| 1 | Design, Engineering, Procurement and Construction (EPC) basis with required services and utilities including handing over complete as per scope of work mentioned in Tender Documents (Volume 1 to Volume VI) and directions of Engineer In charge: |
| 2 | BSL-3 Laboratory Building with BSL-3 , BSL-2 and other labs |
| 3 | Design, Engineering, Procurement and Construction (EPC) basis with support services & allied facilities by incorporating stipulated specifications, all services including handing over complete as per scope of work mentioned in tender documents and directions of Engineer In charge: Infrastructure and External Development works for BSL-3 Laboratory Buidling - Civil & Services Works such as Levelling, Internal Roads and Pathways, Storm drains, Foot Path, Trenches for services , Rain Water Harvesting, External Water Supply Network (Filtered and Unfiltered), External Sewer System , Landscaping, Horticulture Operations etc. as per scope of work, Tender Drawings and direction of Engineer- In-Charge. |
| 4 | Bituminous Concrete road, Footpath, Open Path ways/Ramps / Building approach /drop off (including sub base, kerb stones, joints etc.) complete as per scope of works and directions of Engineer In charge. |
| 5 | Landscaping, Horticulture, Irrigation System as per scope of works and directions of Engineer In charge. |
| 6 | External Water-Supply System (Filtered and Un-filtered) complete as per scope of works and directions of Engineer In charge. |
| 7 | Sewerage System complete as per scope of works and directions of Engineer In charge. |
| 8 | Storm Water Drainage System (including Rain Water Harvesting) including trenches for services complete as per scope of works and directions of Engineer In charge. |
| 9 | External Street Lighting System / High Mast Lighting / Solar & Conventional street lighting including Cables, Panel etc. with External Signage’s complete as per scope of works and directions of Engineer In charge. |
| 10 | STP/ETP plant complete as per scope of works and directions of Engineer In charge. |
| 11 | BSL-3, BSL-2 and Other Lab Specialized Works |
| 12 | BSL-3 Laboratory Buidling with BSL-3 , BSL-2 and other lab works Specialized equipments, systems and works for BSL-2, BSL-3 and other Lab Specialized Works High Containment laboratory work in NCDC BSL-3 Building shall include specialized internal walls, ceiling and finishing works i/c aluminium coving, door, floor coving, self levelling epoxy flooring, HVAC works including HEPA filters works BIBO/containment housing, Electrical Works, Containment barrier double door autoclave with bio-seal, Effluent decontamination system, Building and Lab management system, CCTV system, Access Control system, Walk-thru-shower system + BLED room, Laboratory work stations, modular laboratory work stations, Double door class 100 dynamic pass box, biosafety door for transfer/decon air-lock and showers, Double door autoclave, compressors, dunk tank, Ventilated type garment storage cabinet, garment storage lockers, Effluent decontamination system for BSl-3 lab 2 nos 750 litre each (1W+1S) with steam boiler and accessories, Water treatment/softening plant, VHP pass Box, Eye-wash stations, Lockers, Biosafety Cabinet Class II Type A2, 6 Feet, HEPA H14 Filter, 415V AC etc and associated works including handing over, validation and certification from Department of Bio-Technology (DBT)// Department of Health Research (DHR) complete as per scope of work and directions of Engineer In charge. |
| 13 | Admin Furniture and Scientific Equipment for BSL-3 Laboratory |
| 14 | Supply, Intallation, Testing and Commissioning of Admin Furniture complete as per scope of work and directions of Engineer In charge. |
| 15 | Supply, Intallation, Testing and Commissioning of Scientific Equipment for BSL-3 Laboratory complete as per scope of work and directions of Engineer In charge. |
| 16 | Providing Operation & Maintenance and Comprehensive Maintenance (CMC) and Annual Maintenance of as per scope of Work and directions of Engineer In charge: |
| 17 | Operation & Maintenance , CMC & AMC during DLP for 1st year |
| 18 | Operation & Maintenance , CMC & AMC for 2nd year |
| 19 | Operation & Maintenance , CMC & AMC for 3rd year |
| 20 | Operation & Maintenance , CMC & AMC for 4th year |
| 21 | Operation & Maintenance , CMC & AMC for 5th year Please Enable Macros to View BoQ information |