| 1 | Providing and fixing of 1 phase 2 wire, 415V, 1no of 100 Amps incoming DP MCCB (Breaking Capacity 25kA) fitted with outgoing 04 No 32 Amps SP MCBs for Service Connections, Distribution Service Pillar suitable for outdoor installation , made out of CRCA sheet painted through 7-tank process with PU painted Busbars 2P, Aluminium with heat shrinkable sleeves and adequate capacities complete with all accesories 4 way Distribution Service Pillar. |
| 2 | Providing & fixing of Support Galvanised angle frame and legs (40mm x 40 mm x 3 mm) for Distribution Feeder Pillar with leg height 1m with 0.3m in soil approx [email protected] per mtr . |
| 3 | Providing and Laying of Cement grouting for support angle legs |
| 4 | Supply, installation, testing & Commissioning of 70 mm² Two Core Cable,1.1kV Grade, Armoured, XLPE Insulated Stranded Conductor FRLS type |
| 5 | Providing & fixing of Earthing Complete by GI Pipe 40 mm 3mtr long through GI Strip 25x3 mm |
| 6 | Providing & fixing of Support GI Channel cross-arm (100 x 50x6mm) / 75x40x40 x6mm including back clamps of 50X8 mm for fixing Cross arm and pole top bracket |
| 7 | Supply, installation, testing & Commissioning of 185mm.sq S/C Cable, 1.1kV Grade,Un-armoured, XLPE insulated stranded conductor FRLS |
| 8 | Supply, installation, testing & Commissioning of 11KV Link Set (Post Type) Heavy Duty, Suitable for 400 - 630 Amp current capacity (IS: 9920 (Part-I to IV)) |
| 9 | Supply, installation, testing & Commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A |
| 10 | Supply, installation, testing & Commissioning of Al Thimbles of Sizes |
| 11 | Supply, Loading, Transportation, insurance, Unloading, Carriage and Delivery at Site and erection of 8 Mtr. Long ST Poles with pit excavation [IS 2713 410 SP 15] |
| 12 | Supply, Loading, Transportation, insurance, Unloading, Carriage and Delivery at Site and Laying of 0.05 ACSR Conductor |
| 13 | Supply, installation, testing & Commissioning of Galvanized Nuts and Bolts of sizes. |
| 14 | Providing & fixing of Earthing Complete by GI Pipe 40 mm 3mtr long through GI Strip 25x3 mm |
| 15 | Supply, installation, testing & Commissioning of LT Fuse Set 3 Phase +1 N |
| 16 | Supply, installation, testing & Commissioning of 16 KN Polymer Shackle Insulator LT |
| 17 | Supply, installation, testing & Commissioning of GI Mukey clamps with GI U/ D - back Clamps of 50*8 mm flat iron |
| 18 | Installation, transportation loading and unloading for 63KVA /100KVA DTs available with the deptt and Dismentalling after completion of work and returned to Divisional store |
| 19 | Operation maintenance of LT UG Cabling for the entire Period of Yatra including Charging of LT Panels |
| 20 | Providing and Carriage of Chain Pulley Block 3MT |
| 21 | Pre and Post Geo tagged Photographic Evidence consisiting of 5x7 inch Photographs and Autocad Single Line Diagram Please Enable Macros to View BoQ information |