| 1 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed: All kinds of soil : ) |
| 2 | Dismantling manually/ mechanically including stacking of serviceable material and disposal of unserviceable material within 50 meters lead as per direction of Engineer-in-charge:Bituminous road. |
| 3 | Laying and fitting of G.I. pipes (all classes) complete excluding cost of pipes, fittings and Earth work. |
| 4 | 25 mm dia GI Pipe |
| 5 | 20 mm dia GI Pipe |
| 6 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20 cm in depth, consolidating each deposited layer by ramming and watering, lead upto 50 m and lift upto 1.5 m. |
| 7 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with: 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) |
| 8 | Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing Tee, including cutting and threading the pipe etc. complete(25 to 40 mm nominal bore ) |
| 9 | Providing and placing on terrace (at all floor levels) polyethylene water storage tank ISI : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank |
| 10 | Provision for pipe special to be paid as per actual complete job |
| 11 | Fixing charges of PVC Storage Tanks at Camp site 1000/500 Ltr Capacity . |
| 12 | Dismantling G.I. pipes (external work) including excavation and refilling trenches after taking out the pipes, manually/by mechanical means including stacking of pipes within 50 meters lead as per direction of Engineer-in-charge :15 mm to 40 mm nominal bore. |
| 13 | Providing fixing / installation of shamiana /refreshment incld. Frame structure , fabric covering , roofs, holes and other required accerioes and sitting arrngments incld. All carriges leads , lifts , at Novyug Tunnel during reception of Amarnath ji Yatra |
| 14 | Providing fixingof pvc pipes of approved make incld. Cost of all fittings required and carriage complete (20mm dia PVC Pipe) |
| 15 | Installation of PSP inside bathroom/Washroom , Kitchen and other required parts incld. Cost of pipes and pipe specials and carrige all complete |
| 16 | Reparing to exsting 01 HP moter submersible incld. All accessories etc complt. Job to exsiting borewell , used during yatra period. |
| 17 | Installation of / opertion of 01 HP moter submersible incld. All allied accessories etc. complete during yatra period |
| 18 | Providing fixing of angle iron stand of structures steel incld. All carriges |
| 19 | Desilting of sumps t Pandith colony vessu for securty establishment |
| 20 | Provision of Uniform |
| 21 | Welding Charges at spot for arresting of lekages for pipes, MS Lid at Vessu Colony extra incld. All carriages complt. |
| 22 | Provding fixing of banners extra completed |
| 23 | Carriage of pipes from divisional store qazigund up to various dumping sites on road by Mechanical Transport for an Avg Lead of 5 Km Please Enable Macros to View BoQ information |