| 1 | The work of safe carriage of the following material from store center-byebag SPN to work site under the jurisdiction of EDD-Chinour. Approx. distance upto 0-80 Km. Including safe loading and unloading. |
| 2 | PCC Pole 8.5/ 9.0 meter long. |
| 3 | PCC Pole 11 Mtr Long by haydra machin loding and unloading |
| 4 | ST Pole 9.0/11/13 meter long. |
| 5 | Line material i.e., cross arm/ conductor/ pin insulater/stay/earthing rod/Disc Fitting/Disc Insulators/11 KV XLPE Cable etc |
| 6 | Safe carriag of Single phase ABC Cable 1*16 sqmm |
| 7 | Safe carriag of three phase ABC Cable size 3*50 sqmm/3*95 sqmm/3*120 sqmm |
| 8 | Safe carriag of LT XLPE 11 KV 3*120 sqmm/3.5*240 sqmm |
| 9 | Safe carriag of 11 KV XLPE CABLE SIZE 3*70 sqmm/3*95 sqmm/3*120 sqmm/3*185 sqmm/3*300 sqmm |
| 10 | Safe Carrige Cable of 33 kv Xlpe Cable |
| 11 | Safe carriag of Cable Jointing kit Cable Size 3*70 sqmm/3*120 sqmm/3*185sqmm/3*300 sqmm. |
| 12 | Safe carriag of ACSR Weasel Conductor New/Old |
| 13 | Safe carriag of Rabbit Conductor |
| 14 | Safe carriag of ACSR Dog Conductor New/Old |
| 15 | SAFE LOADING UNLOADING of 250 / 400/630 kva t/f by haydra machine AND CARRIAGE OF NEW / REPAIRED T/F STORE CENTER BAYBAGH /WORK SHOP SPN |
| 16 | Erection of new H.T / L.T lines including fitting of all accessories as per RESSPO Norms (All type of clamps required and T&P nut bolt of various size provided by contractor. Complete in all respect. As per RESSPO schedule.) |
| 17 | Single PCC Pole 8.5/9.0/11.0 meter long. |
| 18 | Double PCC Pole 8.5/9.0/11.0 meter long. |
| 19 | Tri PCC Pole 8.5/9.0/11.0 meter long. |
| 20 | Four PCC Pole 8.5/9.0/11.0 meter long. |
| 21 | Single STP 9/11 Mtr Long |
| 22 | Double STP 9/11 Mtr Long |
| 23 | Tri ST Pole 9.0 meter long. |
| 24 | Four ST Pole 9.0 meter long. |
| 25 | Grouting with 1:4:8 mixture in size(450x450x1500mm.) including cost of cement/BB & sand Required as per RESSPO Norms |
| 26 | PCC Pole 8.5/9.0/11.0 meter long. |
| 27 | The work of Driving the earthing electrode and making connections with 6 S.W.G. GI wire as per RESSPO Norms |
| 28 | Replacement of damaged conductor/ABC as per norms complete in all respect |
| 29 | Laying, Stringing & Sagging of Following Conductor complete in all respect only conductor/AB cable provided by department and usable I Huck/clamp/nut bolt/washer etc. provided contractor own his cost. |
| 30 | Replecement Of Damaged T/F From Central Store, Baibagh Spn/ Work Shoop And Loading Unloading And Installation Work In Plece Of Damaged T/F After That Safe Loading Unloading And Carrage Of Damaged T/F From Plinth To Central Store / Work Shop Spn After Cpmplete Of Dtc Work Of Damaged T/F . (Nos) |
| 31 | HT/LT conection and discinection of 250/400/630 kva transformer |
| 32 | ACSR Weasal Conductor |
| 33 | ACSR Rabbit Conductor |
| 34 | ACSR DOG Conductor |
| 35 | ACSR Raccoon Conductor |
| 36 | Laying of AB cable 3x50/3x95/3x120 |
| 37 | Laying of AB cable 1x16 |
| 38 | Laying of LT XLPE Cable 11 KV |
| 39 | Grouting of stays, 1:4:8 cc ratio (600x600x300mm.) as per RESPO norms. |
| 40 | Straightening of Tilted pole complete in all respect |
| 41 | Replacement of Broken X-Arm complete in all respect |
| 42 | Replacement of damage disc insulator of 33/11 KV line including carriage of insulator from JE store to site (disc insulator provided by department.) |
