| 1 | SUB ESTIMATE NO 1- Well Deepning |
| 2 | Item No.1-Excavation in general in soft material comprising of soft soil, soft murum,sand,hard murum with boulders in wet or dry condition for Head Works i.e.Intake Well, Jack Well, Pump House, Supply Well, etc.for lift 0 to 1.5 M and lead of 150M including baricatomg, gurad ing, disposing off surplus excavat ed stuff within a radius of 0.5 km. as direct ed by Engineer in charge etc. complete. excluding refilling. |
| 3 | Lift 6.00 to 7.50 m |
| 4 | Lift 7.50 to 9.00 m |
| 5 | Item No.2-Excavation in general in hard material comprising of soft rock, hard rock, Manjara rock, etc by blasting/ controlled blasting/chiselling as required in wet or dry condition for Head Works i.e.Intake Well, Jack Well, Pump House, Supply Well, etc.for lift 0 to 1.5 M and lead of 150M including baricatomg, gurading, disposing off surplus excavat ed stuff within a radius of 0.5 km. as directed by Engineer in charge etc.comp lete. excluding refilling. |
| 6 | Lift 6.00 to 7.50 m |
| 7 | Lift 7.50 to 9.00 m |
| 8 | Item No.3-Dewatering the excavated trenches and pools of water in the building trnches/pipeline trenches, well works by using pumps and other devices including disposing off water to safe distance as directed by Engineer in charge (including cost of machinery, labour, fuel)etc.complete.MJP DSR 23-24 P/I-40/14+10%HA |
| 9 | Item No.4-Providing and laying in situ cement concrete mortar 1:2:4 of trap metal for foundation and bedding including bailing out water manually formwork compacting & curing etc. complete. |
| 10 | Item No.5-Providing and fixing in position steel bar reinforcement of various diameters for RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircases, newels, chajjas,lintels, pardies, copings, fins, arches,etc.as per detailed designs, drawings and schedules, including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required, etc,complete. (including cost of binding wire). |
| 11 | Item No.6-Providing and casting in situ cement concrete of trap/granite/ quartzite /gneiss metal of approved quality for RCC work as per detailed drawings and designs or as directed by Engineer in charge including normal dewatering, centering,formwork, compaction, finishing the formed surfaces with CM 1:3 of sufficient minimum thickness to give a smooth and even surface wherever necessary or roughening if special finish is to be provided and curing, etc.complete. |
| 12 | Verticle wall |
| 13 | Item No.7:- Providing & fixing in well staining 80 mm dia. A.C. pipes or 90 mm PVC Pipe as a weep holes 1.5 m c/c. staggered pipe sloping outside the well staining so as to prevent sand in coming along with water current with all lead and lifts as directed.Weep Holes (MJP DSR 23-24 P/No.291 I/No. 5) |
| 14 | Item No.8 -Providing laterite stone masonry in cement mortar 1:6 in foundation and plinth including striking joints on the unexposed faces and watering and watering complete. As per RA no.4 |
| 15 | SUB ESTIMATE NO 2- PUMPING MACHINRY |
| 16 | Item No. 1-Providing installing, commissioning and testing of submerssible pump set 140LPM discharging water against a total head of 104 m from all causes when running at 2900 RPM (Approx) directly coupled to submotor squrrel gage induction type of adquate capacity as per detail specifications. |
| 17 | 3 H.P 8 Stages |
| 18 | Item No. 2-Providing, erecting , commissioning & testing of floor mounting type L.T. pannel board (skeletion type) as per detail specifications. |
| 19 | Item No. 3-Providing at site and jointing and testing at site of work double flanged type valve as per detail specifications |
| 20 | Non return valve (50 mm dia) |
| 21 | Sluice Valve (50 mm dia) |
| 22 | Item No.4-Providing erecting jointing & testing of vertical drop pipe 65 mm dia G.I. medium duty in 1.5m/1.00m or in length as per site condition with heavy duty flanges etc.complete. as per detail specifications.(R.A No.4) 50 mm dia G.I |
| 23 | 50 mm G.I drop pipe (M-class) |
| 24 | Item No.5 -Providing erecting, jointing & testing of required size M.S.D/F specials & pipe & flanges tubes etc.complete as per detail specifications. |
| 25 | Item No.6-Providing laying, jointing and testing of PVC water proof sub cable proper conductor of type ( 1x3x2.5) sqm size as per detail specifications. |
| 26 | Item No.7-Providing laying & testing of PVC allu. conductor armoured cable (1x3x 4 ) core size & as per details specifications. |
| 27 | Item No.8-Providing G.I. sheet 1.25 mm (18 gauge) to be used for fabrication of boxes panel boards etc. including cutting, bending, drilling, welding, revetting etc. and painting with one coat of red lead oxide & two coates of enamel paint.PWD ele DSR 2022-23 P/I 114/6 -1-5 |
