| 1 | [10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate] |
| 2 | [11.25.1]Pointing on brick work or brick flooring with cement mortar 1:3 (1 cement : 3 fine sand): 1. Flush / Ruled/ Struck or weathered pointing [Through Rate] |
| 3 | [11.6.2]15 mm cement plaster on the rough side of single or half brick wall of mix : 2. 1:6 (1 cement: 6 fine sand) [Through Rate] |
| 4 | [11.78]Painting two coats excluding priming coat with synthetic enamel paint in all shades on new wood work or metallic or plastered or concrete surfaces to give an even shade. [Through Rate] |
| 5 | [11.93.1]Finishing walls with water proofing cement paint of required shade : 1. New work (Two or more coats applied @ 3.84 kg/10 sqm) [Through Rate] |
| 6 | [13.29.2]Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required. 2. In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works [Through Rate] |
| 7 | [17.8.1]Compaction 1. Extra for laying earth/fly ash as per specifications in 20 cm layers and dressing but excluding the cost of rolling [Through Rate] |
| 8 | [2.B0045] B0045. Welding by electric plant [Rate] |
| 9 | [2.RM079] RM079. Earth Cost or compensation for earth taken from private land [Rate] |
| 10 | [26.1]Supplying and stacking at site of work well-decayed farm-yard manure from any available source, approved by the Engineer-in-charge including screening through sieve of I.S.designation 16 mm with 5 km lead. [Through Rate] |
| 11 | [26.13.3]Digging holes in all kinds of soil, and refilling the same, with the excavated earth, mixed with well decayed farmyard manure (cost of well decayed farm yard manure to be paid separately) 3. Hole 0.75 metre dia and 0.75 metre deep [Through Rate] |
| 12 | [26.13.4]Digging holes in all kinds of soil, and refilling the same, with the excavated earth, mixed with well decayed farmyard manure (cost of well decayed farm yard manure to be paid separately) 4. Hole 0.60 metre dia and 0.60 metre deep [Through Rate] |
| 13 | [26.5]Making lawns with rough grassing including uprooting rank vegetation and weeds by digging area to a depth of 30 cm , removing all weeds and other growth with roots by forking repeatedly, ploughing and dragging with ‘swagha’ breaking of clods, removal of rubbish, dressing and supplying doob grass roots, and planting at 15 cm apart, including supplying and spreading of farm-yard manure at the rate of 0.18 cum per 100 sqm fertilizers etc [Through Rate] |
| 14 | [26.58.1]Supply and installation of garden bench 1. Chair type garden bench with L-shaped sides made of reinforced concrete (M30), thickness 100 mm, overall height 1000 mm, base width 620 mm. Back and seat shall consist of 5 Nos. reinforced concrete planks 1500 mm x 100 mm x 50 mm one plank 1500 mm x 200 mm x 50 mm. Seating height of the bench shall be 450 mm. The bench shall be fixed with nuts on concrete mount, all holes sealed after assembly and installation. All materials required to be as per BIS specifications. [Through Rate] |
| 15 | [26.6]Maintenance of rough grassing, including 50 gm DAP and 50 gm Urea fertilizer application , watering and mowing etc for a period of one year. [Through Rate] |
| 16 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km] |
| 17 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [Beyond 10km up to 20km per KM] |
| 18 | [3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [Beyond 5km up to 10km per KM] |
| 19 | [4.12.1]Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead up to 50 m and lift up to 1.5 m, as directed by Engineer-in-charge. 1. All kinds of soil [Through Rate] |
| 20 | [6.14.2]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] |
| 21 | [6.29.3]Centering and shuttering including strutting, propping etc. and removal of form work for : 3. Columns, piers, abutments, pillars, posts and struts [Through Rate] |
| 22 | [6.8.2]Providing and laying damp-proof course with cement concrete 1:2:4 (1 cement : 2 coarse sand (zone-III): 4 graded stone aggregate 12.5mm nominal size) 2. 40mm thick [Through Rate] |
| 23 | [7.20.2]Brick work with common burnt clay modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement Mortar 1:6 (1 cement : 6 coarse sand) [Through Rate] |
| 24 | providing and fixing of wicket gates with brick and RCC pillars having minimum weight of gate 65 kg including painting two coats, distempering of pillars complete in all respect and to the entire satisfaction of Engineer in Charge as per design and drawing |
| 25 | Providing and fixing of main gate with Brick and RCC piller |
| 26 | Provision of purchase of rubber House Pipe 1` dia ISI marked complete in all respect to the entire satisfaction of EIC Please Enable Macros to View BoQ information |