Name of Work:- Construction of reinforced cement concrete safety compound wall for Government assets under SD-II WD-V DDW Gogal Margao Goa.
Sl. No.
Item Description
1
Earthwork in excavation by mechanical means (hydraulic excavator)/manual means over areas (exceeding 30 cm in depth 1.5 m in width as well as 10 sq.m on plan) including disposal of excavated earth lead upto 50 m and lift upto 1.5m disposed earth to be leveled and neatly dressed including providing barricading danger lighting guarding as directed in :;All kinds of soil
2
Rubble packing with hard laterite stone under floors including watering ramming and consolidating etc. in pipeline trenches and other foundations complete.
3
Providing & laying cement concrete 1:2:4 (1 cement: 2 coarse sand: 4 graded granitic or basaltic stone aggrt. 20 mm. nominal size) excluding cost of centering shuttering and finishing in:;All works upto plinth level
4
Providing and laying in position (1:11/2:3) Reinforced cement conrete excluding the cost of centering shuttering finishing and reinfrocement (1 cement: 1½ coarse sand:3 graded stone agg 20mm nominal size);All works upto plinth level
5
Providing and laying in position (1:11/2:3) Reinforced cement conrete excluding the cost of centering shuttering finishing and reinfrocement (1 cement: 1½ coarse sand:3 graded stone agg 20mm nominal size);In walls (any thickness) including attached pilasters buttresses plinth and string courses fillets columns pillars piers abutments posts and structs etc. upto floor five level
6
Providing and laying in position (1:11/2:3) Reinforced cement conrete excluding the cost of centering shuttering finishing and reinfrocement (1 cement: 1½ coarse sand:3 graded stone agg 20mm nominal size);In beams suspended floors roofs having slope upto 15° landings balconies shelves chajjas lintels bands plain window sills staircases upto floor five level
7
Providing TMT steel reinforcement bars of (SAIL TATA. VIZAG JSW Steel Ltd.) ) (Confirming to IS 1786 of 1986) for RCC work (conforming to I.S. 1786 of 1986) including bending binding & placing in position in all the floors along with the factory made precast concrete cover blocks of specified sizes whose compressive strength is not less than that of surrounding concrete in the structural member.
8
Centering and shuttering including struttings propping etc. and removal of formwork for :;vertical surfaces such as retaining walls return walls walls (any thk) including attached pilasters buttresses plinth and string courses fillets etc.
9
Centering and shuttering including struttings propping etc. and removal of formwork for :;Columns Pillars piersabutments posts and strut square rectangular polygon in plan. etc.
10
Pre-cast cement concrete solid block masonry of compressive strength 70 kg / cm2 in cement mortar 1:4 (1 cement : 4 corase sand ) in foundation and plinth size of blocks (30 x 20 x 15);In foundation and plinth
11
Extra for precast concrete block masonary in all sizes in superstructure from floor one level upto floor V level
12
20mm cement plaster 1: 3 (1 cement : 3 fine sand)
13
Neat Cement punning
14
Painting three or more coats with acryllic exterior paint of approved brand and manufacture (Such as Dulex/ Asian Paints/ Sherwin Willians) including applying one coat of cement primer and one coat of surface treatment etc. complete. Please Enable Macros to View BoQ information
We takes all possible care for accurate & authentic tender information, however Users
are requested to refer Original source of Tender Notice / Tender Document published by
Tender Issuing Agency before taking any call regarding this tender.