| 1 | Earthwork in excavation for structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 20 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 2 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawing and technical specification clause 802, 803, 1202 & 1203 P.C.C. Grade M 10 (Nominal Mix 1:3:6) within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 3 | Providing concrete for plain/reinforced concrete in open foundations complete as per drawing and technical specification clause 802, 803, 1202 & 1203 P.C.C. Grade M 20 (Nominal Mix 1:2:4) within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 4 | Providing and laying reinforced cement concrete in superstructure as per drawing and technical specifications clauses 800, 1205.4 and 1205.5 R.C.C. M 25 (1:1.5:3) upto 5m Height. within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 5 | Supplying, fittng and placing TMT bar reinforcement in superstructure complete as per drawing and technical specification clauses 1002,1010 and 1202 within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 6 | Providing and laying flooring laid over cement concrete bedding Rubble stone laid in Cement Mortar 1:3 complete as per drawing and technical specification clause 1303 within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 7 | Back filling behind wing walls and return walls complete as per drawing and technical specification clause 1204.3.8. within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 8 | Providing and laying boulder apron (Stone filling under floor) for bed protection with boulders of minimum size and weight as per Table 1300.1, no fragment weighing less than 25 kg laid dry complete as per drawing and technical specification clause 1301. within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. |
| 9 | Providing weep holes in Brick masonry/Stone masonry Plain/Reinforced concrete abutment, wing wall, return wall with 100 mm dia AC Pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204.3.7 within all leads and lift including carriage of materials and as per direction of Engineer-in- charge. The rate is including octroi, Royality, Malkana, Toll Tax, or any other Taxes imposed by the Government including GST. Please Enable Macros to View BoQ information |