| 28 | Item No.9-Providing and testing varnished plank 20 mm thick fixed towall cr on provided pannel board for fitting MSEB connection with necessary materials supports etc. complete. |
| 29 | Item No.10-Providing, installing, testing, earthing arrangement to installation of motor, L.T. pannel board starter etc. complete as per details specifications. |
| 30 | Sub Estimate No.3 :- Rising Main |
| 31 | MATERIAL SECTION |
| 32 | Item No. 1: Providing and supplying in standard lengths Polyethelene Pipes, confirming to IS 4984/ 14151/ 12786/ 13488 with nesessary jointing material like mechanical connector i.e. thread/ insert joint or flanged joint, including all local & central taxes, transportation and fright charges inspection charges, loading/ unloading charges, conveyance to the departmental store / site & stacking the same in closed shade duely protecting from sunrays & rains, etc complete. |
| 33 | 63 mm dia HDPE 8 kg/cm2 P.E. 100 |
| 34 | Item No.2- Providing ISI mark G.I. pipes of following class and diameters including all statutory duties and taxes such as GST levied by GOI and GOM in all respect inspection charges, transporta- tion to stores, etc.complete. |
| 35 | 80 mm dia G.I medium class |
| 36 | Item No.3:-Providing & supplying air valve as per IS 14845/2000 &MJP's standard specification of approved make & quality of following diametres including all taxes (central & local) ,Railway freight , inspection charges ,unloading from railway wagons, loading into truck,transportation upto departmental stores/ site unloading & staking etc complete. |
| 37 | 15 mm dia S/A Air Valve |
| 38 | LABOUR SECTION |
| 39 | Item No 1-Excavation for foundation/ pipe trenches in hard murum and , including removing the excavated material upto a distance of 50 mtrs. and lifts as below, stacking and spreading as directed, normal dewatering,preparing the bed for foundation and excluding backfilling etc.complete. |
| 40 | Item No.2 -Excavation for foundation/ pipe trenches in hard rock by controlled blasting,including trimmimng and levelling the bed by chiselling where necessary and removing the excavated material and stacking it in measurable heaps within a distance of 50 metres from the area and lifts as below, normal dewatering, excluding backfilling, etc. complete. |
| 41 | Item No-3:-Filling in plinth and floors/trenches with approved murum from excavated materials from foundation 15cm to 20cm layers including watering and compaction |
| 42 | Item No.4: Lowering ,laying and jointing with H.D.P.E pipes by heating to the ends of pipes with the help of Teflon coated electric mirror /heater to the required temperature and then pressing the ends together against each other, to form a monolithic & leak proof joint by thermosetting process. The pressing may be required to be done with Jacks /Hydraulic Jacks /Butt fusion machine etc complete. with all materials labours as directed by Engineer in charge |
| 43 | 63 mm dia HDPE 8kg/cm2 P.E. 100 |
| 44 | Item No 5:- Hydraulic testing of HDPE/MDPE pipe line to specified pressure including cost of all materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. The rate under this item shall also include cost of retesting, if necessary and reinstating to original position. |
| 45 | 63 mm dia HDPE 8 kg/cm2 P.E. 100 |
| 46 | Item No 6-Lowering,laying and jointing G.I.pipes and specials of following class and diameter including conveyance from stores to site of works, all labour, etc.complete.either underground or in vertical position, as directed by Engineer in charge. |
| 47 | 80 mm dia G.I. mediun class pipe |
| 48 | Item No.7:-Lowering laying & fixing in proper alignment and position all type of C.I. air valves as directed by Engineer in charge cost of all material and giving stastifactory hydrolic testing etc complete. |
| 49 | 15 mm dia S/A Air Valve |
| 50 | Item No. 8-Providing and laying in situ cement concrete mortar 1:2:4 of trap metal for foundation and bedding including bailing out water manually formwork compacting & curing etc. complete. |
| 51 | Item No.9: Refilling the trenches with available excavated stuff with soft material first over the pipeline and then hard material in 15 layers with all lead and lifts including consolidation,surcharging etc complete. |
| 52 | Sub Estimate No.4 : Syntex tank Over RCC Platform & pipeline |
| 53 | Item No. 1:- Providing and fixing H.D.P container Syntex or alike one piece moulded water tank made out of low density polythyler and built corrugation including of delivery upto destination hoisting and fixing of accessories such as inlet,outlet overflow of all tanks capacity above1000 to 20,000 litres |
