| 1 | Recovery- Credit of Steel reinforcementfor R.C.C. work recovered from exsiting drain available at site, where not included in the complete rate of RCC dismantle, Complete as per Engineer in charge. The Quantites of the above material have been worked out on the basis of theoretical quantities laid on this road.However agency may visit before quoting rates and asses the extent of retrieved material. There shall be no measurement after actual scarifying / dismantling and if material after dismantling is found on lesser side, no claim of agency on this score will be entertained and full recovery on the basis of qouted rate and quantity exhibited in the BOQ shall be made. The reverse rates are minimum rates to be used as base for quoting purchase rate by the agency. No rates below reserve price will be considered for all purpose in case the agency qoutes lesser than reserve price. |
| 2 | [21.28]Providing and fixing steel bar embedded plastic steps of size 263mm x 165mm of orange colour, confirming to specification in pump chambers, manholes etc., having minimum 3mm thick polypropylene polymer confirming to is:10910 encapsulated on 12mm dia ribbed steel bars per IS :1786. The rate include cost of setting the same to correct lines and levels duly embedded in 1:2:4 cement concrete including carriage, loading, uploading, stacking, handling, re-handling etc., complete in all respect to the satisfaction of Engineer-in-charge [Through Rate] |
| 3 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate] |
| 4 | [34.40]Portable Barricade in Construction Zone Installation of a steel portable barricade with horizontal rail 300 mm wide, 2.5 m in length fitted on a A frame made with 45 x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats) with yellow and white stripes, 150 mm in width at an angle of 450, A frame painted with 2 coats of yellow paint, complete as per IRC:SP:55-2001 [Through Rate] |
| 5 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] |
| 6 | [4.32]Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift up to 1.5 m. [Through Rate] |
| 7 | [5.26]Demolishing R.C.C. work by mechanical means and stockpiling at designated locations and disposal of dismantled materials up to a lead of 1 kilometre, stacking serviceable and unserviceable material separately including cutting reinforcement bars. [Through Rate] |
| 8 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate] |
| 9 | [6.26.2]Extra for providing richer mixes up to plinth and at all floor levels. 2. Providing M-35 grade concrete instead of M-25 grade BMC/ RMC. (Note : Cement content considered in M-35 is @ 350 kg/ cum) [Through Rate] |
| 10 | [6.28.1]Providing and laying in position ready mixed M-25 grade concrete for reinforced cement concrete work, using fly ash and cement content as per approved design mix, and manufactured in fully automatic batching plant and transported to site of work in transit mixer for all leads, having continuous agitated mixer, manufactured as per mix design of specified grade for reinforced cement concrete work, including pumping of R.M.C. from transit mixer to site of laying, excluding the cost of centering, shuttering, finishing and reinforcement, including cost of admixtures in recommended proportions as per IS : 9103 to accelerate / retard setting of concrete, improve workability without impairing strength and durability as per direction of the Engineer - in - charge. 1. All works up to Plinth level. [Through Rate] |
| 11 | [6.30.2]Centering and shuttering including strutting, propping etc. and removal of form for 2. Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. [Through Rate] |
| 12 | [6.30.3]Centering and shuttering including strutting, propping etc. and removal of form for 3. Suspended floors, roofs, landings, balconies and access platform [Through Rate] |
| 13 | [6.33.6]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect below plinth level Note: Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 6. Thermo-Mechanically Treated bars of grade Fe-500D or more [Through Rate] Please Enable Macros to View BoQ information |