| 1 | Civil Work |
| 2 | Surveying, Design (hydraulic & structural) and construction of RCC Infiltration Well cum pump house as per latest BIS codes of Capacity 650 lpm clear water discharge at the right bank of Lohawati river including Approach bridge, hydraulic / structural design drawing from competent authority, all materials, labours, T&P etc complete in all respect including excavation, refilling & removal of surplus soil. |
| 3 | Excavation of earth for pipe line in following strata lift upto 1.5m lead upto 30m including refilling, watering, ramming of excavated earth into the trenches and removal of surplus earth upto a distance of 60m from trenches including supply of labour, T&P etc complete. |
| 4 | Soil Mixed with Boulder |
| 5 | In Hard Rock |
| 6 | Providing carting, laying, welding of following sizes plain ended MSERW pipes confirming IS: 3589 or equivalent specifications, minimum Grade YST 330 including cutting of pipe by gas cutter, welding of flanges on pipes, making bend, tees, reducers,enlargers etc wherever necessary & including hydraulic testing, welding materials, electric generator, transformer, fuel & lubricants, chain pulley, tripod, labours etc required for proper completion of work in all respect. |
| 7 | 100 mm dia., 4.8 mm thick |
| 8 | 100 mm dia., 5.6 mm thick |
| 9 | 100 mm dia., 6.0 mm thick |
| 10 | Supply and Carting, laying, jointing and testing of following sizes screwed and socketed pipes confirming IS:1239 (Part-I) specifications. Including hydraulic testing, cutting and threading, specials etc. complete in all respect. |
| 11 | GI Pipe 50 mm dia (Medium Quality) |
| 12 | GI Pipe 50 mm dia (Heavy Quality) |
| 13 | Supply and fixing of the G.M Gate valves including cartage of materials, labour, T & P etc complete |
| 14 | 50 mm dia |
| 15 | Supply and fixing of the Air valves (Screwed) including cartage of materials, labour, T & P etc complete |
| 16 | 20 mm dia |
| 17 | Providing & Fixing Ultrasonic Water Flow Meter for Bulk pipe lines. Inline type, flange end with Integral mounted, flow rate & Totaliser display, Battery operated (with five year battery life) communication: UART/ RS485, suitable against antifraud attempts etc. including all necessary fittings complete. 50 mm dia. Supply & fixing of Cast steel Sluice and Scour Valve |
| 18 | 100 mm dia., W.P. = 15 Kg/cm2 |
| 19 | 100 mm dia., W.P. = 30 Kg/cm2 |
| 20 | 100 mm dia., W.P. = 50 Kg/cm2 |
| 21 | Providing & Fixing Ultrasonic Water Flow Meter for Bulk pipe lines. Inline type, flange end with Integral mounted, flow rate & Totaliser display, Battery operated (with five year battery life) communication: UART/ RS485, suitable against antifraud attempts etc. including all necessary fittings complete. 50 mm dia. Supply & fixing of Cast steel Reflux / Swing Check Valve |
| 22 | 100 mm dia., W.P. = 15 Kg/cm2 |
| 23 | 100 mm dia., W.P. = 30 Kg/cm2 |
| 24 | Supply & fixing of 50 mm dia. Cast steel Double Ball Air Valve Flanged type, W.P. 15 Kg/cm2 |
| 25 | Supply & fixing of 50 mm dia. Cast steel Double Ball Air Valve Flanged type, W.P. 30 Kg/cm2 |
| 26 | Painting of MSERW/API Pipes with 2 coats of approved quality. (Anti-Corrosive paint over one coat of Primer) (dia. of pipe in mm) |
| 27 | 100 mm dia |
| 28 | Supply of all materials, labour, T & P etc. and Construction of Sluice Valve / Reflux Valve / Scour Valve Chamber as per type design complete (Size :- 1.50 m x 1.50 m x 1.50 m) |
| 29 | Supply of all materials, labour, T & P etc. and Construction of Air Valve Chamber as per type design complete (Size :- 1.50 m x 1.50 m x 1.50 m) |
| 30 | Supply of all materials, labour, T & P etc and construction of Wheel Valve chamber as per type, design (Size :- 1 m x 1 m x 1 m) |
| 31 | Supply of all materials, labour, T & P etc and construction of Air Valve chamber as per type, design (Size :- 1 m x 1 m x 1 m) |
| 32 | Supply of all materials, labour, T & P etc and construction of BPT as per type design drawing. |
| 33 | Supply of all materials, labour, T & P etc. and Construction of Anchor Block as per type design complete of following sizes: |
| 34 | Size - 0.5m x 0.5m x 0.7m |
