| 1 | Scarifying or picking gravelled, macadam or bituminous macadam surfaces in area exceeding 400 Sqm and depth exceeding 50 mm but not exceeding 100 mm deep including removing stacking and deposing off, complete all as specified and directed. |
| 2 | M&L for 7.5cm thick (compacted thickness) WBM, with coarse aggregate of granite, trap or Basalt of grading 2 (63 to 40mm size), spread, rolled and consolidated to gradient and camber with 8 to 12 tone power roller, complete all as specified and directed by Engineer-in-charge. |
| 3 | M&L for preparing un-surfaced water bound macadam by brushing with wire brushes for removing caked etc sweeping with brooms and finally fanning the cleaned surface with gunny bags to remove all loose dirt etc, applying evenly a prime coat of cationic bitumen emulsion (SS-1) conforming to IS : 8887 at a rate of application of 0.70 - 1 kg/sqm on surface of WMM/WBM as specified in table 500-3 of Morth specification for road and bridge work 2013 using mechanical sprayer, complete all as specified and directed by Engineer-in-charge. |
| 4 | M&L for premix bituminous, macadam laid/rolled and compacted to required gradient and camber (consolidated thickness 75mm or less) using paving bitumen Vg-30 @ 4% (minimum) by the weight of total mix of any penetration compacted to required gradient and camber with 8 to 12 tone power roller, complete all as specified and directed by Engineer-in-charge.NOTE : (i) No extra allowances shall be admissible to the contractor if the bitumen content is required more than 4% by the weight of total mix as per approved design. The contractor shall quote the rate accordingly. |
| 5 | M&L for applying evenly a tack coat of cationic bitumen emulsion (RS-1) conforming to IS : 8887 at a rate of application of 0.20 - 0.30 kg/sqm on bituminous surface as specified in table 500-5 of Morth specification for road and bridge work 2013, using mechanical spraye after cleaning of existing surface by air compressor to remove all loose dirt etc., complete all as specified and directed by Engineer-in-charge |
| 6 | M&L for bituminous premix asphaltic semi dense concrete 40mm consolidated thickness (minimum) with 5.5% binder content of paving bitumen Gde-VG-30 by weight of total mix, rolled and compacted, mixed in mechanical hot mixed plant and pre-mixed material laid with mechanical paver, finished including rolling to required gradient and camber with 8 to 12 tonne power roller to required compaction complete all as specified in the relevant clauses of SSR Part-I (2009) and, complete all as specified and directed by Engineer-in-chargeNote : (a) Rate deemed to be included for making good of any undulation/damages in wearing surfaces, where semi sense asphaltic concrete to be laid. (b) Semi dense asphaltic bituminous concrete shall be designed as specified and binder content shall be provided as per design mix, contractor shall quoted his rates considering the bitumen contents as 5.5%. Any variation in binder content on minus side shall be adjusted at the rate of Rs 50.00 per kilogram of binder but variation in binder plus side shall not be paid extra contractor shall quote accordingly. |
| 7 | M&L for 2.5 mm thick painting to road surfaces as in lines, dashes, arrows, letters , zebra crossing etc on roads, pavements and like with thermoplastic road marking paint @ 5 kg/Sqm and applying glass beads @ 300 gms/Sqm over painted surfaces while the painted surfaces are hot by mechanical means including cleaning surfaces, complete all as specified and directed by Engineer-in-charge.(Note. The painting shall be carried out through mechanical appliances by the company's approved applicatior). |
| 8 | S&F of Bi-directional Abrasion resistant Raised pavement markers made out of micro prismatic tough polycarbonate lens of approved colour, Engineered thermoplastic body and fixed on the road with Epoxy including making good the disturbed portion of the road, complete all as specified and directed. |
| 9 | Demolition of cement concrete (un-reinforced) of any description and in any position not otherwise specifically provided for complete all as specified and directed. |
| 10 | M&L for 75 mm thick PCC (1:3:6) type C-2 (using 40 mm graded crushed stone aggregate) as in plinth protection/ footpath/ steps finished cement concrete surface even & fair etc including necessary form work complete all as specified and as directed. |
| 11 | Providing and laying of 80mm thick factory made chamfered edge cement concrete paver block of M-30 grade with approved colour, design & pattern as in footpath, parks, lawns, drive ways or light traffic parking etc., of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over and including 50mm thick compacted bed of coarse sand, compacting and proper embedding/ laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with fine sand and cutting of paver block as per required size and pattern, finishing and sweeping extra sand, complete all as per specified and as directed by Engineer-in-charge. |
| 12 | M&L for PCC (1:4:8) type D-2 (using 40 mm graded crushed stone aggregate) as in foundation filling and mass concrete complete all as specified and directed. |
| 13 | M&L for providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3, including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage, excavation, opening wherever required complete all as specified and directed. |
| 14 | Material & Labour for prepareing of new plastered surface of wall anf applying finishing walls with Acrylic Smooth exterior paint of required shade : New work Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm), complete all as specified and as directed.Note :- (1)The contract sum shall be calculated by deducting the amount shown in Credit Schedule attached to this tender, from total amount of Schedule 'A'/BOQ. Please Enable Macros to View BoQ information |