| 1 | Supplying and stacking at site. (DSR-18/16.3) |
| 2 | 63mm to 45 mm size stone aggregate (DSR-18/16.3.2) |
| 3 | 53mm to 22.40 mm size stone aggregate (DSR-18/16.3.3) |
| 4 | Supplying and stacking at site.: Moorum. (DSR-18/16.3.10) |
| 5 | Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road/vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening / binding material to fill up interstices of coarse aggregate, watering and compacting to the required density . (DSR-18/16.4) |
| 6 | Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. (MORTH 502/5.01/A(i)) |
| 7 | Providing and applying tack coat with bitumen VG-10 using emulsion pressure distributor at the rate of 0.25kg/Sqm on prepared bituminous surface cleaned with mechanical broom (MORTH-5.02/503) |
| 8 | Providing and laying dense graded bituminous macadam with Higher capacity batch type HMP using crushed aggregates of specified grading Premixed with bituminous binder VG-30 @4.5% by weight of total mix and filler, transporting the hot mix to work site, laying with hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve to desired compaction as per MORTH Specification CLAUSE No 505 complete in all respects (Morth/5.04/505(B)) |
| 9 | 40mm compacted thickness with bitumen perpetration of [email protected]% by weight of total mix. (MORTH-/5.05/505(B)) |
| 10 | Providing and laying Bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder VG-30 @5.40 Percent of mix and filler transporting the hot mix to work site, laying with hydrostatic paver finisher with sensor control to the required grade, level, and alignment rolling with smooth, wheeled vibratory and tandem rollers to achive the desired compaction as per MORTH specification clause No 507 complete in all respects. (MORTH/5.05/507(B)) |
| 11 | 30mm compacted thickness with bitumen penetration of [email protected]% by weight of total mix. (MORTH-5.05/507(B)) |
| 12 | Part-B Drain workExcavation in foundation in ordinary soil (Loam clay or sand) including lift upto 1.50 M and lead upto 30.00M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer incharge upto a distance of 30m from the foundation trenches (where machine con not reach/move) (SOR-20/251 (A)/4.1.1) |
| 13 | Cement concrete with 4cm gaugeApproved stone ballast coarse sand & cement in the proportion of 8:4:1 including supply of all materials labour tools & Plants etc required for proper completion of the work |
| 14 | 8:4:1 (1 Cement 4: Coarse sand :8 graded stone aggregate 40mm nominal size) (SOR-20/281/5.08) |
| 15 | Plain/Reinforced Cement concrete in open foundation complete as per Drawing and Technical Specifications. (MORTH-20/9.06/E/Case-II) |
| 16 | RCC Grade M-25 using batching plant transit mixture and manual placing (MORTH-20/9.06/E/Case-II) |
| 17 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. (DSR-18/5.22) |
| 18 | Thermo Mechanically treated bars of grade Fe-500D or more. (SAIL Steel) (DSR-18/5.22.6/AR) |
| 19 | Part-C Grass paver TilesExcavation in foundation in ordinary soil (Loam clay or sand) including lift upto 1.50 M and lead upto 30.00M and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer incharge upto a distance of 30m from the foundation trenches (where machine con not reach/move) (SOR-20/251 (A)/4.1.1) |
| 20 | Preparation and consolidation of sub grade with power road roller of 8 to 12 tonne capacity after excavating earth to an average of 22.5 cm. depth, dressing to camber and consolidating with road roller including making good the undulations etc. and re-rolling the sub grade and disposal of surplus earth with lead upto 50 metres. (DSR-18/16.1) |
| 21 | Wet mix macadam (Plant mix method)Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with grader in sub-base/base course on well prepared surface and compacting with vibratory roller to achieve the desired density (MORTH/4.14/406(B)) |
| 22 | Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x70 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:3 (1 cement : 3 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge. (AR/GNIDA) |
| 23 | Cement concrete with 4cm gauge approved stone ballast, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work. (SOR-20/279)Same as above item no 279 but with 2cm gauge stone grit instead of 4cm gauge stone ballast. (SOR-20/279(a) |
| 24 | Labour cess and GST will be paid extra as per Govt. orders. Please Enable Macros to View BoQ information |