| 1 | Total of Schedule-A |
| 2 | Total of Schedule-B(Manpower) OCP-2185 APPENDIX- 3A PROFORMA FOR STATEMENT OF MINOR DEVIATIONS (Refer Clause C 2.2(e) and C 15.1 of ITT) 1. The following are the particulars of minor deviations from the requirements of the Tender Document: Sr. No Clause Deviations Price adjustment for each deviation/s Note : 1. The Tenderer shall indicate price adjustment against each deviation in Appendix-3A of BOQ. This price is the price which the tenderer shall reduce from this tender price if deviation(s) is/are accepted by the Employer. 2. Where there is no deviation, the statement should be returned duly signed with an endorsement indicating ‘No Deviations’. In case, Performa of deviations is not submitted or submitted as blank, it will be construed that the tenderer has not proposed any deviations from tender documents. 3. If the tenderer proposes deviations in tender documents, and/or any other terms and conditions of the tender, other than in this Appendix, it will have no effect. Signature of authorized signatory On behalf of Tenderer OCP-2185 Preamble |
| 3 | The Bill of Quantities shall be read in conjunction with Notice Inviting Tenders, Instructions to Tenderers, General and Special Conditions of Contract, Employer's Requirement, Technical Specifications and other relevant documents. |
| 4 | BoQ1 consists of Schedule ‘A’ and Schedule ‘B’ (for Manpower) |
| 5 | The rates and prices to be tendered in the unit Priced Bill of Quantities of Schedule A & B are for completed and finished items of works and complete in all respect. |
| 6 | Tenderers shall quote their offer in Indian Rupees (INR) only. Tenderers are required to be quoted percentage (%) Excess/Less for Schedule-A & B in figures in the appropriate highlighted cells in the BoQ1 sheet. All the quoted rates will be deemed to include Duties, Taxes, Octroi, Royalty etc., cost of all plants, labour, supervision, materials, transport, all temporary works, erection, maintenance, utility identification, contractor’s profit and establishment/ overheads, together with preparation of design and drawings, all general risks, insurance liabilities, compliance of labour laws and obligations set out or implied in the contracts. For taxes and duties refer clause C2.5 of ITT & clause 21 of SCC. |
| 7 | If the tenderer fails to quote rates against any item, the tender may be treated as incomplete and non- responsive and shall be rejected. |
| 8 | Errors will be corrected by the employer for any arithmetical errors in computation or summation as per contract conditions. |
| 9 | The Financial Proposal (as per BOQ) shall be uploaded online on the website https://etenders.gov.in/eprocure/app. The rates shall be quoted in the excel file provided in the bid documents. The tenderer shall download the excel file and quote the rates against each highlighted cells in BoQ1. After quoting their rates the excel file shall be uploaded accordingly. The rates shall not be offered/quoted elsewhere in the technical submission/ tender submission. |
| 10 | The actual work executed against all the BOQ as detailed in tender document would be paid on measurement basis. |
| 11 | The contractor may raise their “On Account” payments on monthly basis as per the status of work on the last day of the respective month as per clause 24 of SCC. DELHI METRO RAIL CORPORATION LIMITED Bill of Quantity (BOQ) Contract: OCP-2185 \\"Rail/ Crossing Switch loading & transporation from depot to main line & vice versa and Rail/ Crossing Switch replacement work and necesary preparation for AT weld at Line-3 (Dwarka Sector -21 to Noida Electronic City). Line-4 (Yamuna Bank to Vaishali). Line-9 (Dwarka to Dhansa) of DMRC Network.\\" Item No. Item wise description of work( Full Description) Unit Rate (in Rs.) Quantity Amount (in Rs) Schedule-A |
| 12 | Rail Replacement at main line on viaduct / tunnel / At- grade section as per direction of Engineer in - charge |
| 13 | Crossing Replacement ( with all pads, plates, fittings & fastening etc.if required) at main line on vaiduct / tunnel/ At- grade section as per direction of Engineer in - charge |
| 14 | Half set Switch Replacement (with all sliding chair, fish keys, pads, plates, fittings & fastening etc.if required) at main line on vaiduct / tunnel/ At- grade section as per direction of Engineer in - charge |
| 15 | Loading of Rails/ crossing / switch in depot using Hydra |
| 16 | Manual Transportaition of Rail panel / Crossing / Switch over Dip Lorry from depot to main line or line to depot (Per MT Per KM ) and unloading at the designated location including manual loading if required as per the direction of Engineer in charge. Total amount of Schedule-A (excluding GST) 17331665.0 GST @ 18% on Schedule-A 3119699.7 Total amount of Schedule-A (including GST) 20451364.7 Schedule-B (Manpower) |
| 17 | High skilled manpower for assisting and making necessary preparation of AT welding. |
| 18 | providing semi skilled manpower for shifting of welding material and machinery from platform to actual site and back to platform. Total amount of Schedule -B (excluding GST) 6532295.9 GST @ 18% on Schedule-B 1175813.26 Total amount of Schedule B (including GST) 7708109.16 Grand Total amount of Schedule-A+B (exclusive of GST) ( in INR) 23863960.9 Grand Total amount of Schedule-A+B (inclusive of GST) ( in INR) 28159473.86 Please Enable Macros to View BoQ information |