| 35 | Size - 0.6m x 0.6m x 0.9m |
| 36 | Supply of all materials, labour T&P etc and construct following sizes RCC semi sunk circular CWR including hydraulic testing, fixing of inlet, outlet, washout & overflow G.I. pipes / specials of suitable dia, structural design & drawing from competant authority complete in all respect including excavation, refilling & removal of surplus soil. |
| 37 | 20 KL |
| 38 | 35 KL |
| 39 | 150 KL |
| 40 | Supply of all materials labour T&P etc and install chlorinating chamber as per type design and drawing complete including supply and installation of bucket type chlorinatpr of 25 liters capacity. |
| 41 | Supply of all materials, labours, T&P etc and construct Pump House of 9.0 m X 6.0 m X 4.5 m internal size including construction of platform for pumps & moters, supporting pillers, cable trenches as per structural design & drawing from competant authority complete in all respect including excavation, refilling & removal of surplus soil. |
| 42 | Supply of all materials, labour and T & P etc. and construction of Staff Quarter (Type I) for Pump Operators and Chaukidar as per structural design & drawing from competant authority complete in all respect including excavation, refilling & removal of surplus soil. |
| 43 | Dismantling of following existing road pavement for laying different sizes of pipes, stacking the serviceable materials and disposal of waste materials upto a distance of 30 m including supply of materials, labour, T&P etc. complete |
| 44 | Bituminous road (Single Layer) |
| 45 | CC Road |
| 46 | Construction charge to Non PWD road cutting of following road pavement (which was dismantled during execution of works) after laying of different sizes of pipes and disposal of debris if any upto a distance of 60 m including supply of all materials labour, t&p etc. complete |
| 47 | Construction 3m wide Cement concrete approach path including necessory cutting, excavation protection for making grade 1:20 from main road to pump house link road |
| 48 | Excavation for Protection Work/Site Devlopment etc.in following type of soil: |
| 49 | Soil mixed with boulders |
| 50 | Providing and laying in position cement concrete of specified grade including the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size). including supply of all material,labour,T&P etc.required for proper completion of work. |
| 51 | RR Stone Masonry 1:6 including supply of all materials, labour, T&P etc. complete |
| 52 | RR Stone Masonry laid dry including supply of all materials, labour, T&P etc. complete |
| 53 | Supply and fixing wire crate for the protection of well and filter media Wire crate check 3.0 mx1.5 mx 1.5 m (GI wire 8 gauge BWG) |
| 54 | Construction of 1.5m high boundary wall around pump station & reservoir site complete including excavation, refilling & removal of surplus soil. |
| 55 | Provision of Barbed Wire Fencing through angle iron posts around the water works site on the top of Boundary Wall. |
| 56 | Provision for Iron Gate with two pillars complete. |
| 57 | 3.60m wide gate |
| 58 | Following Source Sustainability Works in the vicinity of water catchment area of water sources: |
| 59 | Dry Stone Check Dam 8m long |
| 60 | Dry Stone Check Dam 4 m long |
| 61 | Contour trenches 3.0 mx0.3mx0.30 m in size |
| 62 | Chal khal 3.0 mx2.0m x2.0m in size |
| 63 | R.R 1:6 stone masonary check dam 8m long |
| 64 | Wire crate check dam |
| 65 | E&M Work |
| 66 | Infiltration Well (Stage-I) |
| 67 | Supply of Submersible pumping plant to deliver 400LPM 50Mtr. head |
| 68 | Supply of Fully automatic auto transformer starter as per Specification and site requirement |
| 69 | Control panel for above pump set as per site requirment |
| 70 | Supply of Power Wiring material as per Specification and site requirement as below.(i) 10 Sq.mm. 1X2 Rx3 core submersible cable-150Mt.(ii) 25 Sq. mm. 1X3.5core Al. Armourd cable-70Mt.(iii) Jointing material- 02 Set |
| 71 | Earthing Material as per IE Rules |
| 72 | MAIN PIPING AND VALVES as per site requirement/specification. |
| 73 | GAUGES with fittings as per site requirement |
| 74 | Supply of following tools required for maintenance of pumping plants. |
