| 1 | Construction of 33KV Gomat alongwith other associated works at 132KV Substation Khair, with all Cost of Men, Materials, Misc. Consumables, T&Ps etc. Required for Satisfactory Completion of the Work as per Technical Specifications and Direction of the Supervising Engineer as per Site Requirement and Details below : |
| 2 | Supply of Materials |
| 3 | Supply of PG Clamp duly made of LM-6 Aluminium Alloy, suitable for Panther to Panther Conductors, complete with 4 No. 16x90mm Size GI Bolts, Nuts, Spring & Plain Washers, as per Technical Specification & Sample. |
| 4 | Supply of PG Clamp duly made of LM-6 Aluminium Alloy, suitable for Moose to Panther Conductors, complete with 4No. 16x90mm Size GI Bolts, Nuts, Spring & Plain Washers, as per Technical Specification & Sample. |
| 5 | Supply of 33KV C.T. Bi-Metallic Terminal Connector Duly made of LM-6 Aluminium Alloy, along with Bi-Metallic Sleeve/ Plate Suitable for Twin ACSR Panther Conductor with 4Nos. 12mm Size GI Bolts, Nuts, Spring & Plain Washers, as per Technical Specification & Sample. |
| 6 | Supply of 33KV Isolator Bi-Metallic Terminal Connector Duly made of LM-6 Aluminium Alloy, along with Bi-Metallic Sleeve/ Plate Suitable for Twin ACSR Panther Conductor with 4Nos. 12mm Size GI Bolts, Nuts, Spring & Plain Washers, as per Technical Specification & Sample. |
| 7 | Supply of 33 KV C.T. Junction Box with Terminal Block, Terminal block having drop down link with water proof rubberized seal & lock arrangement. |
| 8 | Providing &Fixing of 150 Watt L.E.D. Street Light Luminaries Fittings of Philips / Compton Greaves / Havells make in Single Piece Die Cast Aluminium Alloy Housing with Pot Optics Reflector & Toughened Clear Glass Cover with Frame for Lamp Compartment inlcuding Cable Terminations and associated works. |
| 9 | Supply of MS Flat 50X6 MM |
| 10 | Supply of CO2 fire extinguisher 4.5 Kg |
| 11 | Supply of Dry chemical fire extinguisher 4.5 Kg |
| 12 | Supply of Mechanical Foam type fire extinguisher 50 ltr trolley Mounted |
| 13 | Supply of 2 Ton window AC with all accessories and steplizer ( Not less tanh 5 KVA Capacity) |
| 14 | Supply of sand Buckets as per technical specification |
| 15 | Erection Work |
| 16 | Proper Shifting , sorting counting loading and stacking of alotted structures on trucks arranged by the contractor including transportation from storage location to the loading site |
| 17 | Safe carriage of the structure loaded on the trucks duly arranged by the contractor from stores of EFU naini allahabad to 132kv Substation Khair with all due care of safety and precaution during transit required for the job including insuarance /fare/toll tax etc of all the trucks |
| 18 | Unloading of structure at the 132kv Substation Khair including transportation of the structure from the unloading site to the main work site |
| 19 | Safe Loading, Carriage and Unloading of various items like VCB, BSI, LSI, CT, MS Flat ABL,ALP etc. from designated substation to 132KV S/S Khair with help of hydra and truck provided by Contractor with all cost of man material etc. as per requirement. |
| 20 | Erection of Main and Auxiliary structure consisting of columns, beams, peaks, masts etc. and auxiliary structure required for installation of Isolators, CTs, PTs, LAs, and other equipments. The job consists of shifting of all material i.e. structure parts, nuts, bolts, washers etc. from store to site of erection, erection of structure as per relevant drawing and practices using flat and spring washer with each bolt Matching of holes, cutting, matching of members if required shall also be done by the contractor without any extra cost to complete the work satisfactorily. All material to be erected shall be supplied by UPPTCL free of cost but all men, material and T&P required for satisfactorily completion of work shall be arranged by the contractor at his own cost. |
| 21 | Erection of Following Equipments in 33KV Gomat Bay including their Shifting from Storage Place at the Sub Station to Erection Site : |
| 22 | 33KVC.B. |
| 23 | 33KV C.T. |
| 24 | 33KV Bus Isolator with associated PIs |
| 25 | 33KV Line Isolator with associated Earth Blades & PIs |
| 26 | 33KV C.T. / P.T. Junction Box |
| 27 | 33KV Feeder Control & Relay Panel |
| 28 | Interconnection of following equipment and bus bar including cutting, bending of conductor and jumpering clamping along with all other associated work to complete the job satisfactorily as per drawing and technical specifications with Main. |
| 29 | 33KV Line Bay |
| 30 | Laying of Following sizes Control Cables in Cable Trenches from Control & Relay Panels in Control Room to various Equipments, Junctions Boxes etc. in Switchyard as per Cable Schedule including Shifting of Cables in Drums from Storage Place at the Sub Station to Erection Site and Shifting Back the Balance Cables to Stores at the Sub Station : |
| 31 | 2C x 2.5 mm2 |
| 32 | 4C x 2.5 mm2 |
| 33 | 6C x 2.5 mm2 |
| 34 | Termination of 2C x 2.5 mm2, 4C x 2.5 mm2 and 6C x 2.5 mm2 sizes above Laid Control Cables Extending D.C. Supply from DCDB and A.C. Supply from ACDB to Control Panels & Equipments including Drilling of Holes, Providing and Fixing of Cable Glands, Ferrules &Crimping type Lugs. (as per site consumption upto maximum) |
| 35 | Earthing of Main & Aux. Structures and Equipments (CB, Isolators, CTs, PTs, C&R Panel, Junction Boxes etc.) with 50 × 6 mm size M.S. Flat by Cutting, Straightening & Laying 500 mm below Inside Ground & above Ground as per norms and Diagonal / Double Earthing of the Main & Aux. Structures, Equipments including Welding with Main Earth Mat and with the Object to be Earthed including Excavation of Trenches & its Back Filling etc.(as per site consumption upto maximum) |
| 36 | Painting of 50 × 6 mm size M.S. Earthing Strip in Bus Green Colour by Rubbing with Sand Paper & Wire Brush, then Painting with 1 Coat of Red Oxide Primer & 2 Coats (The 2nd Coat of Paint shall be Applied at the Gap of 48 hrs. when 1st Coat of Paint is done &Checked by concerned S.D.O. / J.E.) of 1st Quality Synthetic Enamel Paint of Asian / Berger / Nerolac make in Bus Green / Black Colour. (as per site consumption upto maximum) Please Enable Macros to View BoQ information |