| 1 | Replacement of S.S. Seal Beam plate of Spillway Gate No.6: - |
| 2 | Putting of stop logs in front of spillway gate, stopping excessive leakage of water from the stop logs by inserting suitable packings/sand between stop logs after lifting of Spillway gate by the department |
| 3 | Cutting of damaged/worn-out bottom Seal Base S.S. plate as per the direction of Engineer-in-Charge. |
| 4 | Cutting of damaged/worn-out MS plate of cross-section 150mmx20mm as per the direction of Engineer-in-Charge. |
| 5 | Demolishing of RCC manually / by mechanical means, strengthening and stacking of steel bars and disposal of unserviceable material upto lead of 2 kms as per the direction of Engineer-in-Charge. |
| 6 | Providing and fixing of new MS plate of cross-section 150mm x 20mm including threads (as per drawing) and levelling the same complete in all respects as per the direction of Engineer-in-Charge. |
| 7 | Providing and fixing of anchoring bolts M16x450mm in the threaded holes of MS plate as per the direction of Engineer-in-Charge. |
| 8 | Providing and fixing of 1 no. new S.S bottom Seal Beam plate grade 304 having cross-section 125mm x16mm onto the MS plate by continuous welding on both sides and making the surface smooth by grinding complete in all respects as per the direction and complete satisfaction of Engineer-in-Charge. |
| 9 | Providing and fixing of epoxy resin bonding agent Sikadur -32 cement concrete. |
| 10 | Providing and laying of micro concrete grade M-60 with quick setting compound for damp condition. |
| 11 | Replacement of seals of Spillway Gate No.6: - |
| 12 | Dismantling of old damaged / deteriorated rubber seals of the Spillway gate by cutting / removing counter sunk screws, dismantling of flat strip and after dismantling making seal base surface smooth/even by scrapping, cleaning, welding, grinding, complete in all respects as per the direction of Engineer-in-charge. |
| 13 | Removing old paint from steel and other metal surfaces & making the surface even and smooth - 50% with hand scrapping & 50% with flame cleaning |
| 14 | Painting two coats with ready mixed Zinc rich primer, Berger make, on steel galvanized iron/ steel works |
| 15 | Painting two coats excluding primer coat with coal tar epoxy paint, Berger make, on previously painted steel/metal surface with brushing to give an even shade including cleaning the surface of all greases, dirt, dust and other foreign matter etc. |
| 16 | Providing and fixing 1 No. bottom flat Neoprene Rubber seal of cross-section W100 mm x D16 mm (Lion make) along with seal packings to prevent any leakage of water from the gate complete in all respects as per the direction of Engineer-in-charge. |
| 17 | Providing and fixing 2 No. side Solid bulb J-type Neoprene Rubber seals with Teflon coating of size øD:50mm x W:100 mm xT:16 mm (as per drawing) Lion make along with seal packings to prevent any leakage of water from the gate as per the direction of Engineer-in-charge. |
| 18 | Providing and fixing of MS Flat of cross-section 65mmx12mm with tapper holes as per site complete in all respects as per the direction of Engineer-in-charge. |
| 19 | Providing and fixing of 360 No. (90x2+180) Allen pan head counter sunk bolts of size øD:18mm x H:40 mm complete in all respects as per the direction of Engineer-in-charge. |
| 20 | Extraction of Spillway Stop Logs and removal of silt / muck deposited in the stop log gates during extraction of stop log gates (under water) and cleaning and preparing surface even smooth of stop log gates to the entire satisfaction of Engineer-in-charge. Please Enable Macros to View BoQ information |