| 75 | Supply of rubber resistance sheet of size 1m x 2m x 0.025m |
| 76 | 20 KVA Servo Control Voltage Stabilizer |
| 77 | 100 Amp TPN main switch 3 phase 415 V, 50c/s.AC with complete. |
| 78 | Chain Pulley 3 Tonne capacity 12 Mtr lift |
| 79 | Solar Power Plant of 7.50 kw for campus to provide lights etc. electrification complete fitting works each stages of pump house with Net metering. for I-Well Pump house |
| 80 | Installation and Commissioning of 02 Sets Pumping Plants with 01 Month Trial Testing and 05 months running Operation & Maintenance work at site all acessories inside the pump house( without civil works such as laying and casting of foundations, cable trenches etc |
| 81 | Following Source Sustainability Works in the vicinity of water catchment area of water sources: |
| 82 | At Works |
| 83 | At Site |
| 84 | Painting of entire installation with 2 coats of super enamel paint as per direction of Engineer-Incharge of works |
| 85 | Intenal and external electrification of pump house, staff quarters and campus complete fitttings etc |
| 86 | Cartage of Pumping Plants and all acessories from store to site of work including head load charges from road site as required.to pump house site works complete.(Carting Upto Sites.) - |
| 87 | IPS-I |
| 88 | Supply of Electric driven horizontal Multi stage centrifugal clear water pump capable of delivering 400LPM discharge against a total head of 320m complete with coupling and coupling guards of all accessories. (01 No. running & 1 No. as stand by with 1 No. spare Pump Set)Supply of 45KW TEFC type 4 Pole Electric Motor squirrel cage 2900RPM suitable to operate on 415 +/- 10% Volts, 3 Phase, 50 Hz AC.Supply of MS fabricated heavy duty base plate for mounting above Pump and Motor |
| 89 | Supply of fully automatic air cooled VFD based starter for 60HP/45KW suitable to control above motor with overload & under voltage protections. |
| 90 | Supply of Control Panel as Per Specification and site requirement. |
| 91 | Supply of Power Wiring material as per Specification and site requirement as below.(i) 25 Sq.mm 1x3Rx3 core cu. cond. Armoured cable- 200Mt.(ii) 50 Sq.mm 3.5core Cu. Cond. Armourd cable-70Mt.(iii) Jointing material such as lugs, tape etc. |
| 92 | Earthing Material as per IE Rules |
| 93 | MAIN PIPING AND VALVES as per Specification and site requirement. |
| 94 | GAUGES as per Specification and site requirement. |
| 95 | Supply of following tools required for maintenance of pumping plants. |
| 96 | Supply of rubber resistance sheet of size 1m x 2m x 0.025m |
| 97 | 120KVA Servo Voltage Stablizer |
| 98 | Chain Pulley 3 Tonne capacity 4.5 Mtr lift |
| 99 | Solar Power Plant of 7.50 kw for campus to provide lights etc. electrification complete fitting works each stages of pump house with Net metering.for Stage -I |
| 100 | Installation and Commissioning of Pumping Plants with acessories inside the pump house but without civil works such as laying of foundations, cable trenches etc. |
| 101 | Testing of Pumping Plants against guaranteed figures of 'Schedule E' |
| 102 | At Works |
| 103 | At Site |
| 104 | Painting of entire installation with 2 coats of super enamel paint as per direction of Engineer-Incharge of works |
| 105 | Intenal and external electrification of Infiltration Well pump house, staff quarters and campus complete fitttings etc |
| 106 | Cartage of Pumping Plants and all acessories from store to site of work including head load charges from road site as required.to pump house site works complete.(Carting Upto Sites.) |
| 107 | IPS-II |
| 108 | Supply of Electric driven horizontal Multi stage centrifugal clear water pump capable of delivering 400LPM discharge against a total head of 370m complete with coupling and coupling guards of all accessories. (01 No. running & 1 No. as stand by with 1 No. spare Pump Set)Supply of 52KW TEFC type 4 Pole Electric Motor squirrel cage 2900RPM suitable to operate on 415 +/- 10% Volts, 3 Phase, 50 Hz AC.Supply of MS fabricated heavy duty base plate for mounting above Pump and Motor |
| 109 | Supply of Fully automatic Auto Transformer starter as per Specification and site requirement. |
