| 1 | CC Drain |
| 2 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres All kinds of soil : |
| 3 | Laying (First Class Type B) bedding on well compacted sand, moorum or approved granular material as per Clause 1105 (ii) including Carriage |
| 4 | (CEMENT CONCRETE CAST-IN-SITU) Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)including all carriages of material involved |
| 5 | (CAST-IN-SITU) Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)including all carriages of material involved |
| 6 | Cement concrete flooring 1:2:4 finished with a floating coat of neat cement including cement slurry and curing complete, but excluding the cost of nosing of steps etc. complete 40 mm thick with 20 mm nominal size stone aggregate including all carriages of material involved. |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form work for Foundations, footings, bases for columns |
| 8 | Backfilling behind abutment,wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 Including loading, unloading,haulages, royality,octroi charges, form work etc complete. |
| 9 | 300 mm Pipe |
| 10 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres:2.9.1 All kinds of soil : |
| 11 | Providing and laying reinforced cement concrete pipe NP3 for culverts on first class bedding of granular material in double row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets as per Clause 1106. 300 mm dia including all carriages of material involved |
| 12 | Backfilling behind abutment,wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 Including loading, unloading,haulages, royality,octroi charges, form work etc complete. |
| 13 | CRASH BARRIER |
| 14 | Providing and erecting W metal beam crash barrier comprising 3mm thick corrugated sheet metal beam rail, 70 cm above road/ground level fixed on ISMC series channel vertical posts,150X75X5 mm spaced 2m centre to centre, 1.80 M high, 110 cm below ground level all steel parts and fitments to be galvanised by hot dip process , all fittings to confirm to IS 1367 and IS 1364 metal beam rail to be fixed on vertical posts with spacer channel section 150X75X5 mm, 330 mm long complete as per clause 810 including earthwork in excavation by mechanical means and disposal of same by engineer in charge in all kinds of soil and embedding of vertical channel posts in PCC M15 (1:2:4) block of size 0.45 x 0.45 x 1.1 m and cost of nuts and bolts including loading unloading cost of carriage of all materials to site of work complete job (finished job to be measured) |
| 15 | CULVERT RAILING |
| 16 | Demolishing R.C.C. work manually/by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge |
| 17 | Providing and laying in position specified grade of reinforced cement concrete including curing but excluding the cost of centering, shuttering, finishing and reinforcement. All works upto plinth level 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size)including all carriages of material involved |
| 18 | Centering and shuttering including strutting, propping etc. and removal of form work for Foundations, footings, bases for columns |
| 19 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing inposition and binding all complete upto plinth levelMild steel and medium tensile steel bars |
| 20 | Railing: Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat ofapproved steel primer all complete.Welded |
| 21 | Total Construction cost without GST Please Enable Macros to View BoQ information |