| 1 | Dismantalling of pole for GO switches & Do fuse unitDismantalling of exising double pole structure ( only single pole dismantled for making arrangement for GO & DO fuse unit ) 50 % of Erection. |
| 2 | Erection of pole for GO switches & Do fuse unit:- Digging of pit , Fixing of Stay Rod, Filling of pit and Nozzling and tighting Complete in all respect as directed by the Engineer-In-Charge including all types of risk & incedental at site |
| 3 | Erection of Stay Set (H.T) new/ uprooted:- Digging of pit , Fixing of Stay Rod, Filling of pit and Nozzling and tighting Complete in all respect as directed by the Engineer-In-Charge including all types of risk & incedental at site |
| 4 | Erection of GO & DO fuse unit:- Erection, fitting & commissioning of 11 KV GO switch units with DO fuse units at various tapping points of 11 KV Jhatingri Thaltukhod Feeder |
| 5 | Dismantalling of 11 KV HT Line with ACSR/AAAC 50/55 mm2 :- De-Stringing and removell of conductor from Insulator Complete in all respects as directed by Engineer-In-Charge including all types of lead lift and other incidental Etc. |
| 6 | Erection of 11 KV HT Line with ACSR/AAAC 50/55 mm2 :- Re-Stringing and re-Sagging and Binding with Insulator Complete in all respects as directed by Engineer-In-Charge including all types of lead lift and other incidental Etc. |
| 7 | Sagging of GI Wire:- Re-Stringing and re-Sagging and Binding with Insulator Complete in all respects as directed by Engineer-In-Charge including all types of lead lift and other incidental Etc. |
| 8 | Erection of Earthing (H.T):- Digging of pit , Fixing of G.I. wire to the Earth System , and Filling of pit Complete in all respect as directed by the Engineer-In-Charge including all types of risk & incedental at site |
| 9 | Erection of LT Distribution Box:- Erection , testing & commissioning of LT distribution box for 11/0.4 KV , 25 KVA DTR (MCCB 100 A, 3P 25kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 10 | Erection , testing & commissioning of LT distribution box for 11/0.4 KV , 63 KVA DTR (MCCB 100 A, 3P 35kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 11 | Erection , testing & commissioning of LT distribution box for 11/0.4 KV , 100 KVA DTR (MCCB 160 A, 3P 35kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 12 | Manual carriage of GI wire muffs, X-arms , stay set ,stay wire & other allied material form road head to site of work with average lead 1 Km |
| 13 | Transprotation charges |
| 14 | Material Part: - Prov. GI wire for continuous earthing of 11 KV Jhatingri Thalukhod Feeder |
| 15 | Prov. GO Switch Switch unit |
| 16 | Prov. DO Fuse Unit |
| 17 | Prov.X-Arm (Channel Iron (100x50x6 mm),Length:2800 mmx 2 Nos) |
| 18 | Prov.X-Arm (Channel Iron (75x40x6 mm),Length:2800 mmx 4 Nos) for Supporting D.O.fuse Unit & G.O.Switch |
| 19 | Prov.Disc.Insulator Sets (Comprising 1 No Disc. (Porcelain, BS, 12 KV ,90 KN) including Dead End Clamps etc.) |
| 20 | Prov.R.C.C.Muff with Concrete filling |
| 21 | Prov. H.T.Stay Set Complete in all respects |
| 22 | Prov. Stay Wire (7/3.15 mm) (10.0 Kg Per Stay Set) |
| 23 | Prov.Alluminium Paint |
| 24 | LT distribution box for 11/0.4 KV , 25 KVA DTR (MCCB 100 A, 3P 25kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 25 | LT distribution box for 11/0.4 KV , 63 KVA DTR (MCCB 100 A, 3P 35kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 26 | LT distribution box for 11/0.4 KV , 100 KVA DTR (MCCB 160 A, 3P 35kA, ICS=100% ICU,Kit-Kat 200 Amps) |
| 27 | Prov.L.T. Cable (3.5 Core) 25 mm2 |
| 28 | Prov.L.T. Cable (3.5 Core) 70 mm2 |
| 29 | Prov.L.T. Cable (3.5 Core) 95 mm2 |
| 30 | Prov. Nuts & Bolts of various Sizes(Galvanised)/Coated) 16 mm Φ or more ( With flat and spring washer) |
| 31 | Prov. Alluminium thimble 70mm2 |
| 32 | Prov. Alluminium thimble 120 mm2 |
| 33 | Prov. Alluminium thimble 185 mm2 |
| 34 | Prov. Full Clamps |
| 35 | Prov. Half Clamps |
| 36 | Prov.H.T.Earthing Set Complete Please Enable Macros to View BoQ information |