| 1 | Clearing jungle including uprooting of rank vegetation grass, brush wood, trees, and sapling of girth upto 30cm meausred at height of 1m above ground level and removal of rubbish upto a distance of 50m outiside the pheriphery of the area cleared. |
| 2 | Earth work in excavation by manual means in trenches for foundations, drains, pipes, cables etc. (Not exceeding 1.5mtr in width) and for shafts, wells, cesspits and the like not exceeding 10Sqm on plan, including dressing of site and ramming of bottoms lift upto 1.5mtr. including getting out excavated Earth and disposal of surplus excavated earth as directed. All kinds of soil. 1 meter from cutting edge |
| 3 | Earth work in excavation by mechnical means(Hydraulic Excavator) in trenches for foundations, drains, pipes, cables etc. (Not exceeding 1.5mtr in width) and for shafts, wells, cesspits and the like not exceeding 10Sqm on plan, including dressing of site and ramming of bottoms lift upto 1.5mtr. including getting out excavated Earth and disposal of surplus excavated earth as directed within a lead of 15 meter. All kinds of soil. |
| 4 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundation etc. in Layers not exceeding 20cm in depth |
| 5 | Pumping out water caused by springs, tidal or river seepage, broken water mains or drains and the like. |
| 6 | Dismantling manually/ mechanically including stacking of serviceable material and disposal of unserviceable material within 50metres lead: As per direction of Engineer In-charge |
| 7 | Water bound macadam road |
| 8 | Bituminous road |
| 9 | Dismantling GI pipes (external work) incl. excavation and refilling trenches after taking out pipes manually/ by mechanical means incl. stacking of pipes within 50 metres Lead. |
| 10 | 15mm to 40 mm nominal bore |
| 11 | Above 40mm nominal bore |
| 12 | Deployment of extra fitters/ mazdoor for restoration of damaged GI pipes, locating/ traces of blockages/ leakages including barricadding works on different occassions. |
| 13 | Fitter |
| 14 | Mazdoor |
| 15 | Laying & Fitting of GI pipes (all classes complete excluding cost of pipes, fittings and Earth work. |
| 16 | 15mm dia G.I Pipe |
| 17 | 20mmdia G.I Pipe |
| 18 | 25mm dia G.I Pipe |
| 19 | 32mm dia G.I Pipe |
| 20 | 40mm dia G.I Pipe |
| 21 | 50mm dia G.I Pipe |
| 22 | 65mm dia G.I Pipe |
| 23 | 80mm dia G.I Pipe |
| 24 | 100mm dia G.I Pipe |
| 25 | 150mm dia G.I Pipe |
| 26 | Fixing/ replacement of CI Sluice valves complete with bolts, nuts, rubber insertions etc. (Sluice Valves to be supplied by the department) |
| 27 | 150mmф |
| 28 | 100mmф |
| 29 | 80mmф |
| 30 | 65mmф |
| 31 | 50mmф |
| 32 | Fixing/ replacement of GM Gate valves/ Non Return Valves complete (Gate Valves/ Non Return Valves to be supplied by the department) including bends, collars, unions & other allied items |
| 33 | 150mmф |
| 34 | 100mmф |
| 35 | 80mmф |
| 36 | 65mmф |
| 37 | 50mmф |
| 38 | 40mmф |
| 39 | 25mmф |
| 40 | Making connection of GI distribution branch with GI Main of following sizes by providing & fixing Tee, including cutting & threading the pipe etc complete |
| 41 | 25 to 40mm nominal bore |
| 42 | 50 to 80mm nominal bore |
| 43 | Welding including transportation of plant at site etc complete. |
| 44 | By Gas Plant |
| 45 | By Electric Plant |
| 46 | Demolishing cement concrete manually/bymechanical means incuding disposal of material with in 50 meters lead as per direction of Engineer In-charge |
| 47 | a. 1:3:6 Mix or Richer mix (i/c equivalent design mix) |
| 48 | b. 1:4:8 Mix orLeaner mix (i/c equivalent design mix) |
| 49 | white washing with lime to give and even shade old work (two or more coats) |
| 50 | Painting with synthetic enamel paint of approved and manufactured of required colour to give an even shade two or more codes on old works |
| 51 | Providing and laying in position cement concrete of specified grade including curing but exluding the cost of centring and shuttering. All work upto plinth level with. |
