| 1 | Excavating trenches of required width for pipes, cables, etc including excavation for sockets, and dressing of sides, ramming of bottoms, depth up to 1.5 m, including getting out the excavated soil, and then returning the soil as required, in layers not exceeding 20 cm in depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, within a lead of 50 m : |
| 2 | All kinds of soil |
| 3 | Pipes, cables etc, not exceeding 80 mm dia. |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : |
| 5 | 1:2:4 (1 cement : 2 coarse sand(zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) |
| 6 | 1:5:10 (1 cement : 5 coarse sand (zone-III) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) |
| 7 | Cutting road and making good the same including supply of extra quantities of materials i.e. aggregate, moorum screening, red bajri and labour required. |
| 8 | bituminous portion |
| 9 | Cutting holes up to 30x30 cm in walls including making good the same: |
| 10 | With common burnt clay F.P.S. (non modular) bricks. |
| 11 | Providing and laying non-pressure NP2 class (light duty) R.C.C. pipes with collars jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 cement : 2 fine sand) including testing of joints etc. complete : |
| 12 | 150 mm dia. R.C.C. pipe |
| 13 | Constructing brick masonry manhole in cement mortar 1:4 ( 1 cement : 4 coarse sand ) with R.C.C. top slab with 1:1.5:3 mix (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size), foundation concrete 1:4:8 mix (1 cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size), inside plastering 12 mm thick with cement mortar 1:3 (1 cement : 3 coarse sand) finished with floating coat of neat cement and making channels in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) finished with a floating coat of neat cement complete as per standard design : |
| 14 | Inside size 90x80 cm and 45 cm deep including C.I. cover with frame (light duty) 455x610 mm internal dimensions, total weight of cover and frame to be not less than 38 kg (weight of cover 23 kg and weight of frame 15 kg) : |
| 15 | With Sewer bricks conforming to IS : 4885 |
| 16 | Making connection of drain or sewer line with existing manhole including breaking into and making good the walls, floors with cement concrete 1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) cement plastered on both sides with cement mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of neat cement and making necessary channels for the drain etc. complete : |
| 17 | For pipes 100 to 250 mm diameter |
| 18 | Cleaning of sewer line, sewer manhole,gully chamber by using bamboo/rod for clearing the sewer line,taking out sludge, debris, rubbish and other waste materials, if any, from the sewer line and flooding/flushing with sufficient quantity of water with pressure to ascertain through cleaning of drainage system for smooth and proper functioning of sewer line including disposal of the all waste material outside the muncipal limit or burried into pits at safe available distance as directed all complete. (Note-The operation includes cost of all and nothing shall be paid extra on any account) |
| 19 | Gully Chambers |
| 20 | Sewer Manholes With attached Lines |
| 21 | Cleaning and dewatering of septic tank by bailing out or pumping out the liquid sewage and taking out deposited silt, sludge and manure through mechanical means and disposal of sludge out side the compound to nearest dumping ground to any lead. |
| 22 | Septic Tank upto 70 users capacity |
| 23 | Septic Tank up 100 users capacity Please Enable Macros to View BoQ information |