| 54 | Item No.2-Providing & fixing in position UPVC plumbing pipes of specified outer diameter of required standard thikness confirming to IS 4985including necessary fittings confirming to IS 7834 such as PVC bends,vees,reducers, clamps, plugs etc necessary excavation trench,refilling necessary drilling holes in walls/slab and making the good the surface complete.(For 10.00 kg/sq.m) |
| 55 | 75 mm dia UPVC pipe - 10 kg/cm2 |
| 56 | 50 mm dia UPVC Pipe- 10 kg/cm2 |
| 57 | Item No 3-Excavation for foundation/ pipe trenches in hard murum and , including removing the excavated material upto a distance of 50 mtrs. and lifts as below, stacking and spreading as directed, normal dewatering,preparing the bed for foundation and excluding backfilling etc.complete. |
| 58 | Item No.4 -Excavation for foundation/ pipe trenches in hard rock by controlled blasting,including trimmimng and levelling the bed by chiselling where necessary and removing the excavated material and stacking it in measurable heaps within a distance of 50 metres from the area and lifts as below, normal dewatering, excluding backfilling, etc. complete. |
| 59 | Item No.5-Providing and laying in situ cement concrete mortar 1:2:4 of trap metal for foundation and bedding including bailing out water manually formwork compacting & curing etc. complete. (As per R.A no.1) |
| 60 | Item No.6-Providing and casting in situ cement concrete of trap/granite/ quartzite /gneiss metal of approved quality for RCC work as per detailed drawings and designs or as directed by Engineer in charge including normal dewatering, centering,formwork, compaction, finishing the formed surfaces with CM 1:3 of sufficient minimum thickness to give a smooth and even surface wherever necessary or roughening if special finish is to be provided and curing, etc.complete. (excluding M.S.or Tor reinforcement.) EnE DSR 44/ 4 R.A.No.6slab/landings/ vertical walls/waist slabs/ steps for staircases |
| 61 | R.C.C. (M-200) Grade |
| 62 | RCC Slab & Landing |
| 63 | RCC Column |
| 64 | RCC Beam |
| 65 | RCC Footing |
| 66 | Item No.7-Providing and fixing in position steel bar reinforcement of various diameters for RCC piles, caps, footings, foundations, slabs, beams, columns, canopies, staircases, newels, chajjas, lintels, pardies, copings, fins, arches, etc.as per detailed designs, drawings and schedules, including cutting, bending, hooking the bars, binding with wires or tack welding and supporting as required, etc,complete. (including cost of binding wire).MJP DSR 2023-24 P/I 50/8 |
| 67 | Item No.8: Providing & fixing M.S. Ladder 0.50 m. wide consisting of 75 mm x 10 mm M.S. flats stringers and steps of 16 mm dia bars in double rows about 25 mm cm. C/C including 3 coats of anticorrosive paint etc. complete. |
| 68 | Item No.9-Providing & fixing structural steel work in rolled section like joints, channels, angles tees etc. as per detailed drawing & design and drawings including fixing in position without connecting plates,braces,etc. and one coat of aticorrosive paint and over it two coats of oil painting, of approved quality and shade etc. complete. |
| 69 | Item No.10- Providing and applying two coats of water proof cement paint of approved manufacturer and approved colour to the plastered surfaces including scaffolding and necessary ,cleaning and and preparing the surface watering for two days etc. complete.(In Two coats)Water Proof Cement Painting(PWS DSR 22-23 P/No. 376 I/No.35.13 ) |
| 70 | Sub Estimate No.5- DISTRIBUTION SYSTEM |
| 71 | MATERIAL SECTION |
| 72 | Item No.1 -Providing & supplying in standard lengths polyethelene Pipes, conforming to IS 4984/14151/12786/ 13488 with necessary jointing material like mechanical connector i.e.thread/ insert joint/ quick release coupler joint, compreession fitting joint or flanged joint including all statutory duties and taxes such as GST levied by GI & GOM in all respect ,transportation and freight charges inspection charges, loading/unloading charges, conveyance to the departmental stores/ site & stacking the same in closed shade duely protecting from sunrays & rains, etc. |
| 73 | 90 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 74 | 75 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 75 | 63 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 76 | Item No.2- Providing ISI mark G.I. pipes of following class and diameters including all statutory duties and taxes such as GST levied by GOI and GOM in all respect inspection charges, transporta- tion to stores, etc.complete. |
| 77 | 100mm dia G.I medium class |
| 78 | Item No.3-Providng and supplying Idouble flange Sluice valves confirming for IS 2906/14846 including worn gear arrangement as per test pressure stainless steel spindle, caps including all statutory duties and taxes such as GST levied by GI & GOM inspection charges in all respect transportation up to departmental store.site unloading, staking etc Transportation etc complete. |
