| 1 | Earth work in bulk excavation by mechanical means (hydraulic excavator) over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 m2 on plan) including disposal of excavated earth lead upto 50 meters and lift upto 1.5 m, as directed by Engineer-in-Charge. All kinds of soil : |
| 2 | Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts,wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth anddisposal of surplus excavated earth as directed, within a lead of 50 metres: All kinds of soil : |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering.All works upto plinth level with: 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40 mm nominal size). |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering.All works upto plinth level in 1:3:6 (1 cement: 3 coarse sand: 6 graded stone aggregate 20mm nominal size) with 20% Stone . |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs having slope upto 15°, landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases upto five level including curing but excluding the cost of centring, shuttering, finishing and reinforcement with 1:1½:3 (1 cement : 1½ coarse sand : 3 graded stone aggregate 20 mm nominal size) |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level Thermo-Mechanically Treated bars of grade Fe-500D or more. |
| 7 | Providing and laying damp-proof Course 50 mm thick with cement concrete 1:2:4 (1 cement:2 coarse sand: 4 graded stone aggregate 20 mm nominal size) and curing complete. |
| 8 | Dry random rubble masonry with hard stone in foundation and plinth: Without bond stone. |
| 9 | Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: Cement mortar 1:6 (1 Cement : 6 coarse sand). |
| 10 | Dumping stone including cost of stones in Horizontal on level |
| 11 | Centering and shuttering including strutting, propping etc. and removal of form work for: Foundations, footings, bases for columns. |
| 12 | Carriage of materials by mechanical transport including loading / unloading and stacking complete. Sand / aggregate Avg lead up to 5 kms . |
| 13 | Carriage o fstone Avg lead up to 4 km by MT Please Enable Macros to View BoQ information |