| 110 | Supply of Control Panel as Per Specification and site requirement. |
| 111 | Supply of Power Wiring material as per Specification and site requirement as below.(i) 35 Sq.mm 1x3Rx3 core cu. cond. Armoured cable- 200Mt.(ii) 95 Sq.mm 3.5core Cu. Cond. Armourd cable-70Mt.(iii) Jointing material such as lugs, tape etc. 2 Sets |
| 112 | Earthing Material as per IE Rules |
| 113 | MAIN PIPING AND VALVES as per Specification and site requirement. |
| 114 | GAUGES as per Specification and site requirement. |
| 115 | Supply of following tools required for maintenance of pumping plants. |
| 116 | Supply of rubber resistance sheet of size 1m x 2m x 0.025m |
| 117 | 150 KVA Servo Voltage Stablizer |
| 118 | Chain Pulley 3 Tonne capacity 4.5 Mtr lift |
| 119 | Solar Power Plant of 7.50 kw for campus to provide lights etc. electrification complete fitting works each stages of pump house with Net metering.for Stage -II |
| 120 | Installation and Commissioning of Pumping Plants with acessories inside the pump house but without civil works such as laying of foundations, cable trenches etc. |
| 121 | Testing of Pumping Plants against guaranteed figures of 'Schedule E' |
| 122 | At Works |
| 123 | At Site |
| 124 | Painting of entire installation with 2 coats of super enamel paint as per direction of Engineer-Incharge of works |
| 125 | Intenal and external electrification of pump house, staff quarters and campus complete fitttings etc |
| 126 | Cartage of Pumping Plants and all acessories from store to site of work including head load charges from road site as required.to pump house site works complete.(Carting Upto Sites.) |
| 127 | IPS-III |
| 128 | Supply of Electric driven horizontal Multi stage centrifugal clear water pump capable of delivering 400LPM discharge against a total head of 400m complete with coupling and coupling guards of all accessories. (01 No. running & 1 No. as stand by with 1 No. spare Pump Set)Supply of 56KW TEFC type 4 Pole Electric Motor squirrel cage 2900RPM suitable to operate on 415 +/- 10% Volts, 3 Phase, 50 Hz AC.Supply of MS fabricated heavy duty base plate for mounting above Pump and Motor |
| 129 | Supply of Fully automatic Auto Transformer starter as per Specification and site requirement. |
| 130 | Supply of Control Panel as Per Specification and site requirement. |
| 131 | Supply of Power Wiring material as per Specification and site requirement as below.(i) 35 Sq.mm 1x3Rx3 core cu. cond. Armoured cable- 200Mt.(ii) 95 Sq.mm 3.5core Cu. Cond. Armourd cable-70Mt.(iii) Jointing material such as lugs, tape etc. 2 Sets |
| 132 | Earthing Material as per IE Rules |
| 133 | MAIN PIPING AND VALVES as per Specification and site requirement. |
| 134 | GAUGES as per Specification and site requirement. |
| 135 | Supply of following tools required for maintenance of pumping plants. |
| 136 | Supply of rubber resistance sheet of size 1m x 2m x 0.025m |
| 137 | 180 KVA Servo Voltage Stablizer |
| 138 | Chain Pulley 3 Tonne capacity 4.5 Mtr lift |
| 139 | Solar Power Plant of 7.50 kw for campus to provide lights etc. electrification complete fitting works each stages of pump house with Net metering.for Stage -III |
| 140 | Installation and Commissioning of Pumping Plants with acessories inside the pump house but without civil works such as laying of foundations, cable trenches etc. |
| 141 | Testing of Pumping Plants against guaranteed figures of 'Schedule E' |
| 142 | At Works |
| 143 | At Site |
| 144 | Painting of entire installation with 2 coats of super enamel paint as per direction of Engineer-Incharge of works |
| 145 | Intenal and external electrification of pump house, staff quarters and campus complete fitttings etc |
| 146 | Cartage of Pumping Plants and all acessories from store to site of work including head load charges from road site as required.to pump house site works complete.(Carting Upto Sites.) |
| 147 | Operation & Maintenance of Scheme Including Repair & Maintenance , Staff and Chemicals for Civil and E&M Works For 1 Year Excluding Electricity Charges. Please Enable Macros to View BoQ information |