| 79 | 80 mm dia C.I.D./F. SL Valve |
| 80 | 65mm dia C.I.D./F. SL Valve |
| 81 | 50mm dia C.I.D./F. SL Valve |
| 82 | Item No.4:-Providing & supplying air valve as per IS 14845/2000 &MJP's standard specification of approved make & quality of following diametres excluding all taxes (central & local) ,Railway freight , inspection charges ,unloading from railway wagons, loading into truck,transportation upto departmental stores/ site unloading & staking etc complete. |
| 83 | 20 mm dia S/A Air Valve |
| 84 | LABOUR SECTION |
| 85 | Item No.1-Excavation for foundation/ pipe trenches in hard murum including removing the excavated material upto a distance of 50 mtrs. and lifts as below, stacking and spreading as directed, normal dewatering,preparing the bed for foundation and excluding backfilling etc.complete. |
| 86 | Item No. 2: Excavation for foundation/ pipe trenches in hard rock and concrete road by chiseling, wedging, line drilling by mechanical means other than blasting including trimming and levelling the bed removing the excavated material upto a distance of 50 meters beyond the area and lifts as below stacking as directed by Engineer in charge normal dewatering excluding back filling etc. complete. |
| 87 | Item No.3- Filling in plinth and floors murum bedding in trench with approved murum from excavated materials from foundation 15cm to 20cm layers including watering and compaction etc. complete |
| 88 | Item No.4: Lowering ,laying and jointing with H.D.P.E pipes by heating to the ends of pipes with the help of Teflon coated electric mirror /heater to the required temperature and then pressing the ends together against each other, to form a monolithic & leak proof joint by thermosetting process. The pressing may be required to be done with Jacks /Hydraulic Jacks /Butt fusion machine etc complete. with all materials labours as directed by Engineer in charge, |
| 89 | 90 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 90 | 75 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 91 | 63 mm dia HDPE pipe PE - 100 - 6 kg/cm2 |
| 92 | Item No 5:- Hydraulic testing of HDPE/MDPE pipe line to specified pressure including cost of all materials and labour and water for testing for specified length including cutting, placing end cap making arrangement for filling safe water using reciprocating type pumps which should be able to provide specified test pressure gauges and other necessary equipments, labour, operation charges, etc. required for testing. The rate under this item shall also include cost of retesting, if necessary and reinstating to original position. |
| 93 | 90 mm dia HDPE 6 kg/cm2 P.E. 100 |
| 94 | 75 mm dia HDPE 6 kg/cm2 P.E. 100 |
| 95 | 63mm dia HDPE 6 kg/cm2 P.E. 100 |
| 96 | Item No 6-Lowering,laying and jointing G.I.pipes and specials of following class and diameter including conveyance from stores to site of works, all labour, etc.complete.either underground or in vertical position, as directed by Engineer in charge. |
| 97 | 100 mm dia G..I. mediun class pipe |
| 98 | Item No. 7 - Lowering, laying and jointing in position following C.I.D./F. sluice valve including cost of all labour jointing material, including nut bolts etc. complete. |
| 99 | 80 mm dia C.I.D./F. SL Valve |
| 100 | 65 mm dia C.I.D./F. SL Valve |
| 101 | 50 mm dia C.I.D./F. SL Valve |
| 102 | Item No. 8 - Giving satisfactory hydraulic testing of following C.I. D / F Reflex valves, Butterfly valves and Sluice valves. |
| 103 | 80 mm dia C.I.D./F. SL Valve |
| 104 | 65 mm dia C.I.D./F. SL Valve |
| 105 | 50 mm dia C.I.D./F. SL Valve |
| 106 | Item No.9:-Lowering laying & fixing in proper alignment and position all type of C.I. air valves as directed by Engineer in charge cost of all material and giving stastifactory hydrolic testing etc complete. |
| 107 | 20 mm dia S/A Air Valve |
| 108 | Item No.10-Providing and laying in situ, M-150 grades of C.C.1:2:4 of trap metal for foundation and bedding including dewatering, formwork, compacting and curing,finishing etc.complete. |
| 109 | Item No. 11: Refilling in plinth & floors/ trenches with approved excavated materials from foundation in 15 cm to 20 cm. layers including watering and compaction etc. complete.Refilling |
| 110 | Item No.12-Making provision for name plate of scheme including providing fixing painting as directed including all labour material transport etc complete. |
| 111 | SUB ESTIMATE NO 6 -Electrification Arrangement |
| 112 | Item No. 1: - Making provision for electrification charges for M.S.E.B. work such as providing errecting poles, streching wire, including all labour, transportation & realeasing connection charges for scheme. |
| 113 | GST Please Enable Macros to View BoQ information |