| 1 | Cost of other materials for line and sub station Cost of 11KV Line with 55 mm2 AAAC including 1% LC, T&P @ 2%, Transportation @ 7.5%, Erection Charge @ 10% |
| 2 | Construction of Plinth Mounted, 11/0.4 KV S/S using 9 mtrX 300kg Long PSC Pole with double disc arrangement for 63 KVA Transformer (Excluding Pole & Transformer) including 1% LC, T&P @ 2%, Transportation @ 7.5%, Erection Charge @ 10% |
| 3 | Cost of common material for 11KV Line pin point with 9mtr long PSC Pole (Excluding pole & Civil work cost) including 1% LC, T&P @ 2%, Transportation @ 7.5%, Erection Charge @ 10% |
| 4 | Construction of 3-Ph 95mm2 (5 Wire) AB Cable on 8 mtr X 200Kg PSC Pole for LT Line (30 mtr span) (Excluding pole) including 1% LC, T&P @ 2%, Transportation @ 7.5%, Erection Charge @ 10% |
| 5 | Construction of 3-Ph 50mm2 (4 Wire) AB Cable on 9 mtr X 300Kg PSC Pole for LT Line (30 mtr span) (Excluding pole) including 1% LC, T&P @ 2%, Transportation @ 7.5%, Erection Charge @ 10% |
| 6 | Cost of PSC PoleCost of 9 mtr. Long 300 Kg. PSC Pole for HT line + S/S+ others including 1% LC, T&P @ 2%, Transportation, @ 7.5%, Erection Charge @ 20% |
| 7 | Concreting ratio 1:1, 5:3 (M-20 Grade) (500mm x 500mm x 1800mm) = 0.45 Cum (Per Pole) including 1% LC |
| 8 | Couping Ratio 1:1, 5:3 (M-20 Grade) With dimension (500mm x 500mm x 450mm) = 0.1125 Cum (Per Pole) including 1% LC |
| 9 | PCC Ratio 1:3:6 (M-10 Grade) For DSS Area (3.5 x 2.5 x 0.1) = 0.875 Cum including 1% LC |
| 10 | Stay Concreting Ratio 1:1, 5:3 (M-20 Grade) With dimension (500mm x 500mm x 800mm) = 0.2Cum (Per Stay) including 1% LC |
| 11 | Construction of Earthing Chamber including Installation of earthing pipe, Making Earthing Chamber including excavation, soil Treatment with bentonite powder, calculation of earth resistance, including installation of 3 Mtr GI Pipe 40mm/50mm including welding of Flat(GI) around pipe including 1% LC |
| 12 | ACB/ LTDB Plinth including 1% LC |
| 13 | Boundary wall Fencing with MS gate & Plinth for 63KVA S/S including 1% LC |
| 14 | Dismantal cost of S/S including 1% LC |
| 15 | Dismantal cost of LT Line including 1% LC |
| 16 | Dismantal cost of 11 KV Line including 1% LC |
| 17 | Inspection fee for LT line |
| 18 | Inspection fee for 11KV line |
| 19 | Inspection fee for S/S including |
| 20 | Drawing Approval including Please Enable Macros to View BoQ information |