kachha road/pakka road for suitable size for damaged cable joints/ new cable laying |
| 10 | Opening and reconnection of consumer connections for shifting or replacement of pole. |
| 11 | Re-sagging of conductor, on old line after erection/repair of pole, binding of conductor etc. |
| 12 | Opening of H.T. / LT Jumpers/ Re-Jumpering from the exiting H.T.O.H./ L.T. O.H. line for erection work. |
| 13 | Supply and Fixing Holding clamps for PCC/STP with Nuts & Bolts. |
| 14 | Supply and Fixing Stay clamps for PCC/STP with Nuts & Bolts. |
| 15 | Supply and Fixing F Clamps clamp for PCC/STP with Nuts & Bolts. |
| 16 | Excavation of foundation and taken out the damaged pole/pole to be shifted from the ground. Repairing of rotted bottom of STP by welding MS sheet /3 nos, MS angles of size 45X45X6 MM 750 MM long as per site condition. |
| 17 | Grouting of pole with cement brick ballast and coarse sand as per standard specifications. |
| 18 | Fabrication/ Modifications of MS Items/Nuts & Bolts as per requirement of site conditions. |
| 19 | Fixing of Stay Rod and its erection and grouting by fitting of stay clamp. Stay wire and its proper binding and tightening etc. |
| 20 | Repositioning of tilted PCC pole. |
| 21 | Chopping of tree branches lying in the route of exiting line touching the tree branches to the phase line conductor as per requirement of site. Please Enable Macros to View BoQ information |