| 1 | Repairing of leakages including excavation dewatering, patch clamp, CID joints, labour & all others material required for leakage repairing etc. |
| 2 | 200 mm dia 1.11) A) leakage repaired by patch clamp |
| 3 | 200 mm dia 1.12) B) leakage repaired by CID |
| 4 | 150 mm dia 1.21) A) leakage repaired by patch clamp |
| 5 | 150 mm dia1.22) B) leakage repaired by CID |
| 6 | 100 mm dia 1.31) A) leakage repaired by patch |
| 7 | 100 mm dia1.32) B) leakage repaired by CID |
| 8 | Helper |
| 9 | Rent for JCB |
| 10 | Providing and supplying D.I. fittings with I SI mark Mechanical j oint confirming2) 100 mm dia |
| 11 | Providing and supplying D.I. fittings with I SI mark Mechanical j oint confirming3) 150 mm dia |
| 12 | As above of 1.5 x 1.5 M internal size and depth upto 1.5 M with precast R.C.C slab cover. |
| 13 | Providing and supplying ISI mark CI D/F reflux valves (non-return valves )4) 100 mm. |
| 14 | Providing and supplying ISI mark CI D/F reflux valves (non-return valves )6) 150 mm. |
| 15 | Providing and supplying ISI mark CI D/F reflux valves (non-return valves )7) 200 mm. |
| 16 | Excavation for foundation / pipe trenches in earth, soils of all types, sand, gravel and soft murum, including removing the excavated material upto a distance of 50 metres and lifts as below, stacking and spreading as directed, normal dewatering, preparing the bed for foundation and excluding backfilling, etc. complete. (Bd-A-1/259) |
| 17 | Lowering,laying and jointing in position following C.I.D/F Reflex valves,4) 100 mm. |
| 18 | Lowering,laying and jointing in position following C.I.D/F Reflex valves,6) 150 mm. |
| 19 | Lowering,laying and jointing in position following C.I.D/F Reflex valves,7) 200 mm. |
| 20 | Giving satisfactory hydraulic testing of following C. I. D / F Reflex valves,4) 100 mm. |
| 21 | Giving satisfactory hydraulic testing of following C. I. D / F Reflex valves,6) 150 mm. |
| 22 | Giving satisfactory hydraulic testing of following C. I. D / F Reflex valves,7) 200 mm. |
| 23 | Dismantling brick masonry in lime or cement mortar and stacking the materils as directed with all leads, lifts etc. |
| 24 | Testing:-BRICKS: Water Absorption (Set of 5 4,350.00 1 Test 8,700.00Bricks), Compressive Strength( Setof 5 Bricks), Efflorescence (Set of 5Bricks) Please Enable Macros to View BoQ information |