| 1 | सी0सी0रोड व कवर्ड नाली |
| 2 | Clearing grass and removal of the rubbish up to a distance of 50 m outside the periphery of the area cleared (DSR sl. no. 2.32 @Rs 8.95/sqm) |
| 3 | Construction of embankment with approval material obtained from borrow pits with a lift upto 1.50 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300.1 and 300.2 as per as per techincal specifications clauses 301.5(as per analysis of rates) |
| 4 | Providing and laying cement concrete 1: 6 :12 (1 cement: 6 C.sand: 8 graded brick aggregate 40mm nominal size.) including supply of all materials, labour and T&P etc required for proper completion of the work as per (UPPWD SOR sl no. 273) |
| 5 | Brick masonary work in 1:3 cement mortar in foundation complete exclusing pointing and plastering as per drawing and technical specifications cluases 600, 1202 & 1203.(as per analysis of rates) |
| 6 | Plaster with cement mortar (1:4) 15 mm thick on brick work of substructure/superstructure as per technical specification clauses 613.4 & 1204.(as per analysis of rates) |
| 7 | Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density complete as per Technical Specification Clause 401. |
| 8 | Cement concrete pavement Construction of un-reinforced plain cement concrete pavement Grade M-30, over a prepared sub base, with PPC cement , coarse and fine aggregates conforming to IS: 383, mixed in a concrete mixer and appropriate weigh batcher using approved mix design,laid in approved fixed side formwork and fixing of 125 micron thick polythene film including levelling the formwork as per drawing. spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of ontraction and expansion, construction joints, curing of concrete slabs for 14-days and water finishing to lines and grade as per drawing and Technical Specification Clause 1501.(as per analysis of rates) |
| 9 | Providing and laying cement concrete 1: 2 :4 (1 cement: 2 C.sand: 20 graded stone aggregate 20mm nominal size.) including supply of all materials, labour and T&P etc required for proper completion of the work (UPPWD SOR sl. no. 4.1.3) |
| 10 | Providing and laying reinforcement cement concrete M20 grade in superstructure as per drawing and techincal specifications cluases 800, 1205.4 and 1205.5 (as per analysis of rates) |
| 11 | Supplying, fitting and placing HYSD bar reinforcement in super structure complete as per drawing and technical specification cluases 1002, 1010 and 1202(as per analysis of rates) |
| 12 | P/F of display/ inauguration black granite board including letter writing etc. All cost complete Please Enable Macros to View BoQ information |