| 52 | 1:1.5:3 (1 :cement: 1.5 Coarse sand: 3 graded stone aggregate 20mm nominal size) |
| 53 | 1:2:4 (1 :cement: 2 Coarse sand: 4 graded stone aggregate 20mm nominal size) |
| 54 | 1:3:6 (1 :cement: 3 Coarse sand: 6 graded stone aggregate 20mm nominal size) |
| 55 | 1:4:8 (1 :cement: 4 Coarse sand: 8 graded stone aggregate 40mm nominal size) |
| 56 | Steel Reinforcement for R.C.C work including straightening, cutting, bending, Placing in position and bending all complete thermo mechanically treated bars. |
| 57 | Providing and fixing1mm thick M.S. steel door with frame of 40×40×6 mm angle iron and 3mm M.S. guest plates at the junction and corners all necessary fittings complete including applying a primary coat of approved steel primer using square and central cross piece flats 30×6mm for diagonal braces. |
| 58 | 12mm cement plaster of mix 1:6 (I cement: 6 course sand) |
| 59 | Repair of rods of Slucie valves and gate valves by way of rethreading, making of nut of different dia (complete job) |
| 60 | 150mm dia |
| 61 | 100mm dia |
| 62 | 80mm dia |
| 63 | 65mm dia |
| 64 | 50mm dia |
| 65 | 40mm dia |
| 66 | Hire Charges of Generator 250KVA include cost of service of operating staff and supply of lubricating oiL, including transportation of Generator at site. |
| 67 | Demolishing of brick work manually/mechanically incl. stacking of serviceable material and disposal of unserviceable material with in 50m lead (in cement mortar) |
| 68 | Removing mortor from bricks and cleaning bricks incl. stacking with in lead of 50m (Stacks of cleaned bricks shall be measured from brickwork in cement mortar. |
| 69 | Brick work FPS of class designation 75 in foundation and plinth 1:6 cement mortar |
| 70 | Supply of Stones |
| 71 | Carriage of G.I pipe by Mechanical transport for an average distance of 1KM including loading, unloading and stacking |
| 72 | Carriage by Mechanical transport for an average distance of 1KM including loading, unloading and stacking |
| 73 | Stone Aggregate below 40mm nominal size |
| 74 | Stone Aggregate above 40mm nominal size |
| 75 | Soling Stone |
| 76 | Dismentling of tile work in floors and roofs laid in cement mortar including stacking material within 50mteter lead. |
| 77 | For Thickness of tiles 10mm to 25mm |
| 78 | For Thickness of tiles above 25mm and upto 40mm |
| 79 | Centering and shuttering including sturtting propping etc and removal of form for: |
| 80 | Foundations, Footings, Bases of column etc for mass concrete |
| 81 | Walls (any thickness ) including all pilasters, buttresses, plinth and string courses etc |
| 82 | Suspended Floors, roofs, landing balconies and Access platforms |
| 83 | Lintel Beams, Plinth Beams, Girders, Bressumers and Cantilevers |
| 84 | Columns, Pillars, Piers, Abutments, post and Struts |
| 85 | Finishing Walls with water proofing cement paint of required shade:old work (one of more coats applied @ 2.20 kg/10sqm) complete |
| 86 | Hand packing stones in wire-crates, excluding cost of crates and stones. |
| 87 | Dumping stone excluding cost of stone in Horizontal on level |
| 88 | Engagement of tractor-trolley water tanker for providing drinking water to water stressed areas including cost of POL, hire charges inclusive of salary of Driver, all toll taxes, token and other taxes applicable upto 10KM distance |
| 89 | Support Activity: Awaring people by printing of flexes, recording of Audio, Video song complete Job, for educating people in Samba District, organising seminar and providing refreshment etc complete job for invited people , DDC Chairman, BDC Chairman and all members. Seminar meeting and taking audio video, photography, printing of pamphlet and literature for delivery to the attending audience and oil for generator ( 10 Ltrs.) and hiring vehicle as Jal Rath.Complete job on turn key basis |
| 90 | Note :- (1) If any item/ items not advertised in the above rate list but found necessary to be executed at site. The same shall be paid as per SSR 2022 on Contractors Appreciation / Depreciation. Please Enable Macros to View BoQ information |