| 43 | Cutting/Chopping of Tree Branches. |
| 44 | Erarthing by boaring type upto water level 30 fit by providing GI pipe and welding of strip from boaring site to nutral and body of T/F. All the material, fabrication provided by contractor on his cost. Complete in all respect. |
| 45 | Maintinance/Owarholling Works of 11/33 KV Pannls (Incomming/Outgoing) |
| 46 | Termination of 11 KV cable heat shrinkable type jointing kit/ termination kit suitable 11 KV cables of the following sizes after removal of faults (suitable jointing kit will be provided by the department.) |
| 47 | 3x70/ 3x120/3x185 sqm XLPE cable O/D and I/D |
| 48 | 3x240/ 300 sqm XLPE cable O/D and I/D |
| 49 | 11 KV straight though 3x120/3x185 |
| 50 | Termination of 33 KV cable heat shrinkable type jointing kit / termination of kit suitable for 33 KV cable of following size after removal of faults (suitable jointing kit will be provided by the department.) |
| 51 | 3x300 sqm XLPE cable O/D and I/D |
| 52 | 3x120 sqm XLPE cable O/D and I/D |
| 53 | 3x120 / 3x300 sqm XLPE cable straight through |
| 54 | The work of find the location and pin pointing of 33 KV cable foult in 33 KV damage underground XLPE cable by foult locator machine. (Cable foult locator equipment mounted on a vehicle will be arrange by the contractor) |
| 55 | The work of find the location and pin pointing of 11 KV cable foult in 11 KV damage underground XLPE cable by foult locator machine. (Cable foult locator equipment mounted on a vehicle will be arrange by the contractor) |
| 56 | Laying of 11 KV single circuit XLPE cable by digging of trench including supply of required material as fine sand, first class bricks, stone slab. Including refilling of trench. (All the matrial required for laying will be supplied by the contractor as per departmental norms except 11 KV XLPE cable) |
| 57 | Straightening of tilted X-arm |
| 58 | Straightening of Tilted 9/11/13 mtr stp |
| 59 | Resagging and tightening of 33 kv line |
| 60 | Resagging and tightening of 11 kv line |
| 61 | Resagging and tightening single phase abc of lt line |
| 62 | Resagging and tightening three phase abc of lt line |
| 63 | Straightening of tilted f-clamp |
| 64 | Fabrication work |
| 65 | FIXING AND PROVIDING OF X- ARM CLAMP |
| 66 | FIXING AND PROVIDING OF STAY CLAMP |
| 67 | FIXING AND PROVIDING OF TEE-OFF & TOP CHANNEL CLAMP |
| 68 | FIXING AND PROVIDING OF LT CLAMP |
| 69 | FIXING AND PROVIDING OF DED AND CLAMP FOR PCC/STP |
| 70 | FIXING AND PROVIDING OF SUSPENSION CLAMP |
| 71 | FIXING AND PROVIDING OF I HOOK FOR PCC /STP |
| 72 | FIXING AND PROVIDING OFNUT AND BOLT OFF SIZE |
| 73 | WELDING OF ST POLE WELDING MATERIAL PROVIDED BY THE CONTRACTOR |
| 74 | Laying of 33 KV single circuit XLPE cable by digging of trench including supply of required material as fine sand, first class bricks, stone slab. Including refilling of trench. (All the matrial required for laying will be supplied by the contractor as per departmental norms except 33 KV XLPE cable) |
| 75 | Safe carriage of received back material (scrap) form site to store centre-Byebag SPN Up to 0-80 Km. with loading/unloading both side. Please Enable Macros to View BoQ information |