| 1 | (Erection/Labour Part ) TS No.- 37/2024-25, WBS-D-24-3316 |
| 2 | Erection of S/T pole 11 mtr long, (Single pole) with RCC muff Including digging of pit of size 1.10x0.75x1.50, drilling of holes in poles, X-bracing set, X-arms, Fixing of insulators, X-arms, X- bracing set, fixing of barbed wire, Danger plate, filling of pit & ramming and painting of pole complete in all respects(C.C. 1:3:6 for muffing will be provided by the contractor). |
| 3 | Erection of S/T pole 9 mtr long, (Single pole) with RCC muff Including digging of pit of size 1.10x0.75x1.50, drilling of holes in poles, X-bracing set, X-arms, Fixing of insulators, X-arms, X- bracing set, fixing of barbed wire, Danger plate, filling of pit & ramming and painting of pole complete in all respects(C.C. 1:3:6 for muffing will be provided by the contractor). |
| 4 | Erection of Earthing set comprising digging of pit, fixing of GI wire to the earth system,and filling of pit complete in all respects. |
| 5 | Erection of stay set, comprising digging of pit, fixing of stay rod, filling of pit, Nozzeling and tightining complete in all respects. |
| 6 | Sagging of conductor 1 KM single GI wire, , comprising laying of Conductor, stringing & sagging, binding with insulator complete in all respects. |
| 7 | Erection of ACSR 50 mm² such as stringing, tensioning and sagging,jointing and fastening . |
| 8 | Erection of HT Line ACSR 50 mm² such as stringing, tensioning and sagging,jointing and fastening . |
| 9 | Erection charges of cable termination kit |
| 10 | Erection charges of GO AB Switch |
| 11 | Erection charges of Bus bar |
| 12 | Dismantle Charges of ACSR 6/1/2.11 mm Conductor |
| 13 | Dismantle Charges of PCC Poles |
| 14 | Mannual carriage & Transportation Charges of complete Material |
| 15 | (Supply Part) |
| 16 | ACSR 6/1/3.35 mm (50 mm²) {Includes 3 conductor lengths for 3Φ and Additional 1% (Sag, Jumpering and wastage)} |
| 17 | Steel Tubular Poles (9 m, Working Load > 227 kgf/m²) (with Ruling Span 90 m, 8 No. Run thro' and 3 No. Double Pole Dead End Structures) |
| 18 | Steel Tubular Poles (11 m, Working Load > 227 kgf/m²) (with Ruling Span 90 m, 8 No. Run thro' and 3 No. Double Pole Dead End Structures) |
| 19 | Muffs (2000mm) with concerete filling |
| 20 | Channel Iron (75x40x4.8) [Length- 1.50 Mtr + 0.2 Mtr] |
| 21 | Prov. XLPE Cable 3.5x120mm2 |
| 22 | Shackle Insulator (16 kN) |
| 23 | D-Iron (U- Clamps) with nut and bolts |
| 24 | Earth Knob |
| 25 | Stay set complete in all respect (i/c Stay Clamp) (1No. / Single Pole , 4 No. / Double Pole Structures) |
| 26 | Stay Wire (7/3.15 mm) (10.0 kg Per Stay Set) |
| 27 | Earthing set complete |
| 28 | Single Continous Earth wire (GI, 8 SWG) {alongwith 2 wire lengths for avg. one road crossing @ 20 m and Additional 3% (Sag, Earthing, Cross lacing above road and wastage)} @ 0.102 kg/m |
| 29 | Half clamps: [On Double Pole Dead End structure: 4 No; On Run Thro' structure: 2 No ] |
| 30 | Full clamps: [On Double Pole Dead End structure: 4 No, Single Pole Run Thro' structure: 2 No] |
| 31 | Nuts and Bolts of Various Sizes (Galvanised / Coated) [Preferably 16 mm Φ or more (with flat and spring washers)] |
| 32 | Aluminium Paint |
| 33 | Spiral PVC Spacer Please Enable Macros to View BoQ information |