| 1 | Providing & fixing of GI Channel cross-arm (100 x 50x6mm) / 75x40x40 x6mm including back clamps of 50X8 mm for fixing Cross arm and pole top bracket, Angle Pole Top Bracket (50x50x6 mm) including back clamps of 50X8 mm for fixing Cross arm and pole top bracket . . |
| 2 | Supply,installation, testing and commissioning of Gapless Surge Arrestor, 9kV, 10KA LA with polymer housing, station type. |
| 3 | Supply,installation, testing and commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 4 | Supply,installation, testing and commissioning of 11kV GO, AB Switch 3-Phase, 3-Pole,200 Amp, Vertical Type |
| 5 | Supply,installation, testing and commissioning of 185 mm² Single-Core Cable, 1.1kV Grade, XLPE un armoured FRLS type |
| 6 | Supply,installation, testing and commissioning of 270 mm² Single-Core Cable, 1.1kV Grade, XLPE un armoured FRLS type |
| 7 | Providing & Laying of Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm No.minal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover |
| 8 | Supply,installation, testing and commissioning of LT Fuse Set |
| 9 | Supply,installation, testing and commissioning of GI wire |
| 10 | Sundry Items like Aluminium Lugs, Jumpers, Binding Tape |
| 11 | Pre and Post Geo tagged Photographic Evidence consisiting of 5x7 inch Photographs and Autocad Single Line Diagram Please Enable Macros to View BoQ information |