| 1 | Earthwork in surface excavationby mechanical means in foundation and trenches and lead up to 50 m ….....complete |
| 2 | Providing and laying in cement concrete 1:4:8 with Stone ballast including all materials, labours T&P etc . |
| 3 | Rcc work with cement approved coarse sand and 2 cm gauge approved stone grith in 1:1.5:3proportation for slab ,up to plinth level …..complete |
| 4 | Rcc work with cement approved coarse sand and 2 cm gauge approved stone grith in 1:1.5:3proportation for slab ,above plinth level complete |
| 5 | Thermo mechanically treated bars of grade Fe500D or more in rcc work |
| 6 | centering and shuttering including strutting proping etc removal of form work for foundation footing base of column etc |
| 7 | centering and shuttering including strutting proping etc removal of form work for column piller piers and struts etc |
| 8 | centering and shuttering including strutting proping etc removal of form work for lintel beams plinth beams and antilivers etc |
| 9 | m-150 brick work in 1:6cement and coarse sand in foundation and plinth including supply of all material ,labour and t$p etc. required for proper completion of work in super structure |
| 10 | 12mm thick cement plaster with 1:4 cement and sand mortor on fair side of wall including all material, labours, T&P etc all complete. |
| 11 | painting with water proofing cement paint two or more coat with base of cement primer ..complete |
| 12 | STEELwork in built up section /framed work including cutting straighting etc with one coat of primer etc complete |
| 13 | Earthwork in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as |
| 14 | Excating supply and filling of eath including royality and leading up to 5 km and compacting mechanically ….complete |
| 15 | Providing and laying in cement concrete 1:4:8 with Stone ballast including all materials, labours T&P etc . |
| 16 | Rcc work with cement approved coarse sand and 2 cm gauge approved stone grith in 1:1.5:3proportation for slab , |
| 17 | Thermo mechanically treated bars of grade Fe500D or more in rcc work |
| 18 | foundation footing base of column etc |
| 19 | column piller piers and struts etc |
| 20 | lintel beams plinth beams and cantilivers etc |
| 21 | suspended floor roof landing balconies and cantiliver etc |
| 22 | m-150 brick work in 1:6 cement and coarse sand in foundation and plinth including supply of all material ,labour and t$p etc. required for proper completion of work In foundation |
| 23 | m-150 brick work in 1:6cement and coarse sand in foundation and plinth including supply of all material ,labour and t$p etc. required for proper completion of work in super structure |
| 24 | 12mm thick cement plaster with 1:4 cement and sand mortor on fair side of wall including all material, labours, T&P etc all complete. |
| 25 | 40mm thick 1:2:4 plain cement concrete floor, laid in panels finished with 3mm floating coat of neat cement of cement and marble dust in ration 5:1 including all materials, labours, T&P etc all complete. |
| 26 | painting with distempering two or more coat DSR 13.41 |
| 27 | Painting Steel work with Deluxe Multi Surface Paint to give an even shade. Two or more coat applied @ 0.90 ltr/ 10 sqm over an under coat of primer applied @ 0.80 ltr/ 10 sqm of approved brand and manufacture |
| 28 | P/F on wall face unplasticised Rigid PVC rain water pipes conforming to IS: 13592 Type A Including jointing with seal ring confrming to IS :5382 leaving 10 mm gap for thermal expansion (I) single socketed pipes. |
| 29 | supply and fixing rolling shutter of approved maker made a required size M.S. lathe interlocked togetrher their entire length …...................80x1.25 mm M.S. laths with 1.25 mm thick top cover complete |
| 30 | providing and fixing ball bearing for rolling shutter |
| 31 | LESS DUE TO DEPARTMENT WORKING 5% |
| 32 | LABOUR CESS 1% Please Enable Macros to View BoQ information |