| 1 | Earthwork in all kinds of soil in excavation of foundation trenches for columns, basement, tie beams, walls and steps in all kinds of soil including moorum, hard stoney earth and earth mixed with boulders except sheet rocks and boulders requiring blasting with all leads and lifts including dressing and leveling the bed sides up to required depth and depositing the excavated materials at places away from the work site with all leads and lifts, T&P for shoring, shuttering, dewatering if required etc. complete as per the drawing, designing including cost of all labour, T&P etc. as required for the work complete as directed by the Engineer-in-charge. |
| 2 | Supplying and filling in foundation and plinth with river Sand in layers including watering and rammed with cost, conveyance and royality of sand etc complete. |
| 3 | Supplying all labour, materials, T&P for Cement Concrete (1:3:6) in foundation using 4 cm size hard granite Crusher Broken metal including cost of materials, royalty & conveyance charges with watering, curing all complete as per direction of Engineer-in-charge |
| 4 | First class Fly Ash brick work in cement mortar (1:6) in foundation and plinth with best quality bricks having crushing strength from 75kg/cm2 to 99kg/cm2, immersing the bricks in water for not less than 6 hours before use (the bricks shall be well burnt, free from cracks, well shaped, uniform in size and shall produce a clear metallic ringing sound when struck) includes moulding, chamfering, corbelling etc. complete as per drawing, design and specification, watering and curing for 7 days including cost, conveyance, royalty and taxes of all materials, labour, T&P etc. and as per direction of Engineer-in-charge. |
| 5 | R.C.C work of prop M20 having minimum compressive strength (in work test) 200kg/cm2 in 15cm cubes at 28days after mixing and test conducted in accordance with I.S. 456 and I.S. 516using 12mm to 20mm size (1/2\\" to \\") crusher broken hard black granite chips of 20mm size (not to exceed 25%) of approved quality & from approved quarry including hosting, lowering, laying and compacting concrete with vibrator, watering and curing for 28days, cost of rigid and smooth centering & shuttering and finishing to exposed surface smooth providing, grooves or beads wherever necessary as per direction of the Engineer in charge including cost, conveyance, royalties & taxes of all materials and cost of all labour, T&P etc as required for the work completion in all respects as per direction of Engineer in charge but excluding cost of M.S rod/Tor steel and binding wires and labour charges for bending, binding wires and labour charges for bending, binding and tying the grills. |
| 6 | Column |
| 7 | Plinth Band |
| 8 | Straightening, cutting, bending and binding, welding and jointing (if necessary) coiled/ bent up MS Rods Tor Steel/deformed rods etc. including hoisting, placing in position, tying the grills binding with 18 to 20 gauge binding wire required for R.C.C work including cost, conveyance, taxes of all materials, cost of all labour. T&P etc. as required for the work complete (weight of binding wire will not be considered) as directed by Engineer-in-charge. (Payment will be made on actual weight of M.S rods or Tor steel linear measurements of rod for finished item of works. 5% wastage and lap length are included in the finished rate). |
| 9 | First class Fly Ash brick work in cement mortar (1:6) in Super Structure with best quality bricks having crushing strength from 75kg/cm2 to 99kg/cm2, immersing the bricks in water for not less than 6 hours before use (the bricks shall be well burnt, free from cracks, well shaped, uniform in size and shall produce a clear metallic ringing sound when struck) includes moulding, chamfering, corbelling etc. complete as per drawing, design and specification, watering and curing for 7 days including cost, conveyance, royalty and taxes of all materials, labour, T&P etc. and as |
| 10 | Supplying, Transporting, fitting and fixing M.S. Fabricated Grill as per approved specification and direction of Engineer in-Charge. |
| 11 | Providing 16mm thick plaster in C.M. (1:6) over Brick masonry work racking out the joints finished smooth to proper line and plumb, watering and curing for 7days with cost, conveyance, royalty, taxes of all materials, cost of all labour. T&P etc. complete as per direction of the Engineer-In-Charge. |
| 12 | Providing & laying cement concrete of prop. (1:2:4) in foundation bed and floors using 12mm nominal size down graded, screened, washed hard black crusher broken granite Chips of approved quality & from approved quarry cluding laying in the layers not exceeding 150 mm thick, hoisting, lowering, laying, watering and curing etc. complete to the required levels including cost, conveyance, royalty and taxes of all materials, cost of all labour, T&P etc. as required for the work complete and as per direction of Engineer-in-charge. |
| 13 | Rigid smooth centring and shuttering for R.C.C. works Including false work and dismantling then after casting including cost of materials all complete. (R.C.C. Foundation, Plinth Band, Footings, Column Base, Mass Concrete & Precast Slabs) |
| 14 | Construction of Cement Conrete Kerb Stone with Top & Bottom width 115mm and 165mm respectively, 250mm high in M-30grade 300x300x150 size PCC on M-10grade foundation on 150mm thick, foundation having 50mm projection beyond Kerb Stone, Kerb stone laid with Kerb concrete foundation Machine, laid laying mannually, including Centering&Shuttering completed as per Clause No-408 of MORT&H specifications for Road&Bridge works(Latest revision) and as per direction etc. all of Engineer. |
| 15 | Providing & laying of concrete paver block (60cm thick) of different size M-30 grade of concrete over 50mm thick compacted sand layer including cost, conveyance & royalty of all materials etc. |
| 16 | Earth filling from boro pit ordinary soil within the 5 km lead and lift including and depositing the same at work site and spreading the same as per proper level etc. all complete as directed by the Engineer-in-charge. |
| 17 | Cement Washing Two coats on plaster surface incl. Watering curing etc. |
| 18 | Priming one coat on plaster surface incl. Cost of primer etc. |
| 19 | Weather Seal Coat Paint two coat on plaster surface incl. Cost of Weather seal coat Paint etc. |
| 20 | Painting two coats with approved Enamel Paint on grill work on one coat of primer incl. Cost of paint Primer etc. |
| 21 | Supplying, Fitting & fixing Cement Concrete Bnech at the side Play Ground including cost, conveyance & royalty of all materials etc. (Four Seater Concrete Chair) |
| 22 | Mural Painting Two coat on plaster surface including all cost etc. |
| 23 | Supplying veriated small tree and bushes as per direction of site incharge etc. |
| 24 | Supplying, Fitting & Fixing Transporancy Board Please Enable Macros to View BoQ information |