| 1 | Clearing light jungle area of all kinds of shrubs, bulb weeds, grass, small plants, branches including cutting all unwanted plants, branches, twigs, wild growth, thorny leaves etc. complete, and disposing the same as place specified by Engineer, transporting at contractors own cost complete all as directed by the Engineer-in-Charge. Note: The unwanted cut bulb weeds, wild grass, unwanted vegetation are to be periodically collected and transported to dumping yard. During execution period any damages shall be rectified to the original at contractor cost. The measurement for payment shall be taken prior to cut the jungle and as directed by the Engineer-in-Charge. The rate shall include the cost of labour, transportation, loading, and unloading at dumpyard or place as directed by Engineer-in-Charge. |
| 2 | Sweeping and Cleaning the concrete surfaces daily around the lab area and pathway area in IGCAR complex including collecting and stacking swept material for disposal upto 4km and as directed by the Engineer-in-Charge. Note: 1. Every time cleaning area shall be measured for payment 2. The contractor shall engage minimum 1 number of workers daily as directed by the Engineer-in-Charge. Failure to deploy the minimum number of labour will attract recovery with the minimum wages for every default of labour as mentioned in specification. 3. The rate should also include sweeping tools etc. 4. The contractor shall supply the necessary PPE to the workers. 5. The rate shall include the cost of hire charges of lorry and labour for transporting of sweeping materials to the dumping yard. |
| 3 | Sweeping and Cleaning the road surfaces including water table, road junction & pavement on both sides of roads from new IGCAR gate to Main Gate complex area or IGCAR area or DAE Installations (as required by Engineer-in-Charge) two times in a Month or when and where ever required including collecting upto 200m and stacking swept material for disposal up to 4km Lead complete all as directed by the Engineer-in-Charge. Note: 1. Every time cleaning area shall be measured for payment. 2. The contractor shall engage minimum 2 numbers of workers daily as directed by the Engineer-in-charge. Failure to deploy the minimum numbers of labour will attract recovery with the minimum wages for every default of labour. 3. The contractor shall supply the necessary PPE to the workers. 4. The rate should also include sweeping tools etc. 5. The rate shall include the cost of hire charges of lorry and labour for transporting of sweeping materials to the dumping yard. |
| 4 | Cleaning the storm water drain when and wherever required including collection of all unwanted leaves, small plants, silt and other unwanted debris etc. upto initial lead 200m and stacking for disposal upto 5km lead at place specified by Engineer, all complete as directed by the Engineer-in-Charge. |
| 5 | Width above 500mm upto 1000mm wide with cover slab |
| 6 | Width above 500mm upto 1000mm wide with out cover slab |
| 7 | Levelling, bull-dozing the heeped / dumped loosened earth / debris etc., by hiring JCB / Bull-dozer etc., including transporting, operating the vehicle, operating the vehicle by engaging driver/operator with valid driving license, diesel charges, insurance and admissible taxes, labour if any required etc. complete all as directed by Engineer-in-Charge. |
| 8 | Conveying the surplus excavated earth & debris, boulders and spoil by mechanical means and depositing at places inside DAE installation identified as Dumping yard as per requirement with a lead specified below including loading, unloading, breaking clods, levelling all complete as per specification and as directed by the Engineer-in-Charge. Note: 1) The rates in respect of this Item are applicable for the NET Quantities arrived at after making deductions for voids @ 20% in respect of soil and @ 50% in respect of Rock from the corresponding Stack / Truck measurements. 2) The earth shall be dumped well inside the Dumping yard and not over approach pathway road. |
| 9 | Lead charges for lead Exceeding 3 kilometre but not exceeding 4 kilometre |
| 10 | Clearing blockage in storm water drain, mouth outlets, road side berm rain water pipes, cutting and removing of fallen trees etc., during the monsoon period, cyclone time and rainy days, and all other essential miscellaneous works etc., complete as directed by the Engineer-in-Charge. Note: Contractor has to engage a minimum of 1 number of male coolies per unit with all PPE like Raincoat, Gumboot, PVC Hand Gloves etc. and during night time with hand torches complete. |
| 11 | Cutting and trimming the branches of the trees of below mentioned girth size of maximum height up to 15.00 metre height from ground level with handling the cut out portion secondary stems, trunk, roots etc., of the Banyan Tree / Rain tree / assorted tree, including required labour, tools , hand saw, arc and disposing using mechanical transport of all the cut branches to dumping yard with in a lead of 5.0km including the lorry/tipper and the labours for loading and unloading the branches of tree, leaves etc., and as directed by the Engineer-in-charge. Note: This item operates only for rooted trees |
| 12 | 200mm to 300mm girth |
| 13 | Above 300mm, upto 600mm girth |
| 14 | Removal and uprooting of tree roots with necessary excavation, cutting the lateral roots, conveying the uprooted tree roots at the places as directed including filling the excavated pits all as per specification - Upto a Girth of 600mm. |
| 15 | Cutting & uprooting the creeper, light jungle bushes etc. coupled with the chain link fencing on the both inside and outside for a height, up to the top of fencing, including carefully removing the vegetation intruded in to the chain link fencing without damaging the chain link and transporting the cut vegetation to a lead of 500m and as directed by Engineer-in-Charge. Overall rebate (Optional) INR Zero Only Please Enable Macros to View BoQ information Government of India Department of Atomic Energy Indira Gandhi Centre for Atomic Research CIVIL ENGINEERING GROUP Name of work : Jungle clearance and Cleaning the road surfaces around RCL complex in IGCAR, Kalpakkam during the year 2026-2027. Tender No. : CEG/IGC/2177/2026 INDEX Section Title Page No. VIII Instructions to contractors 2 Schedule of Quantities 1 - 4 Section VIII I. GENERAL INFORMATION FOR GUIDANCE OF TENDERERS |
| 16 | The schedule of quantities is to be read for the purpose of pricing in conjunction with the special conditions, general rules for the guidance of contractors, conditions of contract, specifications, drawings, schedule of supply of materials and the appendices. |
| 17 | The prices inserted in the schedule of quantities shall be inclusive of value of the work described including all cost and expenses, which may be required in and for the construction of the work described together with the general risks, liabilities and obligations not forth or implied in the documents on which the tender is to be based. |
| 18 | The quantities stated are to be considered approximate only and the unit prices entered in the schedule of quantities and prices shall apply only to the actual quantities measured in the completed work in accordance with the specifications. |
| 19 | All the materials other than those shown in schedule of supply of materials in section VII are to be arranged by the contractor and his rates should account for the same. |
| 20 | Rates quoted for all items in this tender shall include cost of all materials including cement and steel. Department will not supply any materials other than materials stipulated in Section VII of the tender and as such the rates quoted must be all inclusive. |
| 21 | If contractors need any clarification they are required to contact the Chief Engineer, Civil Engineering Group, Indira Gandhi Centre for Atomic Research, Central Design Office, Kalpakkam 603 102, Kancheepuram District, Tamilnadu. (Telephone STD Code: 044 – 27480306) ----- Government of IndiaDepartment of Atomic EnergyIndira Gandhi Centre for Atomic ResearchCivil Engineering Group TENDER DOCUMENT FOR Cleaning of Storm water drains and roads in Southern side of IGCAR Premises during the year 2024-2025 at Kalpakkam. Tender No. CEG/IGC/1937/2023 Part – II : Financial Bid (Section - VIII) INDEX Sl. No. Title Page No. |
| 22 | Schedule of Quantities 1 - 2 |