| 1 | Construction of embankment with approved material obtained from R.O.W. with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 2 | Construction of granular sub-base by providing close graded material , spreading in uniform layers with motor grader on prepared surface , mixing by mix in place method with rotavator at OMC , and compacting with vibratory rollar to achieve the desired density , complete as per clause 401 ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 3 | Providng & laying , spreading and compacting stone aggregates of specific sizes (45-63mm S.S.B.) to water bound macadam specification including spreading in uniform thickness , hand packing , rolling with smooth roller 80-100 KN in stage to proper grade and camber , applying and brooming , crushable screening to fill-up the interstices of coarse aggregate , watering and compacting to the require density grading 2 as per Technical Specification Clause 405. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 4 | Providng & laying , spreading and compacting stone aggregates of specific sizes (22.4-53 mm S.S.B) .to water bound macadam specification including spreading in uniform thickness , hand packing , rolling with smooth roller 80-100 KN in stage to proper grade and camber , applying and brooming , crushable screening to fill-up the interstices of coarse aggregate , watering and compacting to the require density grading 3 as per Technical Specification Clause 405.. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 5 | Brick edging on both side of the road with 1st class bricks laid on edge with mud mortar including Cost of all labour materials T&P etc . Complete. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 6 | Providing and applying primer coat with bitumen slow setting emulsion on prepared surface of granular base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.as per technical specification clasue 502. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 7 | Providing and applying tack coat with bitumen VG-10 pressure distributor at the rate of 0.30 kg. Per sqm on the prepared granular surface treated with primer & cleaned with Hydraulic broom as per Technical Specification Clasue 503. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 8 | Providing, laying and rolling of open - graded premix surfacing of 20 mm thickness composed of 13.2 mm. to 11.2 mm aggregates either using penetration grade bitumen or emulsion to required line. Grade and level to serve as wearing coarse on a perviously prepared base, including mixing in suitable plant , laying and rolling with a three wheeled 80-100 KN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clasue 508. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 9 | Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C seal coat as per Technical Spefification Clause -510. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 10 | Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from ROW with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 11 | Earth work in excation in foundation in ordinary soil . As per S.I.No 251 ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 12 | C.C. With 6:3:1 cement fine sand and 40 mm stone ballast in foundation as per ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 13 | C.C. With 4:2:1 cement fine sand and 40 mm stone ballast in foundation as per ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 14 | Providing and laying of 600 mm dia NP-3 hume pipe medium duty confirm to IS 458:2003 including collars/spigot jointed with dtiff mixture of cement in the proportion of 1:2 (1cement:2 fine sand) including testing of joints, all taxes, transportation charges & contractor's profit etc complete. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 15 | Providing and laying of 350 mm dia NP-3 hume pipe medium duty confirm to IS 458:2003 including collars/spigot jointed with dtiff mixture of cement in the proportion of 1:2 (1cement:2 fine sand) including testing of joints, all taxes, transportation charges & contractor's profit etc complete. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 16 | First class brick work with 1:6 cement and coarse sand mortar in foundation as per S.I.No.305 b ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 17 | Struct cement pointing with 1:2 cement & Fine sand mortar as per S.I.No. 574. ( Including all material & T&P etc. complete. & Excluding cost of GST) |
| 18 | 15mm thick plaster with cement mortor consinting of 1 part cement and 4 part of apporved coarse sand Minimum thickness not be less than 10 mm including supply of all materials babour and T&P etc |
| 19 | Maintainance cost :- Maintainance cost will be paid year wise as per Government order No. 17/2024/SA.-113/23-1-2024-23-1099/113/2023 Date 16.01.2024 and HQ UPPWD,Lucknow order No. 3689COPRMC/ Mul-23-24 Date 17.02.2024 |
| 20 | 1st year- maintainance cost 0% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 21 | 2nd year- maintainance cost 0.75% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 22 | 3rd year- maintainance cost 1.50 % on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 23 | 4th year- maintainance cost 2.25% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) |
| 24 | 5th year- maintainance cost 3.00 % on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST) Please Enable Macros